Shown below are the tasks, times, and precedence requirements for the work required to assemble a copier machine. Production time per day = 480 minutes. Desired output per day = 40 units. TASK TASK TIME, mins |IMMEDIATE PREDECESSOR/S A 10 11 5 в A B D 4 B E 12 A F 3 С, D G 7 F H 11 E 3 G, H ΣΤt 6

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question

You may use either clustering or heuristics in assigning tasks to workstations

1. How many workstations should be set up in this production line?

2.Which tasks should be performed in each workstation?

3. Draw the diagram of the production line.

Thank you for your help!

Shown below are the tasks, times, and precedence requirements for the work required
to assemble a copier machine. Production time per day = 480 minutes. Desired output
per day = 40 units.
TASK TASK TIME, mins IMMEDIATE PREDECESSOR/S
A
10
B
11
A
5
B
4
B
E
12
A
F
3
С, D
G
7
F
H
11
E
I
3
G, H
ΣTt 66
Transcribed Image Text:Shown below are the tasks, times, and precedence requirements for the work required to assemble a copier machine. Production time per day = 480 minutes. Desired output per day = 40 units. TASK TASK TIME, mins IMMEDIATE PREDECESSOR/S A 10 B 11 A 5 B 4 B E 12 A F 3 С, D G 7 F H 11 E I 3 G, H ΣTt 66
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,