Using Figures 21.2 and 21.3, determine the cost for a (250 ft) by (200 ft) warehouse. The exterior walls are to be concrete block, which are used as bearing walls. The warehouse is (20 ft) high. Include ten (7 ft by 8 ft) dock levelers in the costs.
Q: The following table represents the activities of a small construction pro- ject that is required as…
A: Critical Path - It is the longest set of activity or sequence that is carried out to complete the…
Q: 3. If total materials cost for the construction of a three-storey commercial building is…
A:
Q: АCTIVITY PRECEDES EXPECTED TIМЕ А В 3 В С, D C 8 D END 15 E END 13
A:
Q: activities A1, A2, A3, A4, A5, A6, A7, A8, A9, and A10 sł durations provided under each activity.…
A: We need to determine Total Time of Project ES=Earliest Start Time EF=Earliest Finish Time LS=Least…
Q: Describe the Burden Fluctuation method?
A: Burden Fluctuation method are also known as Allegheny technique or method. Allegheny technique…
Q: Question Draw and analyze the arrow network for the following activities by using PERT method…
A:
Q: A warehouse rents for $5,236 per month. Assuming that the warehouse contains 9,520 square feet (sq.…
A:
Q: ) Constructed the plan (the activity by arrows) Method, find the construction time for this project…
A: 17 weeks ADGH
Q: What criteria will you used to decide the type of (flume, open ditch, surface pipe or underground…
A: Flumes are specially shaped, engineered structures used to measure the flow of water in open…
Q: What is the probability of completion of the project in 17.5 months? * Actv. Duration (month) a b…
A: Activity Event te=(to+4tl+4tp/6 Variance (del^2)=((tp-to)-6)^2 A 5-10 4…
Q: The expected finishing date for the project with 85% probability. * Actv. Duration (month) a m b…
A:
Q: Draw bar chart for activities for a house construction project
A: Bar chart or Gantt chart is the activity chart on which we plot the activity with the required…
Q: You are the Team Lead of a Consultant building a multi-use facility. The facility consists of 150…
A: There are many methods to be adopted to prepare the bill of quantities and used for valuing work on…
Q: Draw Gantt-Chart for the following activities, define the located activities on the critical path,…
A:
Q: The actual expenditure incurred in the construction of a single storey commercial building of plinth…
A:
Q: Determine the probability that the project will take longer than 50 weeks
A:
Q: Question Table 1 shows the list of the consecutive activities and their details for an 8-mi road…
A: Given:- Target rate of the build = 1.5 miles per week Minimum buffer time = 4 days To determine:=…
Q: C. Use the time and location indices shown above to estimate the cost of a building that contains…
A: For estimating the cost of the building we can use the formula given below Estimated cost=Previous…
Q: Question 5: A crawler bulldozer aving the information shown below; the contractor intends to rent…
A:
Q: Prepare a Precedence Diagram for the following construction plan Activity Duration Preceding…
A: Following Figure shows the Activity Times of the Precedence Network
Q: A rectangular corral is to be built with a required area. If an existing fence is to be used as one…
A: Solution- Small introduction- A fence to used as one of the sides which is already exists. We need…
Q: If you know that the activity (10-30) represents pouring concrete for the foundations, find the size…
A: Given that: Activity 10-30 is for concrete pouring for the…
Q: Q6: Perform PDM calculations for the small project below and determine activity times. Durations are…
A:
Q: ppose a construction site is 35km away from the market area, Apply the knowledge of construction…
A: The construction sites which have huge projects going on require ample amount of materials on site…
Q: Question Table 1 shows the list of the consecutive activities and their details for an 8-mi road…
A:
Q: The cost of building usually includes all of the following except a. any renovating or remodeling…
A:
Q: Q2) Prepare a time schedule for the construction for 80 houses using line of balance technique…
A: :
Q: From the given information below of a const. of commercial bank building a) draw the network…
A:
Q: Find the completion date of Activity D for 1O houses. * Activity Man-hours per unit (Q) Men per Gang…
A:
Q: No Tasks Weighted Start-End time (%) After 75% of the time, the completed workload is as follows: A…
A:
Q: What is the probability of completion of the project in 17.5 months? * Actv. Duration (month) ww w a…
A:
Q: 10. If there is a river on the road construction site, how to solve the problem?
A: The fresh water coming forming sea, ocean is known as river.
Q: Q: Draw the allocation of resources chart on the earliest and latest start time for the project that…
A:
Q: Q5/ Find job mix formula by using mathematical method.
A: Given:- sieve size To find:- job mix formula
Q: Develop a programming budget estimate for a 100,000 square-foot warehouse, assuming a square-foot…
A: Given:- The area of the warehouse = 100,000 square-foot The cost factor for square-foot = $60 per…
Q: The expected finishing date for the project with 64% probability. * Actv. Duration (month) a b 5-10…
A:
Q: ASSIGNMENT TITLE:
A:
Q: prepare a list of material and estimate the cost for providing a 1 bhk flat with 1 rest room
A: A rough estimate for house construction, using Thumb Rule: Cement will cost around 16.4% of total…
Q: discuss in detail, each of the factors affecting haulers productivity.
A: In the transportation of goods and materials haulers are required. For the transporting and moving…
Q: For the PERT problem find the critical path and project duration. What is the probability that the…
A:
Q: 2/ For the project data shown in the table below. If it was decided to turn over the project at 34…
A: The expected time of the activity, te=to+4×tm+tp6 The standard deviation of the activity,…
Q: How many hectare will a disk plow finish in 10 hours if the effective cut is 12”/ disk at a speed of…
A:
Q: 3. The rate of work progress after 4 weeks. Activities Description Man hours Team size Depends on A…
A: Consider the network diagram shown below.
Q: Consider the following project network. Determine the critical path and the project duration. D 2 E…
A: Given:- A project network is given To determine:- The critical path and the project duration
Q: Consider a small project that involves the following activities. Completion Times (days) Preceding…
A: 1.) The expression for the mean value is given as mean value=to+4tm+tp6 The expression for variance…
Q: An equipment costing P250, 000 has an estimated life of 15 years with a book value of P30, 000 at…
A: Given Initial cost of equipment = 250,000 salvage value= 30,000 Estimated life = 15 yrs
Q: What criteria will you use to decide the type of (flume, open ditch, surface pipe or underground…
A: It is asked to answer the criteria used to decide the conveyance system in irrigation. * Conveyance…
Q: H.W(1):- Draw Gantt chart for the following project and determine the duration of the project…
A:
Q: Develop a programming budget estimate for a 100,000 square-foot warehouse, assuming a square-foot…
A: Given:- The area of the warehouse = 100,000 square-foot The cost factor of the construction of…
Q: 2/ For the project data shown in the table below. If it was decided to turn over the project at 34…
A: expected time for activity =1-2=5+11+4×116=10weeks image is attached for the activity the expected…
Engineering - Construction
Cost Estimating
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Prepare a typical bay estimate based on the following information: a. Bay size of 350 feet and a building perimeter of 1,100 feet. b. There are 50 bays in the building. c. Unit prices: • Concrete piles: $950.00 each • Concrete pile caps: $725.00 each • Slab-on-grade: $12.50 per sq. ft. • Structural steel frame: $4.90 per sq. ft. • Roof structure: $10.75 per sq. ft. • Roofing: $8.20 per sq. ft. • Plumbing & HVAC: $9.80 per sq. ft. • Electrical: $6.10 per sq. ft. • Exterior foundations: $100.00 per linear ft. • Exterior walls: 728.00 per linear ft.Calculate the cost per cubic yard to place concrete using each of the alternatives described. The work in both cases consists of placing 140 cubic yards of concrete in footings. a. Using a crane and bucket at a price of $225 per hour, including an operator, with a crew consisting of 6 laborers, a cement finisher, and a foreman. The concrete will be placed in 7 hours using this setup, and transportation of the crane costs $390. b. Using a concrete pump at a price of $295 per hour, including an operator and a crew consisting of 5 laborers, a cement finisher, and a foreman. With this setup, concrete is placed in 6 hours and transportation of the pump costs $290.Show solutions pls. Thanks
- IDENTIFY 1. These are all the works that are to be included in the contract with aclient and these are what the estimator considers in their estimate. 2. This is the cost equivalent to a unit of the measurement of each scope ofwork. 3.This is the document that quantity surveyors base the cost estimates usingthe scope of works in terms of the magnitude/measurements.You are the Team Lead of a Consultant building a multi-use facility. The facility consists of 150 residential buildings, a football park, a commercial area, 2.5km of all-weather roads with adjoining roads. The designs for all structures have been completed and reviewed to ensure that the standards and the Client’s brief are totally complied with. The Bill of Quantities for the whole the works have also been developed based on the drawings and specification. Advice your team on the best Method of Measurement to be adopted to prepare the Bill of Quantities and used for valuing work on completion.From where the temporary construction utility services are obtained?
- three quarters of a pipe where used for a certain project at a new site. when two thirds of the remainder had been used, 50 pipe where left. howmany pipes were used at the startSpiffy Dry Cleaners has recently changed management,and the new owners want to revise the current layout. Thestore performs six main services: (1) laundry, (2) drycleaning, (3) pressing, (4) alterations, (5) delivery, and(6) tuxedo rental. Each is located in a separate department,as shown here. The load summary chart gives the currentlevel of interaction between the departments. Calculate thenumber of nonadjacent loads for the current layout. Design an alternative layout to minimize the number of nonadja-cent loads.what type of contract is this: (1) The supply by a wholesaler of 10,000 bricks to the site following a telephone request from the site agent
- Two installers will install the unit. Each will work the same amount of timeand will be paid $8.00 per hour. How much will each installer earn fromthis job?prepare a list of material and estimate the cost for providing a 1 bhk flat with 1 rest roomUnder a unit-price contract with a 25 percent guarantee requirement of all unit prices quoted, the engineer’s estimate of earthwork quantities totals 9,270 cubic meters. If the actual quantities measured in the field for paypurposes total 10,650 cubic meters, is a change order justified for the quantity change?