Standards Direct materials Direct labor Variable overhead (per direct labor-hour). Fixed overhead (per month) Expected activity (direct labor-hours) Actual results Direct material (purchased and used) Direct labor Variable overhead Fixed overhead Units produced (actual) Direct materials Direct labor Variable overhead Fixed overhead Price Variance F F K4 Required: a. Prepare a variance analysis for each variable cost for each product b. Prepare a fixed overhead variance analysis for each product. Note: For all requirements, Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option. F КА -0.75 pounds at $8.00 per pound 1.25 hours at $26.00 per hour $21.20 $ 416,400 17,350 Efficiency Variance F F 10,300 pounds at $7.40 per pound 14,800 hours at $26.30 per hour $ 331,060 $ 386,740 12,200 units Production Volume Variance Price Variance F 1 pound at $8.60 per pound 1.50 hours at $30 per hour $ 23.00 $ 493,500 23,500 14,200 pounds at 18.90 per pound 22,300 hours at $32.60 per hour $464,212 $ 490,840 14,500 units Efficiency Variance X7 F F Production Volume Variance

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter9: Standard Costing: A Functional-based Control Approach
Section: Chapter Questions
Problem 33P: Business Specialty, Inc., manufactures two staplers: small and regular. The standard quantities of...
icon
Related questions
Topic Video
Question
Robinwood Fixtures manufactures two products, K4 and X7. The company prepares its master budget on the basis of standard costs.
The following data are for September:
Standards
Direct materials
Direct labor,
Variable overhead (per direct labor-hour)
Fixed overhead (per month)
Expected activity (direct labor-hours)
Actual results
Direct material (purchased and used)
Direct labor
Variable overhead
Fixed overhead
Units produced (actual)
Direct materials
Direct labor
Variable overhead
Fixed overhead
Price Variance
F
F
KA
-0.75 pounds at $8.00 per pound
1.25 hours at $26.00 per hour
$ 21.20
K4
$ 416,400
17,350
Required:
a. Prepare a variance analysis for each variable cost for each product.
b. Prepare a fixed overhead variance analysis for each product.
Note: For all requirements, Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for
favorable, or "U" for unfavorable. If there is no effect, do not select either option.
10,300 pounds at $7.40 per pound
14,800 hours at $26.38 per hour
$ 331,060
$ 386,740
12,200 units
Efficiency Variance
Production Volume
Variance
Price Variance
1 pound at $8.60 per pound
1.50 hours at $30 per hour
$ 23.00
F
$493,500
23,500
14,200 pounds at $8.90 per pound
22,300 hours at $32.60 per hour
$ 464,212
$ 490,840
14,500 units
X7
Efficiency Variance
F
F
F
Production Volume
Variance
Transcribed Image Text:Robinwood Fixtures manufactures two products, K4 and X7. The company prepares its master budget on the basis of standard costs. The following data are for September: Standards Direct materials Direct labor, Variable overhead (per direct labor-hour) Fixed overhead (per month) Expected activity (direct labor-hours) Actual results Direct material (purchased and used) Direct labor Variable overhead Fixed overhead Units produced (actual) Direct materials Direct labor Variable overhead Fixed overhead Price Variance F F KA -0.75 pounds at $8.00 per pound 1.25 hours at $26.00 per hour $ 21.20 K4 $ 416,400 17,350 Required: a. Prepare a variance analysis for each variable cost for each product. b. Prepare a fixed overhead variance analysis for each product. Note: For all requirements, Do not round intermediate calculations. Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option. 10,300 pounds at $7.40 per pound 14,800 hours at $26.38 per hour $ 331,060 $ 386,740 12,200 units Efficiency Variance Production Volume Variance Price Variance 1 pound at $8.60 per pound 1.50 hours at $30 per hour $ 23.00 F $493,500 23,500 14,200 pounds at $8.90 per pound 22,300 hours at $32.60 per hour $ 464,212 $ 490,840 14,500 units X7 Efficiency Variance F F F Production Volume Variance
Expert Solution
steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Excel Applications for Accounting Principles
Excel Applications for Accounting Principles
Accounting
ISBN:
9781111581565
Author:
Gaylord N. Smith
Publisher:
Cengage Learning