Question 2 A company is planning to produce televisions for home use. The activities necessary to built an experimental model and related data are given in the following table: Time (weeks) Cost (dollars) Immediate Feasible Time Crash Activity Normal Crash Normal Crash Predecessors Reduction cost/week A 3 2 1000 1400 В 2 1 2000 2500 C 1 1 300 300 D 3 1 1200 1600 A E 3 875 1100 В F 2 1 4400 5000 C G 4 3 1600 1950 D, E H 1 1 1000 1000 F, G What is the project completion date and critical path? Crash the project to 9 weeks at the least cost by drawing the AON networks and explaining а. b. crashing costs for each reduction weeks. Determine the total project cost after crashing. с.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Question 2
A company is planning to produce televisions for home use. The activities necessary to built an experimental
model and related data are given in the following table:
Time (weeks)
Cost (dollars)
Crash
Immediate
Feasible Time
Crash
Activity
Normal
Crash
Normal
Predecessors Reduction
cost/week
A
3
2
1000
1400
В
2
1
2000
2500
C
1
1
300
300
D
3
1
1200
1600
A
6.
3
875
1100
В
F
1
4400
5000
C
G
4
3
1600
1950
D, E
H
1
1
1000
1000
F, G
а.
What is the project completion date and critical path?
b.
Crash the project to 9 weeks at the least cost by drawing the AON networks and explaining
crashing costs for each reduction weeks.
с.
Determine the total project cost after crashing.
Transcribed Image Text:Question 2 A company is planning to produce televisions for home use. The activities necessary to built an experimental model and related data are given in the following table: Time (weeks) Cost (dollars) Crash Immediate Feasible Time Crash Activity Normal Crash Normal Predecessors Reduction cost/week A 3 2 1000 1400 В 2 1 2000 2500 C 1 1 300 300 D 3 1 1200 1600 A 6. 3 875 1100 В F 1 4400 5000 C G 4 3 1600 1950 D, E H 1 1 1000 1000 F, G а. What is the project completion date and critical path? b. Crash the project to 9 weeks at the least cost by drawing the AON networks and explaining crashing costs for each reduction weeks. с. Determine the total project cost after crashing.
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Employee turnover
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.