a) Based on the activity time estimates, the expected times and variance for each of the activities are: (Round your responses to two decimal places.) Activity A B C D E F G H I K Expected Time ☐☐☐☐☐ Variance 000000ooooo

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion​ time, the most likely completion​ time, and the pessimistic completion time​ (all in​ days) for a new contract are given in the following​ table:

                                                                               

 

Time ​(days​)

 

 

 

 

 

Immediate

Activity

a

 

m

 

b

 

Predecessor(s)

A

4

 

6

 

8

 

B

10

 

11

 

12

 

C

1

 

2

 

3

 

D

7

 

8

 

9

 

C

E

1

 

3

 

5

 

B, D

F

1

 

2

 

3

 

A, E

G

6

 

10

 

13

 

A, E

H

10

 

11

 

12

 

F

I

4

 

6

 

8

 

G

J

14

 

16

 

18

 

C

K

5

 

9

 

13

 

H, I

This exercise contains only part a.

Part 2

​a) Based on the activity time​ estimates, the expected times and variance for each of the activities​ are:

​(Round your responses to two decimal​ places.)

 

 

 

 

 

 

 

 

 

Part 3

 

 

 

 

Part 4

 

 

 

 

Part 5

 

 

 

 

Part 6

 

 

 

 

Part 7

 

 

 

 

Part 8

 

 

 

 

Part 9

 

 

 

 

Part 10

 

 

 

 

Part 11

 

 

 

 

Part 12

 

 

 

 

 

Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very
unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table:
Activity
ABCDEFGH - Y
с
a
J
4
10
1
7
1
1
6
Time (days)
m
6
11
2
8
3
2
10
ܝ ܗ ܗ ܘ
Immediate
b Predecessor(s)
w ∞ ∞ Ñ w wo ero w Ñ ∞
12
10
4
14
K 5 9 13
13
12
8
18
C
B, D
A, E
A, E
F
G
C
H, I
Transcribed Image Text:Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: Activity ABCDEFGH - Y с a J 4 10 1 7 1 1 6 Time (days) m 6 11 2 8 3 2 10 ܝ ܗ ܗ ܘ Immediate b Predecessor(s) w ∞ ∞ Ñ w wo ero w Ñ ∞ 12 10 4 14 K 5 9 13 13 12 8 18 C B, D A, E A, E F G C H, I
a) Based on the activity time estimates, the expected times and variance for each of the activities are:
(Round your responses to two decimal places.)
Activity
A
B
CDEF I - -
G
H
K
Expected Time
Variance
Transcribed Image Text:a) Based on the activity time estimates, the expected times and variance for each of the activities are: (Round your responses to two decimal places.) Activity A B CDEF I - - G H K Expected Time Variance
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.