The shown distribution network is to supply two factories A & B with load curves indicated. Assume that both factories have a lagging power factor of 0.8 . Select the required sizes of transformers for both factories such that in the case of a failure in one transformer the overload on the remaining ones should not exceed 15% . ) Select the required sizes of fuses to be installed at both sides of transformers. :) Calculate the annual energy losses in transformers of factory A. Assuming that transformers are in operation continuously . 1) Select the required size of the 11KV. XLPE cables for the distribution network , if cables are to be laid direct in ground with maximum ground temperature of 30º C. e) Calculate the annual energy losses in cables of section SA S 2 Km A 3 Km 11/0.4 KV Trans. 11/0.4 KV Trans. Factory A PF = 0.8 lag. Factory B PF = 0.8 lag. |S (KVA) 500 S (KVA) 500 400 400 300 300 200 200 100 100 Time (hr) 24 Time (hr) 24 12 18 12 18 Load curve of Factory (A) Load curve of Factory (B)
The shown distribution network is to supply two factories A & B with load curves indicated. Assume that both factories have a lagging power factor of 0.8 . Select the required sizes of transformers for both factories such that in the case of a failure in one transformer the overload on the remaining ones should not exceed 15% . ) Select the required sizes of fuses to be installed at both sides of transformers. :) Calculate the annual energy losses in transformers of factory A. Assuming that transformers are in operation continuously . 1) Select the required size of the 11KV. XLPE cables for the distribution network , if cables are to be laid direct in ground with maximum ground temperature of 30º C. e) Calculate the annual energy losses in cables of section SA S 2 Km A 3 Km 11/0.4 KV Trans. 11/0.4 KV Trans. Factory A PF = 0.8 lag. Factory B PF = 0.8 lag. |S (KVA) 500 S (KVA) 500 400 400 300 300 200 200 100 100 Time (hr) 24 Time (hr) 24 12 18 12 18 Load curve of Factory (A) Load curve of Factory (B)
Power System Analysis and Design (MindTap Course List)
6th Edition
ISBN:9781305632134
Author:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Chapter3: Power Transformers
Section: Chapter Questions
Problem 3.44P: A 130-MVA,13.2-kV three-phase generator, which has a positive-sequence reactance of 1.5 per unit on...
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 4 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning