3.36. A site consists of 3 m thick loose sand with an in- "situ void ratio of 0.75. The laboratory tests show that the maximum and minimum void ratios of the sand are 0.85 and 0.50, respectively. Based on the b or field SPT value of 5, this soil will be liquefiable at an earthquake magnitude of 6.5. Vibrocompaction method with granular backfill is proposed to densify to this soil. Assume the diameter of granular columns is 0.75 m. To minimize the liquefaction potential, the t densified soil should have an SPT N value of 20, which h u corresponds to the relative density of 70%. Assume the A ground settles 40 mm after the densification. Find the oira required spacing of granular columns.

Fundamentals of Geotechnical Engineering (MindTap Course List)
5th Edition
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Braja M. Das, Nagaratnam Sivakugan
Chapter11: Ground Improvement
Section: Chapter Questions
Problem 11.6P
icon
Related questions
Question
3.36. A site consists of 3 m thick loose sand with an in-
situ void ratio of 0.75. The laboratory tests show
that the maximum and minimum void ratios of the
sand are 0.85 and 0.50, respectively. Based on the
field SPT value of 5, this soil will be liquefiable
at an earthquake magnitude of 6.5. Vibrocompaction
method with granular backfill is proposed to densify
this soil. Assume the diameter of granular columns
is 0.75 m. To minimize the liquefaction potential, the
st densified soil should have an SPT N value of 20, which
corresponds to the relative density of 70%. Assume the
ground settles 40 mm after the densífication. Find the
required spacing of granular columns.
om
21
Transcribed Image Text:3.36. A site consists of 3 m thick loose sand with an in- situ void ratio of 0.75. The laboratory tests show that the maximum and minimum void ratios of the sand are 0.85 and 0.50, respectively. Based on the field SPT value of 5, this soil will be liquefiable at an earthquake magnitude of 6.5. Vibrocompaction method with granular backfill is proposed to densify this soil. Assume the diameter of granular columns is 0.75 m. To minimize the liquefaction potential, the st densified soil should have an SPT N value of 20, which corresponds to the relative density of 70%. Assume the ground settles 40 mm after the densífication. Find the required spacing of granular columns. om 21
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Methods of ground improvement
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Principles of Geotechnical Engineering (MindTap C…
Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning