The contract Ledger of Alphas Co. revealed the following expenditure an account a contract on 31 Dec. 2012 Materials Plant Wages Expenses 2,10.000 70.000 2.93,000 15,000 10,000 Establishment charges The contract was started on 19 Jan, 12 and the contract price was 10.00,000. Cash received to date was 4,60.000 representing 80% of the work certified the remaining 20s being retained until completion. The value of plant on 31 Dec 2012 was 20.000 and the value of material on hand was 6.000. The cost of work finished but not Ceres on the said date was 50,000. Some of the materials. costing 20,000 were found unsuitable and were sold For 16,000 and a part of the plant costing & 5.000 unsuited to the contract nas sold at a profil of 1,000. In order to calculate the profit made on the contract to 31st Dec 12. the contractors estimated further expenditure that would be incurred in completing the contract and took to the credit of prof and Loss Account for the year that proportion of the estimated net profil to be realised on the contract which the value of work certified bare to the, contract price. The estimates were as under:

Financial Accounting Intro Concepts Meth/Uses
14th Edition
ISBN:9781285595047
Author:Weil
Publisher:Weil
Chapter8: Revenue Recognition, Receivables, And Advances From Customers
Section: Chapter Questions
Problem 48P
icon
Related questions
Question

The contract Ledger of Alphas Co. revealed the following expenditure an account a
contract on 31 Dec. 2012
Materials
Plani
Wages
Expenses
Establishment charges
2.93,000
15,000
10,000
The contract was started on 19 Jan, 12 and the contract price was 10,00,000. Cash received to
date was 4,60.000 representing 80% of the work certified the remaining 20s being ratained until
completion. The value of plant on 31 Dec 2012 was 20.000 and the value of material on hand was
6.000. The cost of work finished but NDT DER e cn the said date was 50,000.
Some of the materials. costing 20,000 were found unsuitable and were sold For 16,000 and a
part of the plant costing & 5.000 unsuited to the contract was sold at a profil of 1,000.
In order to calculate the profit made on the contract to 31st Dec 12, the contractors estimated
further expenditure that would be incurred in completing the contract and took to the credit of profit and
Loss Account for the year that proportion of the estimated net profil to be realised on the contract which
the value of work certified bare to the, contract price.
The estimates were as under :
(a) that the contract would be completed by 30th June 13
(b) then a further sum of 30,000 would have to bo spent on plant and the residual value of the plant
2,10,000
70.000
on the completion of the contract would
12,000.
(s) The materials in addition to those on hand on 31 Dec 2012, would cost € 1,00,000 and that further
Cundry expenses of 7,000 would be incurred.
(d) That the wagors on the contract for the six months to June 2013, would emount to 1,69,900.
(e) That the establishmont charges would cord the same amount per march as in the previous year.
(1) Thot 18.000 would bo sufficiont to meet the contingencies.
Prepare the contract account for the year onded 31 Dec 2012 and show your calculations of the profil
to be ciod tod to profil and Loss Account of the vam
Transcribed Image Text:The contract Ledger of Alphas Co. revealed the following expenditure an account a contract on 31 Dec. 2012 Materials Plani Wages Expenses Establishment charges 2.93,000 15,000 10,000 The contract was started on 19 Jan, 12 and the contract price was 10,00,000. Cash received to date was 4,60.000 representing 80% of the work certified the remaining 20s being ratained until completion. The value of plant on 31 Dec 2012 was 20.000 and the value of material on hand was 6.000. The cost of work finished but NDT DER e cn the said date was 50,000. Some of the materials. costing 20,000 were found unsuitable and were sold For 16,000 and a part of the plant costing & 5.000 unsuited to the contract was sold at a profil of 1,000. In order to calculate the profit made on the contract to 31st Dec 12, the contractors estimated further expenditure that would be incurred in completing the contract and took to the credit of profit and Loss Account for the year that proportion of the estimated net profil to be realised on the contract which the value of work certified bare to the, contract price. The estimates were as under : (a) that the contract would be completed by 30th June 13 (b) then a further sum of 30,000 would have to bo spent on plant and the residual value of the plant 2,10,000 70.000 on the completion of the contract would 12,000. (s) The materials in addition to those on hand on 31 Dec 2012, would cost € 1,00,000 and that further Cundry expenses of 7,000 would be incurred. (d) That the wagors on the contract for the six months to June 2013, would emount to 1,69,900. (e) That the establishmont charges would cord the same amount per march as in the previous year. (1) Thot 18.000 would bo sufficiont to meet the contingencies. Prepare the contract account for the year onded 31 Dec 2012 and show your calculations of the profil to be ciod tod to profil and Loss Account of the vam
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
College Accounting, Chapters 1-27 (New in Account…
College Accounting, Chapters 1-27 (New in Account…
Accounting
ISBN:
9781305666160
Author:
James A. Heintz, Robert W. Parry
Publisher:
Cengage Learning