Q4: A) A 3-phase, 50 Hz, 400 V motor develops 100 H.P. (74-6 kW), the power factor being 0.75 lagging and efficiency 93%. A bank of capacitors is connected in delta across the supply terminals and power factor raised to 0-95 lagging. Each of the capacitance units is built of 4 similar 100 V series capacitors. Determine the capacitance of each capacitor. B) Give a reasonable justification to (two) of the following: 1- The receiving end voltage increased at lightly load. 2- The voltage drop consideration is relatively unimportant in design of feeder 3- In most industrial factories, the power factor is lagging.

Delmar's Standard Textbook Of Electricity
7th Edition
ISBN:9781337900348
Author:Stephen L. Herman
Publisher:Stephen L. Herman
Chapter29: Dc Generators
Section: Chapter Questions
Problem 1PA: You are working as an electrician in a large steel manufacturing plant, and you are in the process...
icon
Related questions
Question
Q4: A) A 3-phase, 50 Hz, 400 V motor develops 100 H.P. (74-6 kW), the power factor
being 0.75 lagging and efficiency 93%. A bank of capacitors is connected in delta across
the supply terminals and power factor raised to 0-95 lagging. Each of the capacitance units
is built of 4 similar 100 V series capacitors. Determine the capacitance of each capacitor.
B) Give a reasonable justification to (two) of the following:
1- The receiving end voltage increased at lightly load.
2- The voltage drop consideration is relatively unimportant in design of feeder
3- In most industrial factories, the power factor is lagging.
Transcribed Image Text:Q4: A) A 3-phase, 50 Hz, 400 V motor develops 100 H.P. (74-6 kW), the power factor being 0.75 lagging and efficiency 93%. A bank of capacitors is connected in delta across the supply terminals and power factor raised to 0-95 lagging. Each of the capacitance units is built of 4 similar 100 V series capacitors. Determine the capacitance of each capacitor. B) Give a reasonable justification to (two) of the following: 1- The receiving end voltage increased at lightly load. 2- The voltage drop consideration is relatively unimportant in design of feeder 3- In most industrial factories, the power factor is lagging.
Expert Solution
steps

Step by step

Solved in 7 steps with 1 images

Blurred answer
Knowledge Booster
Lag, Lead and Lead-Lag Compensator
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Delmar's Standard Textbook Of Electricity
Delmar's Standard Textbook Of Electricity
Electrical Engineering
ISBN:
9781337900348
Author:
Stephen L. Herman
Publisher:
Cengage Learning