1.Develop a project network diagram that shows all the activities and precedence relationships. 2. Determine the project length (without crashing). 3. Determine the critical path activities.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Section A - Please answer # 2 - Determine the project length without crashing

WEBSITE DESIGN
During discussion both you and Rissa have determined that the following activities are necessary
for the development of a sustainable, functional website (See table below).
I.
A
B
C
D
E
F
G
H
|
J
K
L
M
Pictures of
clothing
Video of clothing
Design of main web page
Design of web product categories
Design of web order page
Completion of main web page
Review & changes of web page
Completion of product category & order system
Review & changes of product category & order
system
Video for ordering system
Design of web subscription section
Social media ads
Final website integration, review & changes
Predecessor
Section A
||
A, B, C
F
A, B, D, E
H
B
J
J
G, I, K, L
Estimated
Time
(days)
3
5
2
2
2
2
1
2
1
15
3
2
2
Maximum
Crash
Time
(days)
1.5
3
1
1
1
1
0
1
0
5
1.5
1
0
Rissa is not happy about the length of time it takes to complete the website. She asks if this can be
shortened. You inform her that crashing an activity cost $40 per hour ($320 per 8 hour work day).
1.Develop a project network diagram that shows all the activities and precedence relationships.
2. Determine the project length (without crashing).
3. Determine the critical path activities.
4. Determine the crashing cost if the project must be finished in 16 days, 18 days, and 21 days?
Transcribed Image Text:WEBSITE DESIGN During discussion both you and Rissa have determined that the following activities are necessary for the development of a sustainable, functional website (See table below). I. A B C D E F G H | J K L M Pictures of clothing Video of clothing Design of main web page Design of web product categories Design of web order page Completion of main web page Review & changes of web page Completion of product category & order system Review & changes of product category & order system Video for ordering system Design of web subscription section Social media ads Final website integration, review & changes Predecessor Section A || A, B, C F A, B, D, E H B J J G, I, K, L Estimated Time (days) 3 5 2 2 2 2 1 2 1 15 3 2 2 Maximum Crash Time (days) 1.5 3 1 1 1 1 0 1 0 5 1.5 1 0 Rissa is not happy about the length of time it takes to complete the website. She asks if this can be shortened. You inform her that crashing an activity cost $40 per hour ($320 per 8 hour work day). 1.Develop a project network diagram that shows all the activities and precedence relationships. 2. Determine the project length (without crashing). 3. Determine the critical path activities. 4. Determine the crashing cost if the project must be finished in 16 days, 18 days, and 21 days?
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.