What is the reserve capacity, if the maximum demand of generation of power is 50 MW, the load factor of the plant is 60% and the plant capacity factor is 50%? 1. 15 MW 2. 10 MW 3. 20 MW 4. 6 MW

Electricity for Refrigeration, Heating, and Air Conditioning (MindTap Course List)
10th Edition
ISBN:9781337399128
Author:Russell E. Smith
Publisher:Russell E. Smith
Chapter17: Commercial And Industrial Air-conditioning Control Systems
Section: Chapter Questions
Problem 6RQ
icon
Related questions
Question
What is the reserve capacity, if the maximum demand of generation of power is
50 MW, the load factor of the plant is 60% and the plant capacity factor is 50%?
1. 15 MW
2. 10 MW
3. 20 MW
4. 6 MW
Transcribed Image Text:What is the reserve capacity, if the maximum demand of generation of power is 50 MW, the load factor of the plant is 60% and the plant capacity factor is 50%? 1. 15 MW 2. 10 MW 3. 20 MW 4. 6 MW
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Maximum power transfer theorem
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Electricity for Refrigeration, Heating, and Air C…
Electricity for Refrigeration, Heating, and Air C…
Mechanical Engineering
ISBN:
9781337399128
Author:
Russell E. Smith
Publisher:
Cengage Learning
Power System Analysis and Design (MindTap Course …
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning
EBK ELECTRICAL WIRING RESIDENTIAL
EBK ELECTRICAL WIRING RESIDENTIAL
Electrical Engineering
ISBN:
9781337516549
Author:
Simmons
Publisher:
CENGAGE LEARNING - CONSIGNMENT