Textbook Question
Book Icon
Chapter 11, Problem 9RQ

Calculate the cost per cubic yard to place concrete using each of the alternatives described. The work in both cases consists of placing 140 cubic yards of concrete in footings.

a. Using a crane and bucket at a price of $225 per hour, including an operator, with a crew consisting of 6 laborers, a cement finisher, and a foreman. The concrete will be placed in 7 hours using this setup, and transportation of the crane costs $390.

b. Using a concrete pump at a price of $295 per hour, including an operator and a crew consisting of 5 laborers, a cement finisher, and a foreman. With this setup, concrete is placed in 6 hours and transportation of the pump costs $290.

Blurred answer
Students have asked these similar questions
Derive the labor and equipment cost  for a 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture based from the following crew team composition, output and given prices. 1. Team and Daily Rates 1- Project Engineer (P 2000/day) 1 - Construction Foreman (P 1000/day) 6 - Mason (P800/day) 12 - Laborer (P500/day) 2. Output of team is 13.5 cu.m per day. 3. Equipment (minor tools) is 10% of the labor cost.
A labor crew for placing concrete consists of one labor foreman at $27.69 per hour, one cement finisher at $29.30 per hour, 4 laborers at $24.45 per hour each, and one equipment operator at $34.3 per hour. Such a crew, called a C20 crew, can place 156 cubic yards of concrete per 8-hour day. Determine the cost of C20 crew per cubic yard of concrete. The cost of C20 crew per cubic yard of concrete is determined to be $
Derive the labor and equipment cost  for a 1,000 sq.m 4" thick masonry wall using 1:5 mortar mixture based from the following crew team composition, output and given prices.1. Team and Daily Rates1- Project Engineer (P 2000/day)1 - Construction Foreman (P 1000/day)6 - Mason (P800/day)12 - Laborer (P500/day)2. Output of team is 13.5 cu.m per day.3. Equipment (minor tools) is 10% of the labor cost.

Chapter 11 Solutions

Fundamentals Of Construction Estimating

Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Pricing Concrete Jobs - 24' X 24' Concrete Floor (Prep, Pour, Finish); Author: Mike Day Concrete;https://www.youtube.com/watch?v=V-fgI1Hiu9w;License: Standard Youtube License