• 3.8 management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: Roger Ginde is developing a program in supply chain IMMEDIATE АСTIVITY PREDECESSOR(S) TIME (DAYS) A 2 B 1 10 E A, D 3 F 6 G Е, F 8 a) Develop an AON network for this problem. b) What is the critical path? c) What is the total project completion time? d) What is the slack time for each individual activity? Px

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
icon
Concept explainers
Topic Video
Question
Roger Ginde is developing a program in supply chain
management certification for managers. Ginde has listed a num-
ber of activities that must be completed before a training program
of this nature could be conducted. The activities, immediate pre-
decessors, and times appear in the accompanying table:
3.8
IMMEDIATE
АCTIVITY
PREDECESSOR(S)
TIME (DAYS)
A
2
5
1
10
A, D
3
F
G
E, F
8
a) Develop an AON network for this problem.
b) What is the critical path?
c) What is the total project completion time?
d) What is the slack time for each individual activity? PX
6.
B.
B.
E.
Transcribed Image Text:Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: 3.8 IMMEDIATE АCTIVITY PREDECESSOR(S) TIME (DAYS) A 2 5 1 10 A, D 3 F G E, F 8 a) Develop an AON network for this problem. b) What is the critical path? c) What is the total project completion time? d) What is the slack time for each individual activity? PX 6. B. B. E.
Expert Solution
Introduction

"Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for you. To get remaining sub-part solved please repost the complete question and mention the sub-part(s) to be solved."

AON stands for Activity on Node. It is a network diagram that denotes the activities on nodes. There are arrows between activities to show the dependencies of one activity on the other.

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning