14. A contractor undertook to complete a piece of work in 120 days and employed 140 men upon it. At the end of 66 days only half of the work was done, so he put on 25 extra men. By much time did he exceed the specified time? (a) I (d) 4 (c) 3 (b) 2 of work
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Pressure and stress
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,