Two sheet piles were driven 4 m apart into clayey sand, as shown in Figure 8.9, and a 2 m depth of soil between the two sheet piles was removed. To facilitate some proposed construction work, the region between the sheet piles is being dewatered where the water level is lowered to the excavation level by pumping out water con- tinuously. Assuming the hydraulic conductivity of the clayey sand as 2 x 10-6 cm/s, estimate the quantity of water that has to be pumped out per meter length per day. 4.0 m 2.5 m 2.0 m * 3.0 m K Sheet pile Impervious stratum Ground Level Clayey sand

Fundamentals of Geotechnical Engineering (MindTap Course List)
5th Edition
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter7: Seepage
Section: Chapter Questions
Problem 7.7CTP
icon
Related questions
Question
EXAMPLE 8.4
Two sheet piles were driven 4 m apart into clayey sand, as shown in Figure 8.9, and
a 2 m depth of soil between the two sheet piles was removed. To facilitate some
proposed construction work, the region between the sheet piles is being dewatered
where the water level is lowered to the excavation level by pumping out water con-
tinuously. Assuming the hydraulic conductivity of the clayey sand as 2 x 10-6 cm/s,
estimate the quantity of water that has to be pumped out per meter length per day.
4.0 m
2.5 m
2.0 m
3.0 m
FIGURE 8.9
Sheet pile
Impervious stratum
Ground Level
Clayey sand
Transcribed Image Text:EXAMPLE 8.4 Two sheet piles were driven 4 m apart into clayey sand, as shown in Figure 8.9, and a 2 m depth of soil between the two sheet piles was removed. To facilitate some proposed construction work, the region between the sheet piles is being dewatered where the water level is lowered to the excavation level by pumping out water con- tinuously. Assuming the hydraulic conductivity of the clayey sand as 2 x 10-6 cm/s, estimate the quantity of water that has to be pumped out per meter length per day. 4.0 m 2.5 m 2.0 m 3.0 m FIGURE 8.9 Sheet pile Impervious stratum Ground Level Clayey sand
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Measuring sitework, excavation and piling
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning
Principles of Geotechnical Engineering (MindTap C…
Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning