Practice Question EVM: A simple project consists of five tasks and is scheduled to take 13 weeks to complete. The actual status of the project at the end of week 9 is given in the following table: Project Plan Task Duration Start Actual status Percent Actual current cost complete S350 S225 $475 End Budget (weeks) week week 3. $300 100% 100% $250 $450 $600 2 2 C 4 4 7 100% 9. S300 75% 8 13 S500 $300 75% a) For each activity, compute the ACWP, BCWP, BCWS and add the columns to get the projected total. Record your answers in the table below. Task ACWP BCWP BCWS D

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Practice Question EVM:
A simple project consists of five tasks and is scheduled to take 13 weeks to complete. The actual
status of the project at the end of week 9 is given in the following table:
Project Plan
Task | Duration Start
(weeks)
Actual status
Actual
current cost complete
S350
S225
$475
$300
End
Budget
Percent
week week
$300
100%
100%
$250
$450
$600
$500
B
2
100%
75%
75%
C
4
4
7.
9.
13
D
3
6
8
$300
a) For each activity, compute the ACWP, BCWP, BCWS and add the columns to get the
projected total. Record your answers in the table below.
Task
ACWP
BCWP
BCWS
E
b) Calculate: CV,SV,CPI, and SPI:
Transcribed Image Text:Practice Question EVM: A simple project consists of five tasks and is scheduled to take 13 weeks to complete. The actual status of the project at the end of week 9 is given in the following table: Project Plan Task | Duration Start (weeks) Actual status Actual current cost complete S350 S225 $475 $300 End Budget Percent week week $300 100% 100% $250 $450 $600 $500 B 2 100% 75% 75% C 4 4 7. 9. 13 D 3 6 8 $300 a) For each activity, compute the ACWP, BCWP, BCWS and add the columns to get the projected total. Record your answers in the table below. Task ACWP BCWP BCWS E b) Calculate: CV,SV,CPI, and SPI:
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.