11- What is the time to complete the project that achieves the probability of its magnitude? 16.5
Q: 13.39 Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1.000, is…
A: Earned Value (EV) is the sum of percentage completed multiplied by the task budget. The calculation…
Q: The Mama Lit is a restaurant near a project site and it is a direct supplier of food for the nearby…
A: a) Network Diagram
Q: Part d. Please answer asap, thanks!! The owners' corporation of a residential estate has decided to…
A: The contract can be defined as an agreement between two or more people to do something. In order for…
Q: State the importance of Business Project and the types of it along with examples.
A: Small Introduction about Business Project A project is a group of tasks that must be completed. In…
Q: a) What is the probability that the project can be completed in 25 days or fewer?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: Describe the other impacts on the project, such as quality, resources and risks.
A: Risk is the possibility of uncertainty that affects the related material, resources, management, or…
Q: a. What is the length of the critical path? Length of the critical path hours
A: Below is the solution:-
Q: 2. Reduce job 3 by two days. ONo O Yes 3. Reduce job 5 by two days. Yes O No e. What is the…
A: Given Information: Critical Path:- 1-2-5-8-9-11 Expected Completion Time:- 26.5 days
Q: What is the use of Gantt charts in project management?
A: A Gantt chart is a kind of bar chart used to visually depict a project schedule. It can be said as a…
Q: Question 37 How much slack is there in task A? Your Answer: Your Answer Question 38 If the crash…
A: Slack is the available time in a activity for delaying the project without affecting the total…
Q: What is the critical path? By how many weeks are we 90% sure of completing the project (along the…
A: A project network diagram is a graph that shows the sequence in which a project's activities are to…
Q: What is the completion time ?
A: Completion time is the time when the project completes all the activities involved and accomplish…
Q: predictions regarding Tom's next move
A: Tom Bray was thinking about the present plan for getting work done as he looked across the cove at…
Q: Determine the critical path, and how many weeks will the project take to complete, suppose D could…
A: To find a critical path, one needs to first find all the possible paths to finish the project from…
Q: Consider the project crashing information presented in Figure 8-4. What is the cost to complete this…
A: Project duration is the total time taken to complete the project successfully measurable in days or…
Q: Izzi used a project management softwäre package and has determined the following results for a given…
A: Expected completion time of the project: μ=22 days Variance of Project: σ2=2.77 days Standard…
Q: Case: Tom Bray Tom Bray was mulling over today’s work schedule as he looked across the bay at the…
A: Management by Wandering Around (MBWA) is a management style that employs an ad hoc approach and…
Q: For the project data shown in the table below. Find The expected time to complete 77 % of the…
A: Given data: To find the expected time to complete 77% of the project M=2*O P=3*0 Activity…
Q: c. What is the expected project completion time? (Do not round intermediate calculations. Round your…
A: Find the duration calculations below:
Q: d. Determine the probability that the team and the contractor will be in place and the project…
A: Based on the 3-time estimates given, we find the Expected duration and Variance for each activity as…
Q: Three activities are candidates for crashing on a projectnetwork for a large computer installation…
A: Critical path is the sequence of dependent tasks that form the longest duration, allowing you to…
Q: How does the Work Breakdown Structure differ from the project network?
A: Work Breakdown structure is the clear breakdown of the entire working processes of the project into…
Q: completion time is 31 weeks. What is the be nuch will it cost? Show your work. Activity Expected…
A: Given: Each company takes 1 week to complete the project. Cost per activity to crash is $200…
Q: (f) What is the largest number of weeks allotted to finish the electrical wirings without delaying…
A: Below is the solution:-
Q: What are the Main obstacles for construction sector to adopt the internet in managing project
A: Project management It is the process of organizing and arranging a company's resources to complete a…
Q: What is project management software and what are the advantages and disadvantages? Diagrams?
A: Project management is not an easy task. There are a lot of steps and functions involved in project…
Q: Task Name Normal time Normal Crash time Crash cost (slope) Predecessor cost 4. 85 3. 10 5. 100 4. 30…
A: We are using Forward pass method to solve below problem. Forward pass is a strategy to push ahead…
Q: activities, of which are on the critical path. If the estimated time along the critical path is 214…
A: We have for the estimated time, Mean = 214 Variance = 169
Q: for improvemen
A: WBS refers to the Work Breakdown Structure. The structure squares of a timetable beginning with a…
Q: When Salem Zahri took the green light to start the constructions, he made all necessary arrangements…
A: In the given case is a Salem Zahri took the green light to start the constructions, he made all…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (μ)= 40 weeksDesired completion time (x) = 46 weeks or…
Q: days. Carl's team should be able to complete the project in
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: The VOX Cinema is installing a new system to enhance the quality of movies shown. Several things…
A: Formula:
Q: Name the information contained in the work plan ?
A: A work plan consists of the objectives and processes by carrying out which a team or an individual…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Mean (x) = 40 weeks Desired completion time (μ) = 40 weeks Variance (σ2) = 9 weeks
Q: A renovation of the gift shop at Orlando Amway Center has six activities (in hours). For the…
A: Given data is
Q: The possibility of completing the project in less or equal time The critical path plus 2 weeks is 95…
A:
Q: John, Jack and Jill are project managers for Jusco Company. All three of them lead their own team,…
A: Efficiency and Effectiveness are not similar to each other. The term efficiency refers to completing…
Q: What can the project manager offer to other departments to make the situation a win-win?
A: A project manager is responsible for the smooth execution of the projects but it will be difficult…
Q: a. Why is risk identification important to a project? b. Give 3 examples how IT/MIS tools can…
A: Risks are unexpected events that might affect the business either in a positive or negative manner.…
Q: 2. Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of…
A: A Project Evaluation and Review Technique (PERT) is a device that projects the board uses to deal…
Q: Whitbread World Sailboat Race Question: Their rationale for project crashing. The relationship…
A: Here are some basic reasons for project crashing: Commanded deadline in which disfavor will be…
Q: 1. What is the expected (estimated) time for each activity? 2. Based on the calculation of estimated…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: To ensure project can be done with the available resources, time and budget is termed as
A: Introduction In human resource management , while creating plan for project there are various roles…
Q: The project shown within details what is the possibility t finish the project in 38 days? And what's…
A: Given that: Activity a m b 1 to 2 2 7 8 2 to 3 5 6 9 2 to 4 3 7 8 2 to 5 4 5 6 3 to 6…
Q: What is the earliest completion time of the project? days
A: A project network diagram is the process of a project shown visually. It is a diagram that has boxes…
Q: Determine the critical path of the following table using the Gantt chart. Activity Preceded by…
A: Here, we have got the data in tabulated form, this tabulated data includes activity Id, Predecessor,…
Q: 1- The number of critical paths in the project is All options are incorrect O
A: One of the methods to find the longest duration that a project would take to complete is the…
Step by step
Solved in 4 steps with 4 images
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 6 - E 5 BB 8 - F 6 BC 2 A G 9 C, ED 3 A H 7 D , F Dave's earilest start (ES) and earliest finish (EF) are: Activity ES EF A 0 6 B 0 ? C D E F G HI need a detailed explanation and assistance to solve this problem: A company decides to plan a project, with activities, precedences and random duration statistics given in the following table: Activity Immediate Predecessors Duration Minimum (weeks) Duration Mode (weeks) Duration Maximum (weeks) A none 2 5 9 B A 1 6 8 C A 3 5 12 D B 2 4 12 E B, C 4 6 8 F B 6 7 8 G D, E 1 2 6 H F, G 4 6 16 * What method should be used? Compute the mean and variances for each activity and add them to the table above * Draw the project network and label the arcs with the activity name. * Assuming that the critical path is AàBàP1àEàGàH, compute the probability that this path duration is between 28 weeks and 32 weeks. * Assuming that the critical path is AàBàP1àEàGàH, compute the number of weeks within which the project will be completed with probability 0.95.Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?
- Project 1-3: Creating a Project Schedule for Hiring a New EmployeeIn this project, you will create a project schedule for the process of hiring a new employee for your department. GET READY. OPEN a new blank project schedule. Set the project start date to be October 21, 2019.Enter the following tasks and durations:Task DurationWrite job description 2dNotify departmental recruiter 1dPost job internally 5dPost job externally 5dCollect résumés 10dReview résumés 5dSet up interviews 3dConduct interviews 8dSelect candidate 1dMake offer milestoneAssign a finish-to-start relationship to all the tasks.Change the relationship between tasks 3 and 4 to a start-to-start relationship.Auto-fit all the columns and rows.Change all tasks to the Automatically Scheduled mode.Use the statistics button on the Project Information dialog box to determine the current project duration.SAVE the project schedule in the solutions folder for this lesson as Hiring Employee xxd where…Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the 13th day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedence relationships are given in Table. Electric Motor Project Data Activity Normal Time(days) Normal Cost ($) Crash Time (days) Crash Cost ($) ImmediatePredecessor(s) A B C D E F G H 4 7 5 6 3 11 4 3 1000 1400 2000 1200 900 2500 800 300 3 4 4 5 2 6 3 1 1300 1200 2700 1400 1100 3750 1450 500 None None None A B C D,E F,G a. Draw the project network diagram.b. What completion date would you recommend?You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…
- You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 4 B B 6 − F 5 B C 4 A G 10 C, E D 2 A H 8 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…To design a new app, a project manager has gathered the time information foreach activity as shown in the following table:Activity Predecessors Optimistic Most Likely PessimisticA / 1 4 7B / 2 6 10C B 3 3 9D A 6 13 14E A, C 4 6 14F B 6 8 16G D,E,F 2 5 8Identify the critical path. How much slack time is associated with each noncritical activity?Suppose you wanted to have 99% confidence in the project finishing on time. How manyweeks in total would your project team need to achieve this 99% likelihood?
- CPMGT 300 week 3 discussion question 1Week Three Discussion Topic One1 The Statement of Work and the Requirements Document of the project planning process are two components of delivering a product or service. Define these components and their relevance to the planning process. What might these two planning components have in common? What are their differences? Explain your answer. ………….Answer Preview………….Three Discussion Topic OneStatements of work (SOW) is referred to as a formal document that defines and capture the work activities timelines and deliverables a vendor need to execute in performance of a particular job for a client. The statement includes various detailed pricing and requirement together with a standard regulatory as well as terms and conditions of government. Requirement document is defined as………APA155 Words Added to cartDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 5 B B 8 − F 6 B C 4 A G 11 C, E D 3 A H 7 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…This project has the following activities that need to be completed (see Table below) a) Draw the AOA and AON diagrams b) Find the critical path in AOA and AON Diagrams. Show calculations and table. c) Find the completion time. Show calculations d) Find the duration of each activity. Show calculations e) Show the predecessors in a table format. Activity TE AB 1 AC 3 AD 3 DC 4 CB 3 DE 8 CF 2 BF 4 IJ 2 CE 6 EF 5 FG 10 FH 11 EH 1 GH 9 EJ 3 GI 8 HJ 6 .