Question
  1. Construct a network diagram for this project?

TABLE 1:  Activities and duration project

                                                                          Duration in weeks

                                                              __________________________________

Activity        Proceeding activity     Optimistic       Most likely      Pessimistic

 

A                            -                                     2                         3                        3

 

B                             -                                   10                       12                      15

 

C                            A                                   4                           5                       8

 

D                            B                                  2                           2                        2

 

E                         A, D                                 3                          3                        3

 

F                           B                                    3                          4                       5 

 

G                       C, E, F                               8                         10                    20

 

                        G                                    2                          3                       5

 

I                           G                                    2                          2                       2

 

J                          H                                    4                           5                      10

 

K                        I, J                                   2                           4                      6

TABLE 1: Activities and duration project
Duration in weeks
Activity
Proceeding activity Optimistic
Most likely
Pessimistic
A
2
3
В
10
12
15
А
4
8
D
В
2
2
2.
А, D
F
B
4
С, Е, F
8
10
20
2
G
2
10
K
I, J
5.
3.
3.
3.
4.
Transcribed Image Text:TABLE 1: Activities and duration project Duration in weeks Activity Proceeding activity Optimistic Most likely Pessimistic A 2 3 В 10 12 15 А 4 8 D В 2 2 2. А, D F B 4 С, Е, F 8 10 20 2 G 2 10 K I, J 5. 3. 3. 3. 4.
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.