What is the outcome when a bottleneck resource is augmented with more capacity? Throughput time increases Cycle time decreases The resource with the second least utilization becomes the bottleneck All of the above
Q: When the effective capacity turns out to be much less than the theoretical capacity, why it is not…
A: Effective capacity is the maximum quantity of work that a company may accomplish within a specific…
Q: Help ! Choice Bank receives credit card applications that need to be reviewed for a decision.…
A: Utilization is the work done in a given specified time, that is how much did the employee utilize…
Q: Cubway, the sandwich shop, is run by Jim, Tim and Kim. When a customer arrives, Jim spends 5 minutes…
A: Here, First, I would draw the flow chart for this application case or situation, the flow chart is…
Q: The assembly department started the month with 468,000 units in its beginning work in process…
A: Inventory is the raw items, material, and raw parts that a company used to manufacture the products…
Q: People are served in a process with two resources. The first resource has a capacity of 2 people per…
A: The detailed solution is given in Step 2.
Q: department during the month to begin processing in the Assembly Department. There were 34,000 units…
A: Given data •The Assembly Department started the month work in process with 37,000 units •An…
Q: Give a brief explanation of five major process scheduling policy factors.
A: Process scheduling:- The task of the process manager that deals with removing the active process…
Q: Why does the theory of constraints advocate that a manager’s attention be directed tothe bottleneck…
A: The theory of constraints is the one which focuses on removing as well as identifying the…
Q: In a manufacturing system, the technique of deciding how to assign work to specific work stations…
A: b. Line balancing
Q: Process layout is employed: a. where dissimilar jobs are manufactured on similar machines b. where…
A: process layout is a plan for the floor plan of a plant which means to further develop effectiveness…
Q: day. They accept clients and provide them with the service from 7 a.m. to 6 p.m., Monday - Saturday.…
A: THE ANSWER IS AS BELOW:
Q: 1. What is the outcome when a bottleneck resource is augmented with more capacity? 2. Which of the…
A: 1. Bottleneck: The resources required the longest time in the operation of the supply chain is known…
Q: The Earliest Due date (EDD) rule for sequencing a given set of jobs usually ____________ Select…
A: Scheduling is a technique for allocating precious computational resources typically processor time,…
Q: Compute the task time for a system where the total time per shift is 480 minutes, there is one…
A: To compute the takt time, calculate the net time per shift and the net time available per day. Step…
Q: Given this set of daily service operation, assuming a processing order of A-B-C-D-E; Determined the…
A: If four cycles are used, then the inventory size of the operation can be minimized and be more…
Q: How does the capacity analysis react when many processes are running concurrently
A: Capacity analysis can be defined as the way of knowing the capacity of the organization which…
Q: A production line at V. J. Sugumaran’s machineshop has three stations. The first station can process…
A: Given that: Station 1 can process one unit in 10mins. Station 2 has two identical machines and can…
Q: FILE UPLOAD: Draw a flowchart for customers fueling their cars at a gas station, starting with the…
A: A flowchart is a sort of outline that addresses a work process or cycle. A flowchart can likewise be…
Q: Which of the three workstations, W, X, or Y, has the highest aggregate workload, and thus serves as…
A: As per the provided data the information is as follows.
Q: In an 11-week period, a work center produces 1000 standard hours of work. What is the measured…
A: Measured Capacity The term measured capacity is used to determine the actual capabilities of the…
Q: Steel City Juice is a local company that makes two kinds of juice: orange juice and apple juice.…
A:
Q: What is Determining slack (or Float) Explain briefly with examples
A: Project management is a process of managing all the activities of the projects. So that the project…
Q: Process D has five activities in a straight line. The cycle time for Activity 1 is 10 seconds,…
A: Given data Cycle time of Activity 1= 10 seconds Activity 2= 35 seconds Activity 3= 30 seconds…
Q: The site is scheduled to run from 8:00 am to 5:00 pm and has 9,000 citations today. You can start…
A: given, scheduled run = 8.00am to 5.00 pm citation = 9000 arriving rate = 1250 per hour
Q: Joe’s commercial laundry has contracts to wash bedsheets for hotels. Joe intakes each batch of…
A: Here, the ironing process has the least capacity per hour. Hence, the ironing process is the…
Q: RTP streams in different sessions identified by a receiver? How are different streams from within…
A: The RTP (Real-Time Transport Protocol) gives start to finish network transport work for application…
Q: What is the outcome when a bottleneck resource is augmented with more capacity? A Throughput time…
A: In supply chain management, bottleneck resources often occur which increases the overall process…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: What is the outcome when a bottleneck resource is augmented with more capacity? a. Throughput time…
A: The time taken to complete a certain task is called throughput time. An organization can determine…
Q: Loans are evaluated in a process with two resources. The first resource has a capacity of 30 loans…
A: Given, First resource capacity = 30 loans / hour Second resource capacity = 38 loans / hour Demand =…
Q: True or false a change in the design of a product, modifications to the schedule or a new product…
A: Statement- A change in the design of a product, modifications to the schedule or a new product…
Q: An order for 200 units of a product is processed on work centers A and B. The set up time on A is…
A: Given: A B Set-up time 45 min 40 min Run time 5 min 8 min
Q: What happens to the non-bottleneck resources when the bottleneck resource is maximized?
A: Bottleneck resources generally refer to those resources whose capacity is similar or equal to or…
Q: in a short essay explain the advantages and disadvantages of shortest processing time (SPT) and…
A: most brief handling time (SPT) A need sequencing decide that indicates that the work requiring the…
Q: Determine the total production cost for additional 10 units after the second unit was completed…
A: The formula for the total production cost =Cost of material, equipment usage, and supplies + Labour…
Q: Which operation is the bottleneck of this process? a. Stocking b. Pricing c. Spotting d. Shipping…
A: An operation that takes the maximum time to complete its task in a supply chain for a particular…
Q: Choice Bank receives credit card applications that need to be reviewed for a decision. There are two…
A: Given that, Time taken to process pre approved applications = 6 minutes Time taken to process not…
Q: B Bunt's fleet repair facility has the capacity to repair 800 trucks per month. However, due to…
A: Formula used- Utilization = Actual Output / Total Capacity
Q: Define the concept of Bottleneck? Explain what system capacity is? Explain why doubling the capacity…
A: The theory of constraints is a concept of identifying the constraints that delay the productivity of…
Q: Considering the concept of constraint management, what are a few of the challenges of managing…
A: At first it is important to know the concept of constraint management. The word constraint depicts…
Q: Diablo Electronics manufactures four unique products (A, B, C, and D) that are fabricated and…
A: In production and project management, a bottleneck is one process in a chain of processes, with the…
Q: A production line has three stations and the first station can process a unit in 10 minutes. The…
A: The capacity of any process is determined by its slowest resource and is measured in units per time.…
Q: Pine Valley Furniture Pine Valley Furniture recently implemented a new internship program and has…
A: How were Pine Valley Furniture’s projects initiated? What is the focus for eachof the new systems?…
Q: itical aspects of designing department layouts
A: The layout of a manufacturing facility is an arrangement of many elements. It examines the…
Q: Which of the following is an inherent assumption in the Resource based view of the firm? a)…
A: Resource Based view : This is a managerial framework which is used to determine the resources…
Q: Explain the reason why doubling the capacity of a bottleneck would not double the system capacity
A: To determine: the reason why doubling the capacity of a bottleneck would not double the system…
What is the outcome when a bottleneck resource is augmented with more capacity?
- Throughput time increases
- Cycle time decreases
- The resource with the second least utilization becomes the bottleneck
- All of the above
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- What is the outcome when a bottleneck resource is augmented with more capacity? a. Throughput time increases b. Cycle time decreases c.The resource with the second least utilization becomes the bottleneck d. All of the aboveWhat is the outcome when a bottleneck resource is augmented with more capacity? A Throughput time increases B Cycle time decreases C The resource with the second least utilization becomes the bottleneck D All of the aboveWhat is the outcome when a bottleneck resources is augmented with more capacity? Will throughput time increases Will cycle time decreases The resources with the second least utilization becomes bottleneck All the baove statement are correct
- For a given process, the raw processing time is 102 sec, the bottleneck cycle time is 20 sec/item, and the WIP is 6 items. The expected lead-time (LT) is ____ seconds. Enter a whole number answer.An order for 100 of a product is processed on operation A and operation B. The setuptime on A is 50 minutes, and the run time per piece is 9 minutes. The setup time onB is 30 minutes, and the run time is 6 minutes per piece. It takes 20 minutes to movea lot between A and B. Since this is a rush order, it is given top priority (president’sedict) and is run as soon as it arrives at either workstation.It is decided to overlap the two operations and to split the lot of 100 into two lotsof 60 and 40. When the first lot is finished on operation A, it is moved to operation Bwhere it is set up and run. Meanwhile, operation A completes the balance of the 100units (40) and sends the units over to operation B. These 40 units should arrive asoperation B is completing the first batch of 60; thus, operation B can continue withoutinterruption until all 100 are completed.a. Calculate the total manufacturing lead time for operation A and for B withoutoverlapping.b. Calculate the manufacturing lead time…In a few words, explain how to prevent a process getting starved in priority scheduling.
- If a production process has a bottleneck cycle time of 48 minutes/item, what is the maximum daily capacity of the system, assuming the company operates two, 8-hour shifts? Enter an integer value.A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are: Task Time(secs) ImmediatePredecessor u 30 none v 30 u w 6 u x 12 w y 54 x z 30 v,y If the company wants the output rate to be equal to demand, what is the last task performed at the second workstation if tasks are assigned in order of the most following tasks?Why does the theory of constraints advocate that a manager’s attention be directed tothe bottleneck of a process?a. It is useful to lower the utilization of the bottleneck.b. The bottleneck has considerable influence on the average flow rate of a process.c. It is important to minimize the buffer inventory in front of the bottleneck.d. First-come-first-served scheduling of jobs at the bottleneck ensures that all jobs havethe same expected waiting time before they are processed at the bottleneck.
- A local toy manufacturer is using a production line that runs hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 201 01, 2.13, 2.0, 2.61 2.71. and 2.95 minutes for A, BC, D , and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task and task each require task B to be completed. Task must be completed prior to stating task E. Task F needs both task Dand task E to be completed. Finally, task G can start only once task Fis completed . What should be the calculated cycle time in minutes?Jane Reed bakes breads and cakes in her home for parties and other affairs on a contract basis. Jane has only one oven for baking. One particular Monday morning she finds that she has agreed to complete five jobs for that day. Her husband John will make the deliveries, which require about 15 minutes each. Suppose that she begins baking at 8:00 A.M. (given) Determine the sequence in which she should perform the jobs in order tominimizea. Mean flow time.b. Number of tardy jobs.c. Maximum lateness.Process D has five activities in a straight line. The cycle time for Activity 1 is 10 seconds, Activity2 is 35 seconds, Activity is 30 seconds, Activity4 is 80 seconds and Activity is 40 seconds. If activities 1, 2 and 3 are combined into one activity and assigned to one worker, and activities 4 and 5 are combined and assigned to second worker, the capacity of the system becomes ?