a. If you start the project immediately, when will it be finished? The critical path is path and the project duration is Activity START A BCDEFG FINISH Tomores, SCIT Activity Time (weeks) 0 3 5 1 3 6 10 2 0 Immediat weeks. (Enter your response as an integer.)
Q: Which of the following paths would be infeasible?
A: Network diagrams are used to represent the structure of a network and the flow of information among…
Q: sparkling wines. Its most popular product is the French Bete Noire, which is shipped directly from…
A: Ans) Data: Annual Demand = D = Weekly Demand*52 = 50*52 = 2600 S = ordering cost = 260 Unit cost = c…
Q: Arnold Tofu owns and operates a chain of "hamburger" restaurants in northern Louisiana. Sales…
A: 1) Using Excel: In Excel select columns of profit and sales, go to insert tab select scatter chart.…
Q: Discuss the drivers and useful sources of information while moving from domestic to international…
A: Careful deliberation is required before deciding to obtain raw materials and/or components for your…
Q: To reduce and dampen information distortion, what should firms do? (select all that apply) Group of…
A: It is the goal of every supply chain to maximise the total value created. The value created by a…
Q: Which type of network optimization problem is used to solve this problem?
A: The network optimization problem is a mathematical problem that is trying to find the least cost of…
Q: Evaluate the effectiveness of a Agile/Scrum approach compared to a plan-based approach based on the…
A: The concepts of agile and scrum are not so different from each other. Agile is a concept that helps…
Q: You are trying to invest $100,000 in a portfolio of stocks and bonds. You want the highest return…
A: Given data is
Q: If the annual demand is 14,000, the number of working days is 330 in a year, and the delivery lead…
A: As per guideline, expert can only solve first question ' s sub part. So please upload remaining part…
Q: Using trend projection, develop a formula to predict sales for years 11 and 12. You have to show all…
A: The given data stated below, Year TV Sales 1 150 2 300 3 480 4 600 5 630 6 640 7…
Q: Determine the most profitable number of each model of robot to produce during the coming month. [PX]
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Create a time series plot. b) Develop a six period moving average. What is the forecast for month…
A: NOTE: We are allowed to do the first three sub-parts only. Forecasting demand is an essential task…
Q: What are some cultural values that are highly inconsistent with yours? How might the presence of…
A: A community's cultural values are its fundamental principles and ideals.There are several parts to…
Q: Jack Ltd is a market leader in the manufacture of apple juice. They operate a reorder level system…
A: Given data: Average usage = 800 per dayMinimum usage = 540 per dayMaximum usage = 1260 per dayLead…
Q: Favors Distribution Company purchases small imported trinkets in bulk, packages them, and sells…
A: Ans) Basic Table Calculation: Mean and other Calculation: Linear Equation:
Q: A small tailoring business makes an average of 150 garments every week (1 week = 5 working days). If…
A: Throughput refers to the time taken to process/complete/manufacture 1 unit frrom beginning to end
Q: Mr. Henry produces a particular type of shoes on a Fancy line. The process involves eight different…
A:
Q: I only need help with part C please.... The Metropolitan Bus Company (MBC) purchases diesel fuel…
A: Maximum inventory is largest stock level hold in the company. It is calculated with following…
Q: nd leaves Roger in the photocopy room while the photocopier cools down. While waiting, Roger flips…
A: Personal information files need to be kept safe and guarded against theft, loss, misuse, and…
Q: Owen Conner works part-time packaging software for a local distribution company in Indiana. The…
A: Breakeven point indicating the unit level or revenue level which facilitating no cost or loss. Here,…
Q: A hotel has 200 rooms and 2 fares: low fare, which is $250 per night’s stay, and high fare, which is…
A: The protection level refers to the number of rooms in a hotel that are kept reserved for the high…
Q: 8. Consider the warehouse location decision facing CupAMoe's (Example 8.60). a. (**) Suppose Robbie…
A: Given data is Coordinates of Capital City = (1,5) Coordinates of Springfield = (4.5,3) Coordinates…
Q: Emerald manufactures large screen televisions. Their best-selling model has annual demand of…
A: Given data: Annual demand = 8,000 units/year Daily production capacity (p) = 200 units/day. Setup…
Q: Sea Wharf Restaurant would like to determine the best way to allocate a monthly advertising budget…
A: (a)
Q: able 5.1: The demand forecast developed for the year ended 31 December 2022. Month Production days…
A: Daily demand = Monthly demand / Number of days in a month Daily demand (level strategy) = Sum…
Q: A firm has established a distribution network for the supply of a raw material critical to its…
A: When supply is less than demand or vice versa, it is called as unbalanced problem. For unbalanced…
Q: Jordin Henry's machine shop uses 2,470 brackets during the course of a year. These brackets are…
A: Ans) Data:
Q: Data collected on the yearly registrations for a Six Sigma seminar at the Quality College Year 1…
A: A time series forecasting technique called exponential smoothing may be expanded to handle data with…
Q: a) What is the ROP to satisfy a %90 probability of not stocking out? b) What is the safety stock? c)…
A: Daily demand (d) = 100 Standard deviation demand (Sd) = 12 Lead time (L) = 5 Standard deviation (Sl)…
Q: “Coady used a strategy of focusing on reducing the number of projects in the portfolio.” Briefly…
A: According to the case study - Frontier Airlines Holdings has bankrupt a few years later, they…
Q: The Bijou Theater shows vintage movies. Customers arrive at the theater line at the rate of 100 per…
A: From the question description, the following information can be extracted. Arrival rate λ = 100 per…
Q: I am confused where your numbers are coming from. If look at the diagragm I attached. The…
A: Bottleneck station is the one which takes highest time to process 1 unit of any product in a given…
Q: “Being successful in business requires a number of qualities and competencies, not all of which can…
A: The aptitude and preparedness to create, plan, and manage a business enterprise—along with all of…
Q: GRAPH METHOD Graph-Based Method: Example Lets consider the following relationship chart and using…
A: Graph based method is construction type layout method which is used with an adjency based objective…
Q: Audi Profile, History and Status Quo: In 1910, the first Audi car was produced in Zwickau, Saxony.…
A: The case is about an automobile manufacturer that produces luxurious cars. The company follows a…
Q: Jantel Mitchell's bakery prepares all its cakes between 4 A.M.and 6 A.M.so they will be fresh when…
A: Given data; Cost price 10 $ per cake Selling price 16 $ per cake Salvage price 8 $ per…
Q: Forecasting method A has errors of 10, -15, 5 and 20. Forecasting method B has errors of -10, 4, 16…
A: Forecasting is a method of predicting the unknown. In other words, it is a step forward by looking…
Q: Chris Sandvig Irrigation, Inc., has summarized the price list from four potential suppliers of an…
A:
Q: How many tyres should MWV order at once? (Hint: Consider a 12-month timeframe and recall that each…
A: Annual Demand (D) = 450 * 12 * 2 = 10,800 tyresPrice (P) = R 400Carrying Cost (C) = 15% of P = R…
Q: What are the consequences of shipping and receiving errors?
A: Shipping errors are the mistakes made in the process of shipping. Receiving errors are mistakes made…
Q: task duration (hours) predecesor 1 predecesor 2 predecesor 3 A 4 B 5 C 3 A D 3 A…
A: Formulae used: Cycle Time = Operation time/dayoutput /day Theoretical minimum number of…
Q: Why we should not hire a staff through friend's recommendation and should go through proper process…
A: Ans) Hiring a staff through friend's recommendation is not a good idea for the business. Business…
Q: Read the case study below and answer ALL the questions that follow. CRISIS IT In May 2007, Frontier…
A: The case is about a bankrupt airline. A new CIO was hired after a year of bankruptcy. The new CIO…
Q: 4. AlwaysRain Irrigation, Inc. would like to determine capacity requirements for the next four…
A: Formulas to be used: % of capacity used=Total demand production capacity per 1000 units per…
Q: Firms focusing on responsiveness tend to a. locate facilities close to the market they serve. b.…
A: In supply chain management, considerations around facility network infrastructure are essential.…
Q: Explain the role of transportation in logistics. Support your answer with an example ?
A: Logistics is the science and art of organising the smooth transport of goods, data, and other…
Q: Zuke's Nukes is a retailer of organic microwavable entrees. They purchase frozen meals in batches…
A: The entire number of units produced during a production run is, in fact, referred to as the batch…
Q: A manufacturer’s annual demand is 6000 units. The current units per order is $100. The setup cost is…
A: Economic order quantity is the optimal quantity of products or goods that company purchase, store…
Q: terested in arriving at a forecast of rentals so that she can order the correct quantities of…
A: Ans) Formula:
Q: 24,000-seat arena that is home to the city’s professional basketball and ice hockey teams and that…
A: The given value for the Smoothing parameter α = 0.20 We have to find the forecast for year 5. This…
Step by step
Solved in 2 steps with 1 images
- Management Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (A) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)A project consists of three tasks: A, B, and C. Task A is known to take five days forsure. Tasks B and C are each dependent on A. B takes five days. C takes seven dayswith a probability of 0.5 and three days with a probability of 0.5. What is the expectedcompletion time of the project?a. 8 daysb. 10 daysc. 11 daysd. 12 daysManagement Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)
- Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the 13th day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedence relationships are given in Table. Electric Motor Project Data Activity Normal Time(days) Normal Cost ($) Crash Time (days) Crash Cost ($) ImmediatePredecessor(s) A B C D E F G H 4 7 5 6 3 11 4 3 1000 1400 2000 1200 900 2500 800 300 3 4 4 5 2 6 3 1 1300 1200 2700 1400 1100 3750 1450 500 None None None A B C D,E F,G a. Draw the project network diagram.b. What completion date would you recommend?In reference to the attached image and data below: Step A we learned: Critical Path = A, B, H, I, J; Project Time = 40 Weeks; Total Cost = 364,000 Step B we learned: To crash the critical path I would crash A by 1 week, B by 2 week, H by 2 week and C by 3 week. This would not alter the critical path, only the time line. Steps C we learned: Modeling uncertainty in activity times. In this case I would use the activity times and determine the Variances and the Standard Deviation. Using “best case” (x) and “worst case” (y) scenarios for activity times the formula’s would be (x-y)/6 and (x-y)^2/36. What are the final recommendations for this case?Using your results from Problem 6,(a) Calculate the probability that the project will be completedin 38 weeks.(b) Calculate the probability that the project will be completedin 42 weeks
- there are four project baselines. Scope baseline Schedule baseline Cost baseline Performance measurement baseline Pick one of the baselines above, explain it, and tell us how it is applied to monitor and control a project. If possible, use the Getta Byte Project to provide examples.Ans c. The earliest starting time for activity H is 15 days Ans d. The latest start time for activity J is 25 days. Ans e. The critical path is A-B-H-I-L-M with the minimum duration of the project as 28 days This is a follow up question please do f and gYou are in charge of a project. Your team has determined that there are 7 activities to be completed. Here are the activities, the time to complete the activity and the immediate predecessor of the activity. Using this data 1) construct a Gantt Chart, 2) determine the time it will take to complete the project, 3) You are monitoring the progress of this project and discover that activity C is in danger of taking longer than planned due to funding issues. What options do you have to get the project back on track? Activity Time Immediate Predecessor A 10 Weeks None B 6 Weeks A C 7 Weeks A D 6 Weeks B E 8 Weeks C F 3 Weeks D G 4 Weeks F
- The following represents a very simple project. The calendar allows for 5 work days (M-F) per week. To keep things simple we won’t separate capital expenses and labour. The cost per activity shown below is total (i.e. not per day). Activity Duration (days) Precedent Cost A 5 None* $500 B 7 None* $1000 C 3 A , B $400 D 4 C** $500 E 6 C** $800 * Except for ‘Start’ ** The project can only be signed off once D and E have been completed. Enter the data into a software tool such as GanttProject, and generate the Gantt chart. Please ensure that: 1.…For conducting a project seven activities should be performed but maximum availablemanpower is 17. Task duration and manpower requirement is given below. Project managersaid, “It is possible to complete the project without leveling the manpower". Evaluate thestatement of the PM. (Justified or Not-Justified)Widgetco is making a prototype of a new product. The productconsists of two subassemblies. Before building either subassembly, the firm must purchaseraw materials and train workers. Before the subassemblies can be combined, subassembly2 must be inspected. The following table describes the project:Activity Description Requires Duration (Days)A Train workers 6B Purchase materials 9C Make subassembly 1 A,B 8D Make subassembly 2 A,B 7E Inspect subassembly 2 D 10F Combine subassemblies C, E 12G Subassembly 2 safety report E 6How quickly can Widgetco complete this project?(a) Define decision variables.(b) Write a suitable LP problem formulation.