Hourty rates vary for the consultant-client combination and are based on several factors, inciuding project type and the consultant's experience. The rates (dollars per hour) for each consultant-client combination are as follows: Client Consultant A B D Avery 100 125 115 100 Baker 120 135 115 120 Campbell 155 150 140 130 a Develop a network representation of the problem b. Formulate the problem as a linear program, with the optimal solution providing the hours each consultant should be scheduled for each client to maximize the consulting firm's billings What is the schedule and what is the total billing? c New information shows that Avery doesn't have the experience to be scheduled for client B. If this consuiting assignment is not permitted, what impact does it have on total billings? What is the revised schedule?
Q: Activity Duration Number of men 1-2 3 5 2-4 2 3 2-3 3 7 3-4 0 0 3-5 3 2 4-5 7 2…
A:
Q: The following table shows activities with duration, dependency, dependency type, and the number of…
A: Network diagram:
Q: The Advanced Tech Company has a project to design anintegrated information database for a major…
A:
Q: Develop a network representation of this problem. Formulate the problem as a linear program.
A: Linear programming is a mathematical technique that is also used in operations management…
Q: he table below show a set of activities of an IS project,its expected completion time (ET) and…
A: Network Diagram : Critical Path = A-B-C-D-G-H Project Completion time = 7+9+5+17+10+7 = 55
Q: estimate the work unit price and the work price.
A: From the given points in the question, the following conclusions can be drawn: 1- The number of days…
Q: A given task was estimated to cost $15,750 to complete. Currently, the project team has completed…
A: Given- Task completion cost (budgeted amount)= $15,750 % of project completion= 65% Expenditure…
Q: Consider a project that has been modeled as in the table below: a. Draw the PERT/CPM network for…
A: given,
Q: Construct a network diagram for the project. a. b. What are the project completion time and the…
A: Honor Code: Since you have posted a question with multiple subparts, we have solved the first three…
Q: A marketing firm is planning to conduct a survey of a segment of the potential product audience for…
A: Critical paths are indicated in red lines.
Q: A car manufacturing plant outlines a number of activities involved in its operations. The following…
A: Solution: Given data Days Immediate predecessors Activity a m b A 3…
Q: Consider Table 6-3. All duration estimates or estimated times are in weeks, and the network proceeds…
A: The question is related to Critical Path Analysis. The details are given regarding activities and…
Q: Dr. Ell has been given a budget of $10,000 to organize a conference at her university in 3 months'…
A: This question is related to the project management subject and It falls under the…
Q: The Mobicom Corporation is in the design phase of a system project. The project manager wants to…
A: ACTIVITY PRECEDING TIME[WEEKS A - 5 B - 6 C - 4 D A B 7 E C 8 F C, D 10 G D 8
Q: Widgetco is making a prototype of a new product. The product consists of two subassemblies. Before…
A: Linear programming can be referred to as a method of optimizing the problems within the given…
Q: following activities required to complete this project together with the time estimates and…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Given data is
Q: Using the information provided in the table, the network diagram and the project completion time =…
A: Project Crashing is decrease in the total duration for the completion of a project and are closely…
Q: The Advanced Tech Company has a project to design anintegrated information database for a major…
A:
Q: The Peabody Coal Corporation recently completed the final feasibility report for a new general…
A: Hi, since there are multiple questions, we will proceed with answering the first three questions…
Q: Use the following project status information to calculate each of the requested EVM numbers below.…
A: Task Budget Cost Duration % Complete Actual Cost Planned Value Earned Value =% complete *PV A…
Q: Project Management
A: given,
Q: Draw the network and answer the following questions. a. What is the project completion time?
A: Project network is the network that represents the relationship between activities and their…
Q: a. Formulate a linear program that can be used to determine the number of hours each graphic…
A: Solution a) Let X1 be the number of hours assigned to Lisa X2 be the number of hours assigned to…
Q: A project requires these activities to be completed and the table below shows the expected time and…
A: It can see that the cost variance is positive. While the scheduled variance is negative. The…
Q: A project consists of seven activities, lettered A through F below. For each activity, the estimated…
A: Given data is Steps for project crashing: Create the network diagram Find the path with the…
Q: The diagram below was developed for the project launch of Kitty Condo, a new product in the luxury…
A: Project paths Normal duration A-D-G 29 A-E-H 31 B-F-H 27 C-I-H 25 Critical…
Q: For the project detailed in the table below: a) Draw the Activity on Node (AON) network diagram…
A: Activity Immediate Predecessors Duration A - 4 B - 6 C A,B 7 D B 8 E B 5 F C 5 G D 7…
Q: Activities, preceding activities, normal and crashed completion times of each of the activities and…
A: Forward Pass: Early Start (ES) = Maximum EF value from immediate Predecessor(s) Early Finish (EF) =…
Q: ES_{end} = LF_{D} = FS_{D} = TS_{G} = IS_{G} =
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: The activities in the Jaffar Brothers project are as: Activity Immediate Predecessors Time…
A:
Q: Scott and Associates, Inc., is an accounting firm that has three new clients. Project leaders will…
A: LPP Formulation:
Q: The normal time, crash time, and cost estimates for the setup of a new produc tion line at Ithaca…
A: a. A-B-E-G: 5+4+4+2=15 A-C-E-G: 5+6+4+2=17 A-C-F-G: 5+6+5+2=18 (There is a mistake in the question,…
Q: Hoosier Burger Juan Rodriquez has assigned you the task of requirements determination for the…
A: a. Assume you are preparing the customer satisfaction questionnaire. What types of questions would…
Q: The client of a project has requested the project team to crash 8 hours of time. The table below…
A: The network diagram for the above network is as below. I have used principles of AON network…
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A:
Q: To complete the wing assembly for an experimental aircraft, Jim Gilbert has laid out the seven major…
A: With the help of data provided in the questions, the solution can be derived from the following…
Q: 2. Eowle Marketing Research has four project leaders available for the assignment of project leaders…
A: All linear programming (LP) problems focus on maximizing or minimizing some numerical values…
Q: A project consists of seven activities, lettered A through F below. For each activity, the estimated…
A: The question is related to Crashing. The cost slope will be calculated for each activity with the…
Q: A project consists of seven activities, lettered A through F below. For each activity, the estimated…
A: The question is related to Crashing. The Critical path activity having the least Cost slope will be…
Q: Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: How many alternatives are available? b. Obtain the optimal assignment using the Hungarian method.…
A: THE ANSWER IS AS BELOW:
Q: The City of Rockland is planning to build a new fire station. A project manager and the project team…
A: Determine the project scheduling technique:I would choose CPM as the project scheduling technique if…
Q: Problem 9-14 (Algorithmic) Davison Construction Company is building a luxury lakefront home in the…
A: Activity Optimistic Most probable Pessimistic A 4 9 14 B 5 6 7 C 3 4 5 D 8 11 14 E 7 9 17…
Q: Scott and Associates, Inc., is an accounting firm that has three new clients. Project leaders will…
A: a. Number of alternatives = Number of leaders x Number of clients = 3 x 3 = 9
Q: a. The expected project completion time for this problem is and the standard deviation is . b.…
A:
Q: On June 12, 2013, the Delta Corporation was awarded a $160,000 contract for testing a product. The…
A: The three imperatives project chiefs work inside are budget, scope, and schedule. Schedule (or time)…
Trending now
This is a popular solution!
Step by step
Solved in 7 steps with 9 images
- Amy Zeng, owner ofZeng's Restaurant Distributions,supplies nonperishable goods to restaurants around the metroarea. She stores all the goods in a storage area with a single dockand one aisle. The goods are divided into five categories accordingto the following table. The table indicates the number of tripsper month to store or retrieve items in each category, as well asthe number of storage blocks taken up by each. The following picture of the storage area provides an identificationnumber for each of the 16 storage blocks. For each item category,indicate into which blocks it should be stored.J.C. Howard's medical testing company in Kansas wishes to assign a set of jobs to a set of machines. The following table provides the production data of each machine when performing the specific job: Machine Job A B C D 1 9 10 7 6 2 11 5 9 6 3 9 11 5 12 4 12 8 13 9 a) The optimal assignment of jobs to machine that will maximize total production is:A chocolate maker has contracted to operate a small candy counter in a fashionable store. To startwith, the selection of offerings will be intentionally limited. The counter will offer a regular mixof candy made up of equal parts of cashews, raisins, caramels, and chocolates, and a deluxe mixthat is one-half cashews and one-half chocolates, which will be sold in one-pound boxes. In addition, the candy counter will offer individual one-pound boxes of cashews, raisins, caramels, andchocolates.A major attraction of the candy counter is that all candies are made fresh at the counter. However, storage space for supplies and ingredients is limited. Bins are available that can hold theamounts shown in the table.IngredientCapacity(pounds per day)Cashews 120Raisins 200Caramels 100Chocolates 160In order to present a good image and to encourage purchases, the counter will make at least 20boxes of each type of product each day. Any leftover boxes at the end of the day will be removedand given to a…
- Gerald Glynn manages the Michaels Distribution Center. After careful examination of his database information, he has determined the daily requirements for part-time loading dock personnel. The distribution center operates 7 days a week, and the daily part-time staffing requirements are Day M T W Th F S Su Requirements 7 3 4 4 5 4 5 Find the minimum number of workers Glynn must hire. Prepare a workforce schedule for these individuals so that each will have 2 consecutive days off per week and all staffing requirements will be satisfied. Give preference to the S-Su pair in case of a tie. (Note: If there is a tie that cannot be broken by following the preference to the S-Su pair, choose the pair closest to the beginning of the considered week.) The minimum number of workers is 7 workers. (Enter your response as a whole number.) Specify the workforce schedule for each employee by indicating the day offs (other days are considered to be…1. Maribel is selling regular and special juices. To make a bottle of regularjuice, she needs 2 pounds of mango and 3 pounds of pineapple. On theother hand, 4 pounds of mango and 2 pounds of pineapple are needed tomake a bottle of special juice. A profit of P30 is made for a bottle of regularjuice and P40 for a bottle of special juice. Maribel is currently has 800pounds of mango and 480 pounds of pineapple. She wants to make at least180 bottles of special juice. How many bottles of each type of juice mustshe make to maximize her profit? How much will be her maximum profit? 2. A calculator company produces a scientific calculator and a graphingcalculator. Long-term projections indicate an expected demand of atleast 100 scientific and 80 graphing calculators each day. Because oflimitations on production capacity, no more than 200 scientificand 170 graphing calculators can be made daily. To satisfy a shippingcontract, a total of at least 200 calculators much be shipped each day. Ifeach…Gerald Glynn manages the Michaels Distribution Center. After careful examination of his database information, he has determined the daily requirements for part-time loading dock personnel. The distribution center operates 7 days a week, and the daily part-time staffing requirements are Day M T W Th F S Su Requirements 7 3 5 5 6 2 2 Find the minimum number of workers Glynn must hire. Prepare a workforce schedule for these individuals so that each will have 2 consecutive days off per week and all staffing requirements will be satisfied. Give preference to the S-Su pair in case of a tie. (Note: If there is a tie that cannot be broken by following the preference to the S-Su pair, choose the pair closest to the beginning of the considered week.) Part 2 The minimum number of workers is _________workers. (Enter your response as a…
- 7-17 The Outdoor Furniture Corporation manufactures two products, benches and picnic tables, for use in yards and parks. The firm has two main resources: its carpenters (labor force) and a supply of redwood for use in the furniture. During the next production cycle, 1,200 hours of labor are available under a union agreement. The firm also has a stock of 3,500 board feet of good-quality redwood. Each bench that Outdoor Furniture produces requires 4 labor hours and 10 board feet of redwood; each picnic table takes 6 labor hours and 35 board feet of redwood. Completed benches will yield a profit of $9 each, and tables will result in a profit of $20 each. How many benches and tables should Outdoor Furniture produce to obtain the largest possible profit? Use the graphical LP approach. Make sure to find explanations from this question that I need to learn correctly.develope a space matrix for macdonalds. Below are the instructions. The steps required to develop a SPACE Matrix are as follows: 1. Select a set of variables to define financial position (FP), competitive position (CP), stability position (SP), and industry position (IP). 2. Assign a numerical value ranging from +1 (worst) to +7 (best) to each of the variables that make up the FP and IP dimensions. Assign a numerical value ranging from -1 (best) to -7 (worst) to each of the variables that make up the SP and CP dimensions. On the FP and CP axes, make comparison to competitors. On the IP and SP axes, make comparison to other industries. 3. Compute an average score for FP, CP, IP, and SP by summing the values given to the variables of each dimension and then by dividing by the number of variables included in the respective dimension. 4. Plot the average scores for FP, IP, SP, and CP on the appropriate axis in the SPACE Matrix. 5. Add the two scores on the x-axis and plot the resultant…The manager of a medical center wants to schedule staff based on a pattern of 5 days working and 2 consecutive days off. Based on the history of their workload, below is their weekly staff requirement: Day Monday Tuesday Wednesday Thursday Friday Saturday Sunday Staff needed 6 5 4 4 6 4 3 a. Determine what days employee 3 does not need to work. multiple choice Saturday and Sunday Monday and Friday Tuesday and Thursday Wednesday and Friday b. Determine the minimum number of full time staff. c. Determine the minimum number of part time staff. Prev Question 9 of 10 Total9 of 10 Visit question mapNext
- 9-7 The management of the Executive Furniture Corporation decided to expand the production capacity at its Des Moines factory and to cut back the production capacities at its other two factories. It also recognizes a shifting market for its desks and revises the requirements at its three warehouses. The table on this page provides the requirement at each of the warehouses, the capacity at each of the factories, and the shipping cost per unit to ship from each factory to each warehouse. Find the least-cost way to meet the requirements given the capacity at each factory.Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company’s needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 3 1 $13 $14 $15 2 $11 $12 $11 Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as Edwards provides sufficient advance orders, each supplier can devote its capacity to component 1, component 2, or any combination of the two components, if the total number of units ordered is within its capacity. Supplier capacities are as follows: Supplier 1 2 3 Capacity 400 800 600 If the Edwards production plan for the next period includes 800 units of component 1 and 600 units of component 2, what purchases do you recommend? That is, how many units of each component should be…The Swift Corporation wants to schedule the following seven-job problem to be processedon two machines A and B. Each job must be processed by two machines A and B, firston machine A and then machine B. The operation processing times at machine A and Bare as follows: Jobi 1 2 3 4 5 6 7 Processing time on machine A (ai) 9 8 7 12 6 8 15 Processing time on machine B (bi) 6 5 7 19 12 11 7 Suppose jobs arrived in their natural order (i.e., job l before job 2, etc.), and FIFOsystems of scheduling and processing the jobs is used. What is the completion timeof each job and what is the total throughput time (makespan) of all jobs?