Question 3: Yiğit Çınar is developing a program with a number of activities that must be completed. The activities, immediate predecessors, expected times and variances given in the table below. Activity Immediate Pred. Time (days) A 2 1/9 B 5 1 3 1/9 D В 10 1 E A, D 1/3 F C 1/9 G Е, F 8 1/3 Questions: Develop an AON (Activity On Node) network for this problem. What is the earliest start, earliest finish, latest start and latest finish (ES, EF, а. b. LS, LF) times for all activities? What is the completion time of the project? What is variance and standard deviation of critical path? What is the probability of completion the project on the completion time? Which activities are slack activities? If we have 3 days delay in activity D what will be the new completion time с. d. е. f. g. of the project? 2.

Understanding Business
12th Edition
ISBN:9781259929434
Author:William Nickels
Publisher:William Nickels
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
icon
Related questions
Question

Can you solve this question as fast as possible please

Question 3: Yiğit Çınar is developing a program with a number of activities that must be
completed. The activities, immediate predecessors, expected times and variances given in the
table below.
Activity
Immediate Pred.
Time (days)
A
2
1/9
В
5
1
C
3
1/9
10
1
E
А, D
2
1/3
F
C
1/9
G
Е, F
8
1/3
Questions:
Develop an AON (Activity On Node) network for this problem.
What is the earliest start, earliest finish, latest start and latest finish (ES, EF,
а.
b.
LS, LF) times for all activities?
What is the completion time of the project?
What is variance and standard deviation of critical path?
What is the probability of completion the project on the completion time?
с.
d.
е.
f.
Which activities are slack activities?
g.
If we have 3 days delay in activity D what will be the new completion time
of the project?
Transcribed Image Text:Question 3: Yiğit Çınar is developing a program with a number of activities that must be completed. The activities, immediate predecessors, expected times and variances given in the table below. Activity Immediate Pred. Time (days) A 2 1/9 В 5 1 C 3 1/9 10 1 E А, D 2 1/3 F C 1/9 G Е, F 8 1/3 Questions: Develop an AON (Activity On Node) network for this problem. What is the earliest start, earliest finish, latest start and latest finish (ES, EF, а. b. LS, LF) times for all activities? What is the completion time of the project? What is variance and standard deviation of critical path? What is the probability of completion the project on the completion time? с. d. е. f. Which activities are slack activities? g. If we have 3 days delay in activity D what will be the new completion time of the project?
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Layout strategy
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Management Information Systems: Managing The Digi…
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
Business Essentials (12th Edition) (What's New in…
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
Fundamentals of Management (10th Edition)
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON