Q1: Draw the arrow diagram for the following activities and show the critical path: activity duration Pervious Follow A B,C B 4 D,E A F,G D B H. E 4 H,I F 8 H,I G 3 K,J H D,E,F E,F K I 4 K,J J 4 G,I M,N K 3 G,H,I L L K J 4 J L,M P 1 CS Scanned with CamScanner

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Q1: Draw the arrow diagram for the following activities and show the critical path:
activity
duration
Pervious
Follow
A
B,C
D,E
4
A
7
A
F,G
D
В
H.
E
4
H,I
F
H,I
G
K,J
D,E,F
K
4
E,F
K,J
J
G,I
G,H,I
4
M,N
K
L.
L.
K
M
J
4
J
P
6.
L,M
1
CS Scanned with CamScanner
M52
Transcribed Image Text:Q1: Draw the arrow diagram for the following activities and show the critical path: activity duration Pervious Follow A B,C D,E 4 A 7 A F,G D В H. E 4 H,I F H,I G K,J D,E,F K 4 E,F K,J J G,I G,H,I 4 M,N K L. L. K M J 4 J P 6. L,M 1 CS Scanned with CamScanner M52
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Site plan requirements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning