ASSESSMENT TASK 4 – REVIEWING IMPLEMENTATION A COMPLETED PROGRESS REPORT
1. KPI progress:
Objective 1
 Agreement signed within the time limit and auctioned, but only 180 machines installed in the past 12 months. There was a slower uptake in Northern Territory and North Queensland, due to the tourist slump with the strong Australian dollar.
 Melbourne warehouse is still not open. It is currently being run on the more expensive agency model.
 Still no service contractor for Northern Territory. All others meet the deadline, although agents in Western Australia, Tasmania and Northern Territory were very expensive.

Objective 2
 100% volumes have increased to the point that all orders fill a container. KPI achieved in quicker time due to the initial increase in demand.
 13.8% some states still underperforming. Strategy still in line with timetable.

Objective 3
 12,000 clicks per day Achieved in half the time allocated. SEO specialist contractor very experienced.
 Survey reveals only (50%) uptake. Design and colors not attractive. Strategy introduced within timeframe.

Objective 4
 30 suggestions and 8 new innovations, leading to a significant reduction of waste. Introduced with designated timeframe.
 12kw per person. Introduced to late in the year and not rolled out across the whole organization.

2. Milestone progress:

Project name: Australian Hardware Brisbane
Milestone # : xxxxxxx
Date due : July 30, 201x

Milestone status:

 Has this milestone