Draw and analyze a project network diagram to answer the following questions: What is the most that Activity E can be delayed in starting, without delaying the project? O A. 22 О в. 21 C. 19 D. 20 Е. 18
Q: scenarios of a project activities (tables given below) and their required times to be completed in…
A: In this question is about the critical path where we have to make a network diagram and have to show…
Q: The nine activities A to I whích make up a project are subject to the following precedence…
A: Disclaimer- Since you have posted a question with multiple sub parts , we will solve first three sub…
Q: Q1: For the project listed below, find the following items: 1- Total project finishing time 2-…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: A E Start Finish B D F G Activity | A А В C D E F G Time 3 5 5 6 he crashing data for this project…
A: Critical path activity-
Q: a. Construct a CPM network for the design project. b. Compute the EF, LF, and slack for each…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: The following activities are part of a project to be scheduled using CPM. 1. Activity Immediate…
A: Since there are 2 questions and it is multiple, we will solve only one. The first CPM will be…
Q: Picture attached below
A: ACTIVITY DURATION ES EF LS LF SLACK CRITICAL A 3 0 3 0 3 3 - 3 = 0…
Q: a. Construct the network. b. How long will it take to finish the project? c.. What is the critical…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: a. Draw the CPM Network b. What is the critical path c. What will the scheduled (earliest…
A: In the question, we have Activity Table data, this table data includes activity ID, Immediate…
Q: a. Draw the project network diagram. b. What completion date would you recommend?
A: Below is the solution:-
Q: Give data of a project. Project manager checks the project at the end of week 10th Manpowers/ weeks…
A: Cost Variance (CV = EV - AC) Cost Performance Index (CPI = EV/AC) Schedule Variance (SV = EV -…
Q: 5) Draw the Network and do the analysis Using the information in Table 1, assuming that the project…
A: Note: - Since we can answer only up to 3 subparts, we will answer sub part i, ii, and iii for…
Q: The network diagram and task times for a project are shown below. Aj A4 A5 A3 Task Duration (days)…
A: This question is related to the project management subject, here, This subject falls under…
Q: Draw the Network Diagram and determine the Critical Path and duration of the project (in days).…
A: Given Information:
Q: H.W(1):- Draw Gantt chart for the following project and determine the duration of the project…
A: A Gantt chart is a type of bar chart. It shows the schedule of a project. It was invented by Henry…
Q: An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and…
A: We have, Optimistic, To = 2 Most likely, Tm = 3 Pessimistic, Tp = 6
Q: Þroject, Activity, Predecessor, Duration Below is a project listed in a table with: • activity, •…
A: Given- Activity Predecessor Duration (Weeks) A None 3 B A 7 C A 5 D B 12 E B 8 F C 5…
Q: 1. Construct the activity-on-node network. 2. Identify the critical path. 3. Compute the duration of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: A2 A4 A5 Task Duration (days) 3 A1 A2 A3 3 Aa A5 days What is the late finish time for activity A,?
A: Using the Forward path, Early Start of the activity = Early Finish of predecessor activity Early…
Q: 12. Given the following network project where the times are in days: Task Normal Crash Normal Crash…
A: Given data: TASK NORMAL TIME CRASH TIME NORMAL COST CRASH COST IP A 2 1 200 300 - B 3 1 100…
Q: HW 5: By using Microsoft Excel construct the Gantt chart for the project with the activities…
A: Given data:
Q: Given the following table, construct a network diagram, either AOA or AON. Times are in days.a.…
A:
Q: . CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL…
A: Activity-on-node is a therm related to project management. It directs to a precedence diagramming…
Q: oger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: The project network is the diagrammatic form in which project activities and their durations are…
Q: Enrichment Exercise 7.2 Promoter of championship boxing match must perform the task shown in the…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: a Draw the Network diagram on your own paper. b. How many paths are there in the network? c. What is…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: 2. A network consists of the activities in the following list. Times are given in days. Activity…
A: Given data is
Q: In the project considered here, activity crashing can take place over a wide range of reduction…
A: Given details: Let's consider the amount in hundreds to make the calculation easier.
Q: • Q1: Determine the critical path, the critical activities and the project completion time.…
A: The project network diagram is the diagram that shows the activity and the project duration to…
Q: Construction of a building is based on the followingCPM network:a. Draw the network for this project…
A: "Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: Q3: Draw the network diagram and determine the critical path for the following project: Activity…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Task time estimates for the modificat ion of an assembly line at Jim Goodale's Carbondale, Illinois,…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Task time estimates for a production line setup project at XYZ Company are as follows; Activity Time…
A: We are authorized to answer three subparts at a time since you have not mentioned which part you are…
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: What would a project manager have to do to crash an activity? 2. Describe the meaning of slack, and…
A: Project management is a process of coordinating all processes related with a project. A crashing…
Q: 13.42 Activity Ais worth $100, is complete, and actually cost $150. Activity B is worth $500, is 75%…
A:
Q: Below matrix shows one of the important data used in project management, identify the name of the…
A: The matrix shown in the question is named as RACI Chart or RACI Matrix. The RACI Chart or RACI…
Q: The production line project consists of nine major activities. Activity B D E Immediate Predecessor…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: 3. Draw a project network from the following information. What activity(s) is a burst activity? What…
A: A network diagram is the graphical representation of project activities or tasks and their duration…
Q: Crash the project until no more crash can be performed How much it would cost The new critical…
A: Proect crashing is one of the techniques used in the calculation of the duration of the critical…
Q: The following activities represent a small project to be constructed Activity Normal Duration…
A: Find the given details below: Given Details: Activity Normal Duration(Days) Previous Activity…
Q: 14 - In earned value analysis, we found that BCWP: $24,800 BCWS: $27,650 ACWP: $21,900 The project…
A: Earned Value Analysis (EVA): It is a system that enables the project manager to estimate the amount…
Q: Q2. Consider the following data summarizing the details of a project involving 12 activities.…
A:
Q: 4. For each of the following network diagrams, determine both the critical path and the expected…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: Activity Immediate Normal Time Cost/day Lower Time Predecessor (days) & Limit None 450 None 300 A 3…
A: Given data is
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: Draw a project network given the information below. Time (Days) Predecessor Description First…
A: A network diagram is the pictorial representation of all the activities in the project in…
Q: Q1: A project consisting of the following activities: ML KTJIH GFE D CB A K J HE GF D.C D.C D.C A BB…
A:
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 6 images
- Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way. Activity NormalTime(weeks) NormalCost ($) CrashTime(weeks) CrashCost ($) MaximumweeksReduced CrashCost perWeek ($) A 3 500 2 900 1 400 B 4 600 3 700 1 100 C 6 800 3 1,286 3 162.00 D 6 1,500 4 2,150 2 325 E 6 1,750 4 2,250 2 250 F 5 1,200 5 1,200 0 0 G 7 1,500 5 1,794 2 147 H 3 500 3 500 0 0 Reduce G by select a number of (1-4) week(s), C by select a number (1-4) of week(s), at a cost of $ __________ enter a dollar amount .Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 6 - E 5 BB 8 - F 6 BC 2 A G 9 C, ED 3 A H 7 D , F Dave's earilest start (ES) and earliest finish (EF) are: Activity ES EF A 0 6 B 0 ? C D E F G H#3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to more than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors Most Likely Duration A - 8 B A 12 C A 6 D A 12 E B 10 F E 7 G C 18 H C 13 I G 10 J H 13 K D 10 L K 11 M L 7 N F, I, J, M 4 Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?A student has been put in charge of a new garden design. The new design will involve five different activities. Per project management guideline, activities “a” and “b” start on day 0. Draw the network diagram. Calculate ES/EF/LS/LF and Slack for all activities. Activity A: Immediate Predecessprs (-) Duration days (3) Activity B: Immediate Predecessprs (-) Duration days(5) Activity C: Immediate Predecessprs (a) Duration days(3) Activity D: Immediate Predecessprs (b) Duration days(7) Activity E: Immediate Predecessprs (C,D) Duration days(3)You are the project manager of the software installationproject in Table 7.12. You would like to find the minimum-costschedule for your project. There is a $1,000-per-week penaltyfor each week the project is delayed beyond week 25. In addi-tion, your project team determined that indirect project costsare $2,500 per week.a. What would be your target completion week?b. How much would you save in total project costs with yourschedule?
- The VOXN Cinema is installing a new system to enhance the quality of movies shown. Assume that the following table provides information on the immediate predecessor relation and time estimated for each event. a.List the possible eight events which you think essential in expanding a Cinema.b. Draw a network diagramc.find the total time required to complete the project d. List the critical events of the project. Activity immediate predecessor Time (weeks) A - 3 B - 4 C A 6 D B 2 E A 5 F C 2 G D , E 4 H F , G 510. The project described in the following table is scheduled to be completed in 11 weeks. Constructa network diagram using AOA or AON (see Example 5 for either type). Then answer the followingquestions:a. If you were the manager of this project, would you be concerned? Explain.b. If there is a penalty of $5,000 a week for each week the project is late, what is the probabilityof incurring a penalty of at least $5,000? Path Activity Estimated time(Weeks) Std. Dev(Wks) A C 4 0.7 D 6 0.9 B E 3 0.62 F 9 1.9Given the following table, construct a network diagram, either AOA or AON. Times are in days.a. Determine the expected duration of the project.b. Compute the probability that the project will take at least 18 days.Path Activity Time EstimatesA 4-5-6Top B 7-8-10C 3-5-9D 7-8-11Bottom E 2-3-4F 1-4-6
- The Advanced Tech Company has a project to design anintegrated information database for a major bank. Datafor the project are given in Table 7.6. Indirect project costsamount to $300 per day. The company will incur a $150 perday penalty for each day the project lasts beyond day 14.a. What is the project’s duration if only normal times are used?b. What is the minimum-cost schedule?c. What is the critical path for the minimum-cost schedule?2) Following is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct Cost Activity Preceded By Regular Crash Regular Crash A -- 6 days 2 day $2000 $3800 B -- 12 6 2000 10000 C A 4 2 1000 4000 D B, C 10 6 3400 4600 E D 8 6 2800 3900 F E 6 2 5000 7600 G B, C 18 8 16000 19600 H F, G 6 4 2000 4000 (a) Construct a network including the Early and Late Start and Finish times. (b) Identify the normal Critical Path(s) and the normal expected completion time (c) Can the project be crashed to last 18 days? Which activities should be crashed and at what additional cost?Gabrielle Kramer, owner of Pet Paradise, is opening a newstore in Columbus, Ohio. Her major concern is the hiringof a manager and several associates who are animal lovers.She also has to coordinate the renovation of a building thatwas previously owned by a chic clothing store. Kramer hasgathered the data shown in Table 7.14. a. How long is the project expected to take?b. Suppose that Kramer has a personal goal of completingthe project in 14 weeks. What is the probability that it willhappen this quickly?