Textbook Question
Chapter 11, Problem 9RQ
Calculate the cost per cubic yard to place concrete using each of the alternatives described. The work in both cases consists of placing 140 cubic yards of concrete in footings.
a. Using a crane and bucket at a price of $225 per hour, including an operator, with a crew consisting of 6 laborers, a cement finisher, and a foreman. The concrete will be placed in 7 hours using this setup, and transportation of the crane costs $390.
b. Using a concrete pump at a price of $295 per hour, including an operator and a crew consisting of 5 laborers, a cement finisher, and a foreman. With this setup, concrete is placed in 6 hours and transportation of the pump costs $290.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Derive the labor and equipment cost for a 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture based from the following crew team composition, output and given prices. 1. Team and Daily Rates 1- Project Engineer (P 2000/day) 1 - Construction Foreman (P 1000/day) 6 - Mason (P800/day) 12 - Laborer (P500/day) 2. Output of team is 13.5 cu.m per day. 3. Equipment (minor tools) is 10% of the labor cost.
A labor crew for placing concrete consists of one labor foreman at $27.69 per hour, one cement finisher at $29.30 per hour, 4 laborers at $24.45 per hour each, and one equipment operator at $34.3 per hour. Such a crew, called a C20 crew, can place 156 cubic yards of concrete per 8-hour day.
Determine the cost of C20 crew per cubic yard of concrete.
The cost of C20 crew per cubic yard of concrete is determined to be $
Derive the labor and equipment cost for a 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture based from the following crew team composition, output and given prices.1. Team and Daily Rates1- Project Engineer (P 2000/day)1 - Construction Foreman (P 1000/day)6 - Mason (P800/day)12 - Laborer (P500/day)2. Output of team is 13.5 cu.m per day.3. Equipment (minor tools) is 10% of the labor cost.
Chapter 11 Solutions
Fundamentals Of Construction Estimating
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- if you have a delivery of 255 m3 of concrete how many samples do you have?arrow_forwardPrior to concrete pouring of a slab on grade, a polyethylene sheet it to be laid on the ground. The slab dimension is 30 meters wide and 50 meters length, how many linear meter of 12 feet wide PE sheet you’ll need for this activity? a. 400 l.m. b. 450 l.m. c. 500 l.m. d. 1673 l.m. What is total material of PE sheet, if the cost per 50 m. is Php 7,000? a. Php 56,000.00 b. Php 63,000.00 c. Php 70,000.00 d. Php 238,000.00arrow_forwardSHOW COMPLETE SOLUTIONS AND DRAWINGS: A column with a section of 0.30m x 0.35m is to be filled up class AA reinforced concrete. It is 3.00m in height How many cement bags do you need to fill it up? If you will have a total of 10 columns, how many cubic meters of sand and gravel will you need? Compute for the Total Cost needed for the 10 columns if 1 cement bag is Php 275 pesos, and 1 cubic meter of Sand is sold at Php 1850.00, and 1 cubic meter of Gravel is sold at Php 1950.00. Take note: The Class AA type of concrete mix has 12 bags of cement per cubic meter. To get the volume of the following: Volume of sand= volume of column x 0.50 Volume of Gravel= volume of column x 1.00arrow_forward
- A bill of quantity of a project includes 500m2 of masonry work. The work will be done by one crew with a production rate of 50 m2/day and consists of: Crew member No Price rate Brick layer 2 50$/day Assistant 1 25 Labor 2 12 Vendor price of 1000 bricks = 160$. Each 55 bricks are estimated to make one square meter of masonry. Each one cubic meter of mortar is used to join brick area of 50 m2 and consists of: Quantity Material Primary quotation form vendor One cubic meter Sand 15$/m3 6 sacks (50 kg each) Cement 240$/ton As a contractor, it is required to estimate the work unit price and the work price. Assume all material waste as 10% and assume overheads and markup as 20% of total cost. (WRITE THE ANSWER ONLY)arrow_forwardYou are given the following information about a dry-batchpaving operation. You are going to use one mixer that has aservice rate of 30 services per hour. The dry-batch trucksyou use for bringing concrete to the paver have an arrivalrate of 7.5 arrivals per hour. Each truck carries 6 cubic yardsof concrete. You have a total amount of 13,500 cubic yardsof concrete to pour. You rent a truck at $15 per hour and thepaver at $60 per hour. If the job takes more than 80 hours,you pay a penalty of $140 per hour owing to delays in jobcompletion. On the basis of least cost, determine the numberof trucks you should use. Plot the cost versus the numberof trucks used.arrow_forwardcan you help me with this question? what do you think are some of the problems that using pumping for concrete work brings?arrow_forward
- Your company was hired to renovate this old grain silo. You need to compile a quote for bidding the following tasks. 1. The foundation is cracked and will need to be repoured. The silo is 40 feet in diameter, and the foundation will need to be 6 inches (.5 feet) thick. First find the volume of the foundation. Then find the cost if material is $1/cu ft and labor is a flat $300. 2. Next the walls will need to be painted barn red to the height of 100 feet (ignore the dome). One gallon covers 1000 sq ft of surface, how many gallons must be purchased? If each gallon cost $30, and labor is a flat $1500, how much is this portion of the job? 3. Last, we are instructed to fill the silo with grain. How many cu ft of grain can fit into the silo? If we charge $0.02 per cu ft, what is this portion of the job cost? 4. Find the total bid.arrow_forwardGiven the bridge abutment shown here, determine the numberof worker hours required to form the structure usingdata from R. S. Means or other appropriate reference.arrow_forwardthree quarters of a pipe where used for a certain project at a new site. when two thirds of the remainder had been used, 50 pipe where left. howmany pipes were used at the startarrow_forward
- 9-Identify the costing method that is suitable for mines, quarries, cement works etc. a. Operation b. Contract c. Process d. Batcharrow_forwardYou are aconstruction engineer workingon a largeconcrete foundation project, involving theplacement ofover 500,000 c.y of concrete. The construction site is adjacent toa salt-water source (bay) & it is decided to set up a concrete batchplant onsite. The project schedule shows that the various concrete pours are to take place from April to September. What considerationswould you makewith regards to cement type, aggregate, waterquality, and admixtures? Explain your considerations in detail.arrow_forwardwhat are the Profession of individuals involved in constructing a wooden wharf ?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Pricing Concrete Jobs - 24' X 24' Concrete Floor (Prep, Pour, Finish); Author: Mike Day Concrete;https://www.youtube.com/watch?v=V-fgI1Hiu9w;License: Standard Youtube License