a. Draw a precedence diagram using AOA , AON and Gantt chart. b. Find the critical path using CPM. c. Determine the expected length of the project.
Q: What characteristic(s) of the critical path times makes them critical? What two factors are compared…
A: Critical path activities are those that, if delayed, will cause the project's completion to be…
Q: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C.…
A: Network diagram as per given information:
Q: advise a person or a company to use Gantt and PERT charts. Differentiate between the 2.
A: THE ANSWER IS AS BELOW:
Q: A) Draw the Gantt Chart B) Draw the Network Diagram C) Identify and draw the critical path using the…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: a) What are the activities on the critical path (using the letters provided) b) What is the shortest…
A: We are allowed to do first three sub-parts only. The answer is as below:
Q: What project scheduling tool expands and contracts to share the right information to the right…
A: Schedule Variance An Schedule Variance denotes how much ahead or behind schedule a project is. By…
Q: a. Construct the network diagram for this project. b. Determine the earliest and latest start times…
A: Below is the solution:-
Q: a. Draw the CPM Network b. What is the critical path c. What will the scheduled (earliest…
A: In the question, we have Activity Table data, this table data includes activity ID, Immediate…
Q: Which of the following activities is not part of defining a project?a. The project triangleb. The…
A: An organization has numerous projects running at a time and numerous projects in the pipeline to be…
Q: Three recent college graduates have formed a partnership and have opened an advertising firm. Their…
A: Precedence DiagramThe precedence diagram is as shown in the diagram below:
Q: 1. Organize the infomation above in an activity precedence table showing the activity, precedent and…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: Draw the project PDM. b. Determine the critical path. c. Calculate the total slack time. а.
A: In this question, I would first determine the expected activity time for each activity, based on the…
Q: 1. Jim's team has completed the WBS and WBS dictionary and the stakeholders have approved the…
A: The correct option is "d", which is "DECOMPOSITION". Decomposition would involve dividing the…
Q: a. Draw a project network b. Identify the critical path c. Develop the activity schedule for the…
A: A project schedule network diagram shows the tasks that are to be performed in the defined sequence.…
Q: Construct a network diagram for the project. a. b. What are the project completion time and the…
A: Honor Code: Since you have posted a question with multiple subparts, we have solved the first three…
Q: (1) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: (a) Draw a project netvork. (Submit a file vith a maximum size of 1 MB.) Browse. No file selected.…
A: A project schedule network diagram shows the sequential and analytical association between tasks in…
Q: A project manager has compiled a list of major activities that will be required to install a…
A: A manager wants to put in a computer data system within the company. The activity, immediate…
Q: a) Draw an AON diagram of the project, including activity durations. b) Define the critical path,…
A: In project management, there are two types of networks. One is AON and the second is AOA. AON…
Q: A project consists of ten activities as detailed below. Draw an A-O-A diagram representation for the…
A: A-O-A Network Diagram :
Q: a. Draw the precedence diagram. b. What is the probability that the project can be completed in 24…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: m- the network diagram of one of the projects and its data as in Table No. (4), so if I want to…
A: Below is the solution:-
Q: (a) Based on the information in Table 1, draw a complete AON precedence diagram to illustrate the…
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: Q4. Answer the following questions (a-h), based on the provided project Gantt Chart. The red line…
A: Note: Since you have posted a question with multiple sub-parts, we will solve first four sub-parts…
Q: When developing a Work Breakdown Structure (WBS) for a project, your team can organize the second…
A: A work breakdown structure is a project structure method where the components, activities, and…
Q: A project manager has compiled a list of major activities that will be required to install a…
A:
Q: Construct a Network Diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: a) Construct a Gantt chart using MS Project 2016 b) Assuming the default 5-day workweek, calculate…
A: This question is related to the topic of Project Management and this topic falls under the…
Q: . CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL…
A: Activity-on-node is a therm related to project management. It directs to a precedence diagramming…
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: For each activity, we have immediate predecessor data and Time in days, using the above table,…
Q: Which one is NOT a basic output of a PM network analysis? Select one: a. Identification of the…
A: One of the important tools that are widely used in project management is network analysis. It is…
Q: i. Calculate the expected time for each activity ii. Draw a Gantt Chart from the same information…
A: As per Bartleby guidelines we can only solve first 3 sub par Below is the solution:-
Q: PERT could be used to answer which of the following management questions? A. Can we delay a…
A: Project management scheduling contains a list of a project related activities and deliverables,…
Q: Table 1 Time (In Days) 9. Activities Immediate Predecessors A -- В A 5 A 9 B,C E В, С 7 F D 10 G E…
A: There are following table shows the activities, times and sequences required for the project…
Q: cts to implement in project man
A: To be a good project manager, one must have a wide range of abilities. It requires a variety of…
Q: What does Goldratt's Critical Chain explain? Select one: a. Theory of Constraints for better…
A: The theory of constraints is a theory that consists of principles that can be used in eliminating…
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A:
Q: The activities related to a project with their immediate predecessors are given as follows: Activity…
A: Given data is
Q: A. (5 points) Draw AON diagram of the project, including activity durations. B. (4 points) Based on…
A:
Q: (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File no file…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: a. Draw the network diagram b. What is the critical path? c How many dayswill it take to complete…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Dave is the project manager for a construction project that is building a gazebo. When the project…
A: Since the project absolutely must be completed in 7 months for it to be worth doing, the deadline is…
Q: a. Prepare/draw a full Gantt Chart as at end of Week 5. b. Calculate and indicate the missing (?)…
A: Part a:
Q: Use the Program Evaluation and Review Technique to represent the project in an activity network. In…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: The following table contains a list of activities, with precedence requirements and crash costs. All…
A: Based on the table data,specifically Data like activity ID, Normal time and predecessor data, we…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 4 images
- Your hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed in 18 weeks, before the next Joint Commission survey. Project activity times are listed in the table that is attached as an image. a) Draw the network diagram.b) Identify all project paths. Which path is the critical path and why?c) What is the project completion time and total project costs if only normal times are used? ActivityThe fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in Chicago, their durations, and what activities each must precede: a) Draw an AOA diagram of the project, including activity durations.b) Define the critical path, listing all critical activities in chronological order.c) What is the project completion time (in weeks)?d) What is the slack (in weeks) associated with any and all noncritical paths through the project?The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis. a. Draw the network diagram for the project below. b What is the critical path and completion time for the project? c. Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration. Activity Normal Time Crash Time Normal Cost Crash Cost Predecessor A 10 7 2,000 2,600 B 12 8 1,500 2,000 A C 16 12 2,200 3,000 A D 8 7 2,500 3,000 B E 12 9 1,950 2,275 C F 9 8 800 1,000 D G 24 29 3,650 4,000 E, F H 17 14 1,200 1,800 G
- 3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the nodenumbers in circles and draw arrows from node to node, labelling each arrow with theactivity letter and estimated duration. 3.2 Identify all the paths on the network diagram and note how long they are. 3.3 What is the critical path for this project and how long is it? 3.4 What is the shortest possible time needed to complete the project?The conditions and pert times for constructing a network diagram are given below.-Creation conditions:(0-1) It is the initial activity.(1-2) and (1-3) Activities begin together.It follows activity (2-4) (1-2), activity (3-4) (1-3), and ends together.( 4-5 ) It is the last activity. a-Create the network diagram.b-Calculate the critical path and show it on the diagram.c- If the expiry time is extended by 15 days, how much will the probability of expiry increase?Suppose you are a project manager, and you have to manage a project with activities and their respective durations in weeks as listed in Table below. Construct a precedence network diagram to analyze your project. please do it hand written
- GreenzTech Inc. is planning on installing a new computerised accounting system. For thisproject, they have established the following activities, precedence relationships, and timeestimates in weeks:a. Draw the network diagramb. Calculate the expected time for each activity.c. Calculate the variance of each activityd. Based on the calculation of estimated times, what is the critical path?e. What is the estimated time of the critical path?f. What is the activity variance along the critical path?g. What is the probability of completion of the project within 50 weeks or less?Draw a network representation of the project (nodes = activities, arrows = precedence constraints). Provide early start/early finish as well as late start/late finish times for all activities. What is the duration of the project, and which tasks are on the critical path? Task Description Duration Predecessors A Project Planning 16 days - B Evaluation Existing Apps 20 days - C Define Value Proposition 12 days B D Define User Interface 18 days B E Define Technology Requirements 22 days C and D F Document Requirements 14 days E G Develop Architecture 35 days A and F H Creation Code Design 18 days G I Roadmap Feature Development 12 days G J User Interface Development 74 days H and I K Code Development 92 days H and I L Release Testing 32 days J and K M Get User Feedback 22 days L N Bug Fixing 28 days L O Marketing Plan 54 days E P Release Product 5 days M, N and OJanice Eliassen must complete the activities in the following table to fin ish her consulting project. a) Draw the appropriate PERT diagram.b) Find the critical path and project completion time.c) Find the probability that the project will take more than49 time periods to complete.
- The managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries. This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table. What is the probability that project can be completed two months early?Given the following table, construct a network diagram, either AOA or AON. Times are in days.a. Determine the expected duration of the project.b. Compute the probability that the project will take at least 18 days.Path Activity Time EstimatesA 4-5-6Top B 7-8-10C 3-5-9D 7-8-11Bottom E 2-3-4F 1-4-6b) Draw the project’s Gantt chart c) Change the time of at least two activities that can reduce the overall project duration, draw the new critical path and the new Gantt chart