Questions 1. Organize the information above in an activity precedence table showing the activity, precedent and duration (calculated using the PERT weighted average formula and round to the nearest integer). 2. Draw an AON network diagram and calculate its early start, early finish, late start and late finish times, floats (Free and total) for each activity. Make sure you fully label all nodes in the network. 3. Identify the project's critical path and its length.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
An IT project manager of ABC Company has developed an activity list for the purpose of
tracking employees' daily activities on the project. The project's schedule is considered to be of
high risk due to the possibility of sabotage by some of the employees. In addition, the IT project
manager has gathered time information for each activity, as shown in the table below. Consider
the following project's tasks and their identified best, likely, and worst case estimates of task
duration. Assume the organization computes PERT weight average based on the standard
formula.
Activity Optimistic Most
Pessimistic
likely
A
25
В
3
8
C
7
8
D
4
4
E
10
19
34
F
14
18
G
16
20
H
32
44
65
I
12
17
25
J
2
8
18
The dependencies between the
activities listed in the table above are as follows:
The project starts with two activities-A, and B-which can be done concurrently.
When activity A is finished, activity C can start
When activity B is finished, activities D and E can start
When both activities C and D are finished, activity F can start
When activity E is finished, activity G can start
When activity F is finished, activity H can start
When both activities G and H are finished, activity I can start
When activity G is finished, activity J can start
The project is complete when activities I and J are finished
Questions
1. Organize the information above in an activity precedence table showing the activity, precedent
and duration (calculated using the PERT weighted average formula and round to the
nearest integer).
2. Draw an AON network diagram and calculate its early start, early finish, late start and late
finish times, floats (Free and total) for each activity. Make sure you fully label all nodes in the
network.
3. Identify the project's critical path and its length.
Transcribed Image Text:An IT project manager of ABC Company has developed an activity list for the purpose of tracking employees' daily activities on the project. The project's schedule is considered to be of high risk due to the possibility of sabotage by some of the employees. In addition, the IT project manager has gathered time information for each activity, as shown in the table below. Consider the following project's tasks and their identified best, likely, and worst case estimates of task duration. Assume the organization computes PERT weight average based on the standard formula. Activity Optimistic Most Pessimistic likely A 25 В 3 8 C 7 8 D 4 4 E 10 19 34 F 14 18 G 16 20 H 32 44 65 I 12 17 25 J 2 8 18 The dependencies between the activities listed in the table above are as follows: The project starts with two activities-A, and B-which can be done concurrently. When activity A is finished, activity C can start When activity B is finished, activities D and E can start When both activities C and D are finished, activity F can start When activity E is finished, activity G can start When activity F is finished, activity H can start When both activities G and H are finished, activity I can start When activity G is finished, activity J can start The project is complete when activities I and J are finished Questions 1. Organize the information above in an activity precedence table showing the activity, precedent and duration (calculated using the PERT weighted average formula and round to the nearest integer). 2. Draw an AON network diagram and calculate its early start, early finish, late start and late finish times, floats (Free and total) for each activity. Make sure you fully label all nodes in the network. 3. Identify the project's critical path and its length.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.