Problems 6-1: Forecasting project completion (Ungraded) A project has been estimated to take six weeks and cost $130,000. Cost and percent complete data are provided in the table below through 3 weeks of the project. % scheduled data can be obtained from the Gantt chart following the table. Task | $/Task | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 | A | $5,000 | 100% | 100% | 100% | | | | B | $10,000 | 50% | 70% | 100% | | | | C | $25,000 | | 40% | 80% | | | | D | $30,000 | | 20% | 45% | | | | E | $10,000 | | | | | | | F | $20,000 | | | | | | | G | $20,000 | | | 50% | | | | H | $10,000 | | 80% | 100% | | | | | ACWP | $12,000 | $38,000 | $66,000 | | | …show more content…

Task | BAC | % Comp | BCWP (EV) | BCWS (PV) | ACWP (AC) | cv | sv | cpi | svi | EAC | Calculation | A | $5,000 | 100% | $5,000 | $5,000 | $5,500 | ($500) | $0 | 0.91 | 1.00 | 5,500 | Actual | B | $10,000 | 100% | $10,000 | $10,000 | $9,500 | $500 | $0 | 1.05 | 1.00 | 9,500 | Actual | C | $25,000 | 80% | $20,000 | $25,000 | $19,000

Get Access