The network diagram below (activity on arrow) shows the activities needed to complete a project to tclose a seasonal resort after the summer season. The activities are listed as well as the time (in days) it will take to complete them. Note that the three times for each activity are displayed in the following order in the parentheses: optimistic, most likely, pessimistic. This reflects the underlying uncertainty in the activity times, and thus a probabilistic model is used. Use this information to find the expected time for each activity, as well as for each path. Also, calculate the standard deviation for each path (Please do this in Excel). Identify the critical path. Finally, discuss which path has the most uncertain completion time. Winterize Repair Pipes (1, 3, 7) Plumbing (2, 3, 8) Insulate Seal Windows (3, 4, 6) (4, 5, 7) 1 7 Reseal Pool Drain 4 (3, 4, 5) Swimming Pool Clean Pool Treat Pool (1, 2, 3) (1, 3, 4) (1, 4, 5)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Help?

The network diagram below (activity on arrow) shows the activities needed to complete a project to
close a seasonal resort after the summer season. The activities are listed as well as the time (in days) it
will take to complete them. Note that the three times for each activity are displayed in the following
order in the parentheses: optimistic, most likely, pessimistic. This reflects the underlying uncertainty in
the activity times, and thus a probabilistic model is used. Use this information to find the expected
time for each activity, as well as for each path. Also, calculate the standard deviation for each path
(Please do this in Excel). Identify the critical path. Finally, discuss which path has the most
uncertain completion time.
Winterize
Repair Pipes
(1, 3, 7)
2
Plumbing
(2, 3, 8)
Insulate
Seal Windows
(3, 4, 6)
(4, 5, 7)
3
7
Reseal Pool
Drain
4
(3, 4, 5)
6.
Świmming
Pool
Clean Pool
Treat Pool
(1, 2, 3)
(1, 3, 4)
(1, 4, 5)
1.
Transcribed Image Text:The network diagram below (activity on arrow) shows the activities needed to complete a project to close a seasonal resort after the summer season. The activities are listed as well as the time (in days) it will take to complete them. Note that the three times for each activity are displayed in the following order in the parentheses: optimistic, most likely, pessimistic. This reflects the underlying uncertainty in the activity times, and thus a probabilistic model is used. Use this information to find the expected time for each activity, as well as for each path. Also, calculate the standard deviation for each path (Please do this in Excel). Identify the critical path. Finally, discuss which path has the most uncertain completion time. Winterize Repair Pipes (1, 3, 7) 2 Plumbing (2, 3, 8) Insulate Seal Windows (3, 4, 6) (4, 5, 7) 3 7 Reseal Pool Drain 4 (3, 4, 5) 6. Świmming Pool Clean Pool Treat Pool (1, 2, 3) (1, 3, 4) (1, 4, 5) 1.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Product positioning
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.