The controller of ABC Company that produces face masks has requested a quick estimate of the manufacturing supplies needed for its plant for the month of April. When production is expected to be at 470,000 units. Their high-low method used in estimating manufacturing supplies determined that fixed costs part of expenses is P70,560 and the variable cost per unit is P1.45 per unit. How much is the estimated manufacturing supplies for April? P 652,500 P 681,500 P 749,180 P 752,060
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
The controller of ABC Company that produces face masks has requested a quick estimate of the manufacturing supplies needed for its plant for the month of April. When production is expected to be at 470,000 units. Their high-low method used in estimating manufacturing supplies determined that fixed costs part of expenses is P70,560 and the variable cost per unit is P1.45 per unit. How much is the estimated manufacturing supplies for April?
-
- P 652,500
- P 681,500
- P 749,180
- P 752,060
Step by step
Solved in 2 steps