You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table below. Your interest is in minimizing the cost of the project to the community center. Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) START 0 0 0 0 A 8 50 6 290 START B 7 40 3 360 START C 3 1 290 B I D 6 3 290 A, C E 4 30 4 30 A, C F 5 80 4 210 B G 10 50 8 130 D H 11 60 9 120 E, F FINISH 0 0 0 0 G, H a. Using the normal times for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times is days. (Enter your response as an integer.) 70 20

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
please answer within 30 minutes with detailed explanation and calculation.
You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the
start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional
cost. Time and cost data for your project are contained in the table below. Your interest is in minimizing the cost of the project
to the community center.
Activity
Normal Time
(days)
Normal Cost ($)
Crash Time
(days)
Crash Cost ($)
Immediate
Predecessor(s)
START
0
0
0
0
A
8
50
6
290
START
B
7
40
3
360
START
с
3
70
1
290
B
D
6
20
3
290
A, C
E
4
30
4
30
A, C
F
5
80
4
210
B
G
10
50
8
130
D
H
11
60
9
120
E, F
FINISH
0
0
0
0
G, H
a. Using the normal times for each activity, what is the earliest date you can complete the project?
The corresponding project duration using the normal times is days. (Enter your response as an integer.)
Transcribed Image Text:You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table below. Your interest is in minimizing the cost of the project to the community center. Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) START 0 0 0 0 A 8 50 6 290 START B 7 40 3 360 START с 3 70 1 290 B D 6 20 3 290 A, C E 4 30 4 30 A, C F 5 80 4 210 B G 10 50 8 130 D H 11 60 9 120 E, F FINISH 0 0 0 0 G, H a. Using the normal times for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times is days. (Enter your response as an integer.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.