You're managing a project using the earned value management for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual cost (AC) is $150,000. What is the cost variance (CV) for the project?

Managerial Economics: A Problem Solving Approach
5th Edition
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Chapter17: Making Decisions With Uncertainty
Section: Chapter Questions
Problem 8MC
icon
Related questions
Question

You're managing a project using the earned value management for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual cost (AC) is $150,000. What is the cost variance (CV) for the project?

 


 

a.

-50,000

b.

100,000

c.

-100,000

d.
150,000
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Cost of Production
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning