9. The following information is given for a CPM network: Activity Predecessor Successor Normal Time Normal Cost Crash Time A $60 B C D A A, B B, C B. 14 OC. 16 D. 11 B, C D. C D # 5 4 63 70 80 40 2 23 What's the normal project completion time, given the information in the table? Crash Cost $125 90 150 60
Q: The following is given: Price Variable cost Fixed cost $8.00/unit $4.00/unit $50,000 a) Based on the…
A: Break-even point relative with many fields such as business, finance and so on. It is that point…
Q: Referring to the above problem, solve it by the vogel approximation method
A: The transportation model is used to calculate the minimum cost of the route by selecting different…
Q: A cafeteria serving line has a coffee urn from which customers serve themselves. Arrivals at the urn…
A: Given data is Arrival rate (lambda) = 2 per minute Service rate (mu) = 25 seconds = 6025=2.4 mins
Q: Thermostats are subjected to rigorous testing before they are shipped to air conditioning…
A: Control chart is a statistical tool which helps t identify the process controllability based on…
Q: a production company that sells two types of gasoline, G1 and G2, from two types of crude oil, C1…
A: Two types of gasoline are prepared from two types of crude oils. Hence, the decision variables must…
Q: (a)Determine the economic order quantity and total annual cost (in $) under the assumption that no…
A: NOTE: We are allowed to do one question only at a time. EOQ = 2*D*SH((H+b)b)Annual ordering cost…
Q: why use a deliverable orientated WBS to build a greenhouse
A: A greenhouse is a structure whose walls and roof are made up of a transparent material like glass. A…
Q: Wilson Publishing Company produces books for the retail market. Demand for a current book is…
A: A company's ability to manage its inventory is directly correlated to its ability to predict what…
Q: Create a service blueprint for customer support. It can be any company you'd like.
A: A service blueprint is a concept that helps to design and deliver services in the best way possible.…
Q: IN THE MID-1960S, WALT DISNEY’S DREAM was to build a family resort destination like no other. The…
A: Forecasting is a technique to predict future value. It is useful to predict future demand, sales, or…
Q: Given the following payoff table (in K million), about a cooking oil producer in Lusaka. The company…
A: Given data is
Q: Find the critical path. (Enter your answers as a comma-separated list.) (b) What is the…
A: NOTE: We are allowed to do first 3 sub-parts only. Critical path method is a project management…
Q: Bobby, another enterprising barber, is thinking about advertising in the local newspaper because he…
A: Assume that service is distributed exponentially and that client arrival is Poisson distributed.…
Q: (a) Formulate a linear programming model for maximizing total profit contribution. (Let P, units of…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Niue Vanilla has had two successive years in which the Vanilla bean harvest has stretched the firm’s…
A: The expected value of perfect information is the probability that the decision-maker would choose a…
Q: RE-THINKING OPERATIONS IN THE NEXT NORMAL Operations functions—including procurement, supply chain,…
A: The challenges identified in the given data are explained below. Day-to-day operations: - The daily…
Q: Develop a Pareto chart of the following causes of poor grades on an exam: Number 1 2 3 4 5 Choose…
A: I have entered the given Data: Now Arrange the above data from High to low, i.e. Highest Frequency…
Q: the recommendation for this case study
A: The case describes a company from its initial stage to how it grew. The operations and functions of…
Q: 1.What are the decision variables 2.What is the objective functions 3. What are the 11 constraints…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: I need help with the multifactor productivity formula Facility processed 240 orders per hour…
A: Multifactor productivity is a theory that studies the relationship between the factors of…
Q: Use the following Excel output to answer the following questions. a) Write only the objective…
A: Sensitivity report is a tabular representation of results derived from sensitivity analysis. Report…
Q: Consider the following Harley’s current network design with direct shipment. Harley Davidson…
A: Mr. H purchases products from three suppliers. He uses a full truckload strategy. In full truckload,…
Q: 6. Schmidt Industries makes four different snake traps; the Harlan, the Gaylen, the Leah and the…
A: Find the profit for each trap as shown below: Profit = Selling price - (total cost) Total cost =…
Q: Explain how to run a company with good structure and quality management as a operation manager with…
A: The things an operation manager follows to run a company with a good structure are -: 1. To look…
Q: C-Spec, Inc., is attempting to determine whether an existing machine is capable of milling an engine…
A: Process capability index is the part of statistical tool which analysis the ability of the process…
Q: Jake, a project manager for XYS Company, is developing the project plan for the implementation of a…
A: The cost, choice, and timeline associated with the work are factors that the supervisory committee…
Q: Where are the changing cells located? Multiple Choice O O B2:D2 B10:D10 B2:D2, B4:D7, and G5:G7 G10
A: From the above table, we could find it as a Linear programming problem, here, the main purpose would…
Q: Summary of this case study, and the recommendation for this case study
A: The company was started when the owner was studying and the company earned high revenue ($100,000)…
Q: manufacturing-Production Planning A mining company owns 2 different mines that produce ore, which is…
A: The objective for any linear programming problem including cost is to reduce the cost, if it…
Q: Company X is the leading producer of state-of-the-art printers. They have been developing a layout…
A: Organizations are daily getting indulged in their complex operations that bring about a big change…
Q: Define quality and how important it is in operation management
A: Here, As per the question, I would prepare the definition for Quality and then, I would explain how…
Q: The Healthy Chocolate Company makes a variety of chocolate candles, including a 12-ounce chocolate…
A: It measures the capability of the process in terms of its consistency in average performance. In…
Q: Explain the key aspects of operation management decision making
A: According to the business definition, operations management is the design, execution, and control of…
Q: A company is considering three vendors for purchasing a CRM system: Delphi Inc., CRM International,…
A: Decision analysis is the approach to selecting the best alternative based on the available…
Q: A) Draw the network diagram. B) Determine the normal time it will take to complete this project. C)…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Problem #1 Name: Frank Smith Date 4/6 4/7 4/8 4/9 4/10 4/11 In 8:00 8:00 7:45 7:45 8:15 10:00 Out…
A:
Q: Solve the following linear program by the solver method
A: Linear Programming is a statistical and mathematical technique used in operations management.…
Q: The production process shown below consists of five stages. The numbers in parentheses are the times…
A: Find the Given details below: Given details: Stage Time taken for an unit A 4 minutes B 3…
Q: Hart Manufacturing makes three products. Each product requires manufacturing operations in three…
A: As per the given instructions, the decision variables are as follows. P1 = Units of product 1…
Q: If a manager wishes to group like machines and equipment together to accommodate a wide variety of…
A: Layout refers to the systematic procedure of installing workstations and skilled staff collectively…
Q: Calculate the forecasted sales revenue for May using the following data. Month Sales…
A: Here, the data set contains the month column and sales revenue column, the dataset table is…
Q: What is the optimal order quantity for MBC? (b) How frequently should MBC order to replenish the…
A: EOQ = √(2DS/H) Number of orders = D/Q Maximum inventory = Reorder point+ EOQ Reorder point = (D/W)*L
Q: a. A loan processing operation that processes an average of 7 loans per day. The operation has a…
A: The utilization ratio is the percentage of time that a system is running. The efficiency ratio is…
Q: Consider the following transshipment network for finding the shortest route from node 1 to node 7.…
A: In the network model, the total flow of input and total flow of output must be the same. Consider…
Q: 11. The distribution system for the Herman Company consists of three plants, two ware- houses, and…
A:
Q: explain the transformation process in a hotel resort
A: The transformation process of operations in a hotel resort is a complicated process. It involves…
Q: ABC Ltd Company is in the process of preparing a budget for launching a new product. The following…
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: predictive, and prescriptive. Describe each of those. Imagine you are a data analyst in FedRetail,…
A: Business analytics is the process through which businesses use technology and statistical methods to…
Q: Why do we say Inventory can become a liability? Provide 2 situations creating this risk
A: "Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: Activity A B с D E F G H Earliest Start C r r DIC DIC 1 Latest Start Earliest Finish Latest Finish…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 1 images
- Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way. Activity NormalTime(weeks) NormalCost ($) CrashTime(weeks) CrashCost ($) MaximumweeksReduced CrashCost perWeek ($) A 3 500 2 900 1 400 B 4 600 3 700 1 100 C 6 800 3 1,286 3 162.00 D 6 1,500 4 2,150 2 325 E 6 1,750 4 2,250 2 250 F 5 1,200 5 1,200 0 0 G 7 1,500 5 1,794 2 147 H 3 500 3 500 0 0 Reduce G by select a number of (1-4) week(s), C by select a number (1-4) of week(s), at a cost of $ __________ enter a dollar amount .Reliable Garage is completing production of the J2000 kit car.The following data are available for the project:Activity Activity Time (days) Immediate Predecessor(s)A 2 —B 6 AC 4 BD 5 CE 7 CF 5 CG 5 FH 3 D, E, Ga. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?10. The project described in the following table is scheduled to be completed in 11 weeks. Constructa network diagram using AOA or AON (see Example 5 for either type). Then answer the followingquestions:a. If you were the manager of this project, would you be concerned? Explain.b. If there is a penalty of $5,000 a week for each week the project is late, what is the probabilityof incurring a penalty of at least $5,000? Path Activity Estimated time(Weeks) Std. Dev(Wks) A C 4 0.7 D 6 0.9 B E 3 0.62 F 9 1.9
- The VOXN Cinema is installing a new system to enhance the quality of movies shown. Assume that the following table provides information on the immediate predecessor relation and time estimated for each event. a.List the possible eight events which you think essential in expanding a Cinema.b. Draw a network diagramc.find the total time required to complete the project d. List the critical events of the project. Activity immediate predecessor Time (weeks) A - 3 B - 4 C A 6 D B 2 E A 5 F C 2 G D , E 4 H F , G 5The project described in the following table is scheduled to be completed in 11 weeks. Constructa network diagram using AOA or AON (see Example 5 for either type). Then answer the following questions:a. If you were the manager of this project, would you be concerned? Explain.b. If there is a penalty of $5,000 a week for each week the project is late, what is the probabilityof incurring a penalty of at least $5,000?Path ActivityEstimated Time(weeks)StandardDeviation (wks.)A C 4 0.70D 6 0.90B E 3 0.62F 9 1.90The Advanced Tech Company has a project to design an integrated information databasefor a major bank. Data for the project are given in Table Q2 below. Indirect project costsamount to $300 per day. The company will incur a $150 per day penalty for each day theproject lasts beyond day 14.(a)What is the shortest time duration and cost for this project?B)What is the total cost and time of the minimum-cost schedule?
- For the next project: | | TIME ESTIMATE (WEEKS) TASK DESCRIPTION a m b A foundations 2 3 4 B framework 4 7.5 8 C roofs 3 5.5 11 D plumbing 2.5 4 5.5 E electrical wiring 2 3 4 F doors and windows 3 5 7 G interior finish 3 3.5 7 H exterior finish 2 5 8 I inspection 1 1 1 a. I made the network diagram. b. Calculate the parameters corresponding to expected time, variance, nearest and farthest start times and farthest c. What is the probability of meeting a specific project completion date? For example, what is the probability of building the house in 32 weeks? Topic: stochastic processesDraw the PDM network diagram for the following project, calculate the earliest and latest starting and finishing times for all activities, and hence calculate the total float, free float for each activity. Activity IPA Duration (WEEKS) WORKERS REQUIRED PER WEEK EQUIPMENT REQUIRED (hrs/WEEK) H ---- 10 5 8 I H 8 4 2 J H 6 8 6 K J 4 2 1 L J 2 6 2 M J 4 3 2 N I 4 2 0 O I 5 5 0 P I, J 5 6 6 Q L 5 2 0 R M 5 0 4 S N 3 0 4 T Q 3 0 0 U O, S 1 9 8 V K, R 5 14 8 W U 2 6 8 X V 3 6 8 Y P,W,X,T 8 14 8 Z Y 6 5 8 If there is a limit of 15 workers per week, smooth the workers loading using ES and LS histogram. Based on the proposed scheduling, plot the equipment loading histogram for the project. Independently of the above resource leveling, schedule the…A potential project has an initial capital investment of $100,000. Net annual revenues minus expenses are estimated to be $40,000 (A$) in the first year and to increase at the rate of 6.48% per year. The useful life of the primary equipment, however, is uncertain, as shown in the following table: Assume that im = MARR = 15% per year and f = 4% per year. Based on this information, Solve, a. What are the E(PW) and SD(PW) for this project? b. What is the Pr{PW ≥ 0}? c. What is the E(AW) in R$? Do you consider the project economically acceptable, questionable, or not acceptable, and why?
- Dave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managersThe table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities. Activity Preceding Activity Expected Time (ET) A - 7 B A 9 C A,B 5 D C 17 E C 12 F C 7 G D,E,F 10 H D,G 7 Construct a network diagram ,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST). If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?The following information is given for a CPM network: Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost A --- B, C 5 $ 60 2 $ 125 B A D, C 4 70 2 90 C A, B D 6 80 3 150 D B, C --- 3 40 1 60 What is the critical path of the network?