Smooth Chin Device Company The Smooth Chin Device Company is a manufacturer of high-end electric razors. These razors are produced using a machine-paced process. For each razor, a tray with components enters the process at the beginning of a conveyor belt. The tray then passes through the six steps (consisting of various tasks) explained in the table below. Workers perform the assembly operations on the moving tray. The last step consists of an inspection of the then fully assembled razor. The activity times of the process are as follows:   There are six workers, one at each of the six stations (A-F). They begin their workday at 8:00 a.m. and work steadily until 4:00 pm. (They are replaced with other workers for breaks and lunches, but the production is not slowed or stopped during these times.) Their hourly wage rate is $25 per hour. You can assume unlimited demand. What is the process capacity (you can ignore any start-up or empty system effects), in razors/hour?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Smooth Chin Device Company

The Smooth Chin Device Company is a manufacturer of high-end electric razors. These razors are produced using a machine-paced process. For each razor, a tray with components enters the process at the beginning of a conveyor belt. The tray then passes through the six steps (consisting of various tasks) explained in the table below. Workers perform the assembly operations on the moving tray. The last step consists of an inspection of the then fully assembled razor. The activity times of the process are as follows:

 

There are six workers, one at each of the six stations (A-F). They begin their workday at 8:00 a.m. and work steadily until 4:00 pm. (They are replaced with other workers for breaks and lunches, but the production is not slowed or stopped during these times.) Their hourly wage rate is $25 per hour. You can assume unlimited demand.

What is the process capacity (you can ignore any start-up or empty system effects), in razors/hour?

Station
A
Preparation
B
Assembly 1
C
Assembly 2
D
Assembly 3
E
Assembly 4
F
Inspection
Tasks
1.
2.
Lay out chassis [12 sec]
Lay out screws [15 sec]
3. Lay out all other components [17 sec]
Total time for A: 44 sec
4. Perform task AS1 [10 sec]
5. Perform task AS2 [10 sec]
6. Perform task AS3 [20 sec]
Total time for B: 40 sec
7. Perform task AS4 [14 sec]
8. Perform task AS5 [16 sec]
9. Perform task AS6 [20 sec]
10. Perform task AS7 [5 sec]
Total time for C: 55 sec
11. Perform task AS8 [30 sec]
12. Perform task AS9 [30 sec]
Total time for D: 60 sec
13. Perform task AS10 [11 sec]
14. Perform task AS11 [19 sec]
15. Perform task AS12 [20 sec]
Total time for E: 50 sec
16. Inspect electrics [20 sec]
17. Inspect aesthetics [20 sec]
Total time for F: 40 sec
Transcribed Image Text:Station A Preparation B Assembly 1 C Assembly 2 D Assembly 3 E Assembly 4 F Inspection Tasks 1. 2. Lay out chassis [12 sec] Lay out screws [15 sec] 3. Lay out all other components [17 sec] Total time for A: 44 sec 4. Perform task AS1 [10 sec] 5. Perform task AS2 [10 sec] 6. Perform task AS3 [20 sec] Total time for B: 40 sec 7. Perform task AS4 [14 sec] 8. Perform task AS5 [16 sec] 9. Perform task AS6 [20 sec] 10. Perform task AS7 [5 sec] Total time for C: 55 sec 11. Perform task AS8 [30 sec] 12. Perform task AS9 [30 sec] Total time for D: 60 sec 13. Perform task AS10 [11 sec] 14. Perform task AS11 [19 sec] 15. Perform task AS12 [20 sec] Total time for E: 50 sec 16. Inspect electrics [20 sec] 17. Inspect aesthetics [20 sec] Total time for F: 40 sec
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.