Question
Stylo Beb Sdn. Bhd. needs to schedule 2 of their designers (Harry & Ryan) onto their next 3 projects
(A, B & C). Harry and Ryan each have 80 hours to split between the projects. The following table
shows each designer's capability score for each project, along with the minimum number of hours re-
quired for each project:
Project A Project B Project C
Harry
85
70
15
Ryan
65
65
60
Hours Required
55
25
75
Help Stylo Beb by formulating a Linear Program that maximises total capability.
Transcribed Image Text:Stylo Beb Sdn. Bhd. needs to schedule 2 of their designers (Harry & Ryan) onto their next 3 projects (A, B & C). Harry and Ryan each have 80 hours to split between the projects. The following table shows each designer's capability score for each project, along with the minimum number of hours re- quired for each project: Project A Project B Project C Harry 85 70 15 Ryan 65 65 60 Hours Required 55 25 75 Help Stylo Beb by formulating a Linear Program that maximises total capability.
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,