preview

Proj 592 - CP3

Better Essays

PERFORMANCE ANALYSIS
After setting the entire project to 40% complete on Oct 1, 2008 we can see that the project is behind schedule. The schedule variance of the entire project is $ (736,599) and Schedule performance index is at 0.68, which indicates that for every $1.00 spent in the project we are only getting $0.68 worth of work done. Since we do not have actual cost data, the MS Project calculates the budget is under budget by a negligible $80.
Performance Analysis (Cost)
Table 1
Task Name
Cost Variance
CPI
Estimate at Completion
Baseline Cost
Theme Park Project
80
1.00
4,449,920
4,449,920
Site Layout & Side Grading
-
1.00
10,000
10,000
Footings & Foundations
-
1.00
103,600
103,600
Masonry
-
1.00
281,200
281,200
Frames, Columns & Beams …show more content…

Our first issue was Joists and Roof Deck that is late by ($78,873.67) and is 48% behind in schedule. Rough Carpentry is late by ($60,583.15) at 48% behind the schedule and Interior Drywall is late by $(12,200.00) and is 40% behind schedule. Next we need to look at Elevator and we will see that it is ($34,973.67) behind schedule by 48%. Plumbing is late by ($23,401.25) at 24%, HVAC is late by ($14,633.33) at 19%, and Electrical is late by ($13,609.00) at 17%. The main concern right now for our project being behind schedule is the Attraction install and training because it is late by ($327,030.00) at 89% .
The critical activities are not behind schedule and the task the critical tasks are dependent on “Slab on Grade” is complete. Since the critical tasks are not behind schedule it is not safe to assume that the project will complete on time.
Let’s look at the Task “Attraction Install and Training”, the Schedule performance index is very low at 0.16 which indicates that each $1.00 spent on that task & sub-tasks are getting $0.16 worth of work compete.
Estimate at Completion
As we saw in the earlier section the critical path activities are not delayed. But some of the tasks that are delayed are mentioned in the table below. The table below shows the free slack and the total slacks of the tasks that are delayed.
Task
% Complete
Duration
Start Date
Finish Date
Late Start
Late Finish
Free Slack
Total Slack
SPI
Theme Park Project

Get Access