The detail of the direct cost for project XYZ are given in Table 1. Table 1 Details for Project XYZ Normal Direct Cost Activity Predecessor Maximum Slope Time (day) crash time A B 100 A 3 150 100 50 A 4 200 1 D B C 3 200 200 150 1 60 E 4 F 70 90 D.E 1 The indirect cost is listed in Table 2. i If the project needs to be crashed from its initial time, T1 to T5, list the step-by-step changes in activity and the direct cost to crash the project in Table 2, ii. Identify the project's lowest cost possible within T1-T5 duration Table 2 Step Activity crashed Project Duration Total Direct Indirect Total Cost Cost Cost 1 Initial time T1 900 New time T2 800 New time T3 600 New time T4 550 New time T5 500 2344

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The detail of the direct cost for project XYZ are given in Table 1.
Table 1 Details for Project XYZ
Activity
Normal
Direct Cost
100
Predecessor
Maximum
Slope
Time (day)
1
3
crash time
A
A
150
100
A
200
1
50
4
3
B
200
1
60
E
C
4
200
2
70
F
D.E
3
150
1
90
The indirect cost is listed in Table 2.
i. If the project needs to be crashed from its initial time, T1 to T5, list the
step-by-step changes in activity and the direct cost to crash the project
in Table 2,.
ii. Identify the project's lowest cost possible within T1-T5 duration
Table 2
Activity
crashed
Project Duration
Step
Total Direct
Indirect
Total
Cost
Cost
Cost
1
Initial time T1
900
New time T2
800
New time T3
New time T4
600
4
550
New time T5
500
Transcribed Image Text:The detail of the direct cost for project XYZ are given in Table 1. Table 1 Details for Project XYZ Activity Normal Direct Cost 100 Predecessor Maximum Slope Time (day) 1 3 crash time A A 150 100 A 200 1 50 4 3 B 200 1 60 E C 4 200 2 70 F D.E 3 150 1 90 The indirect cost is listed in Table 2. i. If the project needs to be crashed from its initial time, T1 to T5, list the step-by-step changes in activity and the direct cost to crash the project in Table 2,. ii. Identify the project's lowest cost possible within T1-T5 duration Table 2 Activity crashed Project Duration Step Total Direct Indirect Total Cost Cost Cost 1 Initial time T1 900 New time T2 800 New time T3 New time T4 600 4 550 New time T5 500
Expert Solution
steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.