Question
thumb_up100%
you decide to estimate duration and standard deviation of a project using PERT method. the project has 3 steps the following are the optimistic, most likely and pessimistic durations in weeks:
step 1: 2,5,10
Step 2: 1,3,13
Step3: 7,8,11,
what is the estimated duration and standard deviation of the project duration?
Estimated Duration =16 standard Deviation =4.9
Estimated Duration =18 standard Deviation =4.9
Estimated Duration =18 standard Deviation =2.49
Estimated Duration =16 standard Deviation =24
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The purpose of program evaluation is to assess how well the project team, team members, and program manager performed. Group of answer choices True Falsearrow_forwardWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Crash Normal Activity Time (days) Time (days) Normal Cost A 5 4 B 9 7 C 6 5 D 7 5 E 7 4 Total Cost with Crashing Immediate Predecessor(s) $800 $300 $600 $750 $1,200 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $400 $650 $1,500 $1,650 | | | < 0arrow_forwardYou have determined the following for a given project: Expected completion time of the project = 26 weeks Standard deviation of project completion time = 8 What is the probability of completing the project in more than 32 weeks? answer as a decimal and take it to four places.arrow_forward
- Use the following information to answer the questions that follow. Some of your project’s activities are listed below, with time estimates given in days. Activities A and N have been identified as critical. Activity Optimistic Most Likely Pessimistic A 4 6 12 B 2 3 3 D 1 2 3 F 1 2 4 N 2 5 8 What is the standard deviation of the project completion time? 1.67 1.78 2.78 3.17arrow_forwardConsider the office renovation project data in Table 7.16. A“zero” time estimate means that the activity could take a verysmall amount of time and should be treated as a numericzero in the analysis.a. Based on the critical path, find the probability ofcompleting the office renovation project by 39 days.b. Find the date by which you would be 90 percent sure ofcompleting the project.arrow_forwardJordanne King, the project manager for Webjets International, Inc., compiled a table showing time estimates for each of the activities of a project to upgrade the company’s Web page, including optimistic, most likely, and pessimistic.a. Calculate the expected time, te, for each activity.b. Calculate the variance, s2, for each activity.Activity Optimistic (days) Most Likely (days) Pessimistic (days)A 3 8 19B 12 15 18C 2 6 16D 4 9 20E 1 4 7arrow_forward
- Evaluate the below statement according to the project management terminologies and choose the correct answer: It is the process of making a forecast or precise approximation Choose... of time and cost associated with a work package or activity. Graphically describes a project consisting of well-defined Choose.. activities, the completion of which marks its end. One of the Perform Quantitative Risk Analysis process has a Choose.. Tools and Techniques. Useful for building accountability through assigning specific Choose.. tasks to team members. It is the standard format each path through the network must be continuous with no gaps, discontinuities, or dangling Choose... activities. Organizational Assets, Project Scope Statement, Cost Management Plan and Schedule Management Plan are inputs Choose.. of: Choose... Work Breakdown Structure Expert Judgment Bar chart Estimating A horizontal diagram format Plan Risk Managementarrow_forwardConsider the office renovation project data in the following table. A "zero" time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis. a. Based on the critical path, find the probability of completing the office renovation project by 39 days. Refer to the standard normal table (Make sure to round all intermediate calculations for te and variance to two decimal places.) The probability isarrow_forwardThe following information relates to a project (task times are in weeks). Use the information to solve for the critical path and then to determine the probability that the project could be completed within 36 weeks. Task A B C D E F Preceding Tasks to 4 4 2 None A B D, E tm 6 7 7 8 13 9 8 0 W CON 6 tp 8 10 12 18 15 10 Click the icon to view the table of standard normal probabilities. The probability that the project is completed within 36 weeks is. (Enter your response rounded to four decimal places.)arrow_forward
- If the pessimistic duration of an activity is 205, the most likely duration is 160 days and the optimistic duration is 115 days, what is the expected time of the activity for PERT/CPM analysis ? What is the variance for the activity time for PERT/CPM analysis ?arrow_forwardKimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table Total Cost with Crashing Immediate Predecessor(s) $2,050 $2,800 a) Based on the given information regarding the activities for the project, the project completion date = b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing the activities: The first activity to crash is by 2 weeks at a per week crashing cost of Ned, one should crash activity dollars. Total cost of crashing the project to 7 weeks = and activity E by 1 week at a total per week crashing cost of dollars. dollars. weeks. dollars. dollars. Normal Activity Time (weeks) A TERSE Doo LU LỞ MATMARIATION percen 32 TON * Next one should crash activity D and activity by 2 weeks for an…arrow_forwardThe manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Activity Optimistic Most Probable Pessimistic Immediate Predecessors A 1 2 3 - B 4 6 8 A C 2 4 6 A D 1 2 3 B, C E 2 3 4 B F 1 2 3 A G 1 2 3 D H 1 2 3 G I 1 1 1 E, H, F A. Draw a project network for this problem. B. Fill in all the blanks in the following table. Note: For variance (σ2) in activity time, keep two decimal places. Activity Expected Time t (weeks) Variance σ2 ES EF LS LF Slack Critical Path? A B C D…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,

Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning

Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.