What is the variance in completion time for the critical path found in above? Compute and explain.
Q: This section explains project scheduling strategies such as the WBS, Activity Definition, and…
A: Scheduling is the process of arranging the production activities in order to complete the…
Q: Conslder the AON graph of a project shown below. 12 A4 A3 Figure 19.17 A6 02:25:04 Ag A7 A2 A1 A5…
A: Find critical path The total time of all the critical activity is the Project completion time
Q: Consider the AON graph of a project shown below. AA Figure 19.17 Аз A6 A7 Ag A2 A5 The activity…
A: The concept of AON Diagram is mostly used in project management. The AON diagram is a network…
Q: The network diagram below (activity on arrow) shows the activities needed to complete a project to…
A: ANSWER IS AS BELOW:
Q: Which characteristics must a project have for critical path scheduling to be applicable
A: Project characteristics necessary for critical path scheduling to be applicable are:
Q: critical path.
A: Critical path The critical path method (CPM) is a task demonstrating method that is utilized by…
Q: A new project is to be completed. The following activities need to be completed in the order shown,…
A: Find the estimated time calculation below:
Q: 1. Organize the infomation above in an activity precedence table showing the activity, precedent and…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: Given the network plan that follows, compute the early, late, and slack times. What is the project…
A:
Q: Discuss the use of the Critical Path Method (CPM) to findthe shortest time for the completion of a…
A: Critical path method:- Project managers utilise the critical path method (CPM) to develop a project…
Q: a engineering project consists of the activities shown in the following Table. Use the Critical Path…
A: Forward Pass:Early Start (ES) = Maximum (or Highest) EF value from immediate Predecessor(s)Early…
Q: snip
A: If task A is an immediate predecessor of task B, task A must be completed first before task B.
Q: Consider Table 6-3. All duration estimates or estimated times are in weeks, and the network proceeds…
A: The question is related to Critical Path Analysis. The details are given regarding activities and…
Q: snip
A: Early start time =3 days Early finish =5 days Late start time = 10 days late finish time = 12 days
Q: Consider the PERT/CPM network below: The activity/task times are given in weeks: Fill in the blank…
A:
Q: AA Аз A6 Ag A7 A2 A1 A5 The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A,…
A: The critical path consists of the longest sequence of activities from project start to finish that…
Q: Identify the term being described for each of the following: d. The difference in time length of any…
A: The answer is "slack".
Q: (a) Based on the information in Table 1, draw a complete AON precedence diagram to illustrate the…
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: Consider the following project network. Assume that the time required (in weeks) for each activity…
A: THE ANSWER IS AS BELOW:
Q: Prepare an arrow diagram and a list of earliest and latest starts and finishes , the tota float and…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: What is the critical path through the network? What is the project completion time? Suppose the…
A: A network diagram is a visual representation of a project which helps identify the activity…
Q: Construct a Network Diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: A project consists of seven activities, lettered A through F below. For each activity, the estimated…
A: Given data is Steps for project crashing: Create the network diagram Find the path with the…
Q: Use the critical path algorithm to create a priority list for the digraph below, then schedule the…
A: Given data is
Q: latest finish time of the last activity
A: Critical path is the longest duration indicating path from a project. A critical path indicating the…
Q: What are the differences between the Forward Pass, the Backward Pass, Total float, and Free float in…
A: Project Scheduling: In the project scheduling, Forward pass and Backward pass help…
Q: The critical path technique is important in project scheduling, but what exactly does it do?
A: Each project features a few activities that are necessary for timely fulfillment. These are named…
Q: Use the decreasing time algorithm to create a priority list for the digraph below, then schedule the…
A: Find the Priority list below:
Q: Draw and analyze a project network diagram to answer the following questions: What is the most that…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: You have prepared the following schedule for a project in which the key resources is a tractor.…
A: SOLUTION:
Q: How do we calculate slack?
A:
Q: The achievement of the objectives of a project will be possible only by applying the appropriate…
A: Let’s get to know the difference between the two by getting to know the meaning of the scheduling…
Q: NSTRUCTIONS: Draw the AON network for Exercise 14 (pg ASSIGNMENT 200 & 201). Complete the forward…
A: Project management is the process of overseeing a team's activity to complete all project objectives…
Q: Project scheduling methods such as the Work Breakdown Structure (WBS), Activity Definition (AD), and…
A: Below is the solution:-
Q: Please provide the CPM result for each of the following metrics: ES_{end} = LS_{D} = TS_{D} =…
A: THE ANSWER IS AS BELOW:
Q: see the diagram below to answer the questions for this problem. (Correct attachement now added)…
A: Critical Path method calculates the various path of activities in the system and identifies the…
Q: snip
A: Answer: The optimistic time is the shortest possible time for an activity to be completed which is…
Q: Given an activity with multiple time estimate values of a-12, m-15, b-20, calculate the expected…
A: Expected completion time is a concept in Program Review Evaluation Technique (PERT). However,…
Q: A project consists of seven activities, lettered A through F below. For each activity, the estimated…
A: The question is related to Crashing. The Critical path activity having the least Cost slope will be…
Q: Draw the PERT diagrams for the given set of tasks and dependencies. Complete the table showing the…
A: Given data is
Q: What qualities does a project need to be able to use critical path scheduling?
A: Critical path scheduling is an invaluable tool that project managers have at their disposal. Without…
Q: Activity Immediate Predecessor Time A 5 B A 8. B D A 8 9. F C 2 G D, E H F 7 G 4 H, I 3
A: Given activities-
Q: Perform the CPM (critical path method) and give the complete activity schedule table, the project…
A: A Project Evaluation and Review Technique (PERT) is a device that projects the board uses to deal…
Q: For the following simple seven‐activity project, develop a precedence network, calculate all…
A: : Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and…
Q: Which characteristics must a project have for critical path scheduling to be applicable? What types…
A: The critical path method (CPM) is also termed as the critical path analysis (CPA). This method is a…
Q: In reference to the attached activity precedence diagram and activity times shown. (Feel free to…
A: Slack time = Slack time is the time by which a activity can be delayed , without delaying the over…
Q: Consider the following project network. Assume that the time required (in weeks) for each activity…
A: Below is the solution:-
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- Activities A, B, C, and D are on the critical path of the network diagram below: The cost and duration of performing these activities is: Task A: $2,500 in 4 days Task B: $5,000 in 3 days Task C: $10,000 in 6 days Task D: $8,000 in 8 days At the end of day 10, tasks A and B are complete and task C is 25% complete. The amount spent thus far is $11,000. Given this information, how will you summarize the status of the project? Ahead of schedule, over budget Ahead of schedule, under budget Behind schedule, under budget Behind schedule, over budgetA contractor needs to complete a project. The project involves 10 activities (labeled A, B, ..., J) with precedence relationship in network below. The estimate (in weeks) of the duration of each activityis in the table below. a. The mean and variance of the activity time for A~F are given in the table. Find the mean and variance of the activity time for the remaining arcs.b. Identify the critical path and then compute the mean and variance of the project completion time.c. What is the probability that the project is completed between 32 and 36 weeks?d. What completion time should the contractor claims to be 95% sure of completing the project by then?Consider the following PERT time estimates: a. Draw a network for this project and determine the critical path based on the most likely times by inspection.b. Assuming that the critical path is the one you identified in part (a), what is the probability that the project will be completed before 28weeks? Before 32 weeks?c. Assuming that the critical path is the one you identified in part (a), how many weeks are required to complete the project with probability .95?
- Consider a construction project with the following data on precedence relationships, durations, and costs: Activity Immediate predeccessor (s) Normal Time (days) Normal Cost ($) Crash Time (Days) Crash Cost ($) A - 6 120 4 170 B - 4 120 2 220 C A 3 195 2 270 D A 4 320 2 520 E B, C 7 700 4 1075 F D, E 5 650 2 1100 G E 10 1600 6 2300 F and G are the terminal activities of the project. (a) Find the critical path. (b) Find the project completion time and the corresponding cost. (c) Suppose it is required to complete the project in 22 days. Find which activities to crash and by how much, to yield the minimum project cost. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.For each of the following network diagrams, determine both the critical path and the expected project duration. The numbers on the arrows represent expected activity times.a. AOA diagram b. AON diagram c. AOA diagram d. AON diagram. True/False Statements (Tick the correct option) Selection of the critical path in network activity diagram for any project, is always focused onresult of the minimum time duration of the critical activities [ True / False ] Suppose, we have total 03 activities in the project “X”; namely L, M and N respectively. An activity “M” is the immediate successor of the activity “L”, while the activity “M” is the immediate predecessor for the activity “N”. According to this scenario, an activity “M” will be the last activity of the project “X” in the network activity diagram [True / False ] The dummy activity consumes both time and resources [True / False ] Towards the optimal solution through stepping stone method, when degeneracy problem is occurred, the next step is to focus on searching lowest value on the independent position in a non-allocated cells [True / False ] Hungarian algorithm, first convert any given assignment matrix into row reduction matrix [True / False
- The following represents a project that should be scheduled using CPM a. Complete the table b. Draw the Network Diagram c. What is the critical path? d. What is the expected project completion time?' e. What is the probability of completing this project within 16 days?Consider Table 6-3. All duration estimates or estimated times are in weeks, and the networkproceeds from Node 1 to Node 8. (Note that you can easily change this table to createmultiple exercises.)a. Draw an AOA network diagram representing the project. Put the node numbers in circlesand draw arrows from node to node, labeling each arrow with the activity letter andestimated time.b. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8as a guide for how to represent each path.c. What is the critical path for this project and how long is it?d. What is the shortest possible time needed to complete this project?What is the value of the missing item labeled (a) in the table above? Round to the nearest integer. What is the value of the missing item labeled (b) in table above? Round to two decimals. Draw the network diagram for this project. Clearly label the earliest start, earliest finish, latest start, latest finish and slack for each activity. Specify the critical path and the critical activities. State the expected C.P. duration State the variance of the critical path. What is the probability that the dashboard will be delivered within 20 days?
- A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume all activities require the same resource. On a piece of scratch paper, draw the early-start Gantt Chart associated with this table and determine the following. Assume the project is resource-constrained but not time-constrained. Assume only one resource is available and that resource can only do one activity at a time. Activities B, C and D all have the same early start date (time). Since there is only one resource, only one of the activities B, C, D can be started on the early start date. Which should be started first?In making a forward pass through a network, three activities are immediate predecessors for activity T and one following activity. What is the late start time for activity T? Group of answer choices: - the LS of the following activity plus the activity time of T - the smallest EF for the three activities that are immediate predecessors for activity T - the LF of the following activity minus the activity time of T - the LS of the following activity minus the activity time of T - the largest EF for the three activities that are immediate predecessors for activity T