a) Draw the network diagram. What is the project completion time? What is the critical path? b) Crash activity B by one day. What is the new project completion time?
Q: The following table provides the information necessary to construct a project network diagram and…
A: Project crashing is a process which reduces the total duration using additional costs. Here, we can…
Q: A2 A4 A5 A3 Task Duration (days) 3 A1 3 A2 A3 1 A4 A5 days What is the late finish time for activity…
A: Using the Forward Path Early Start of the activity = Early Finish of predecessor activity Early…
Q: B. What is the expected project completion time? 7 weeks 8 weeks 9 weeks 6 weeks C. Which are the…
A: In this question, I would construct the Gantt chart based on the given Activity ID, Activity…
Q: a. Draw a project network. b. What is the critical path? c. What is the normal project cost? d.…
A: Find the Slope calculations below:
Q: SESSION 2– Individual exercise (for marks) Given the following activity precedence table, please…
A: The question is related to Critical Path Analysis. The details are given.
Q: A) Draw the Gantt Chart B) Draw the Network Diagram C) Identify and draw the critical path using the…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: a. Construct the network. b. How long will it take to finish the project? c.. What is the critical…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Ql: For activitices shown in table below, find the new time of project after updating, if the…
A: Given data is
Q: a. Draw the project network diagram. b. What completion date would you recommend?
A: Below is the solution:-
Q: 1. Draw the project network 2. What is the expected time for activity B? 3. What is the variance for…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Norton Industries is installing a new computer system. The activities, the activity times, and the…
A: Crashing an activity is basically adding more assets toward an activity so it tends to be finished…
Q: • Q1: Determine the critical path, the critical activities and the project completion time.…
A: A project network diagram is the visual representation of the project activities and their durations…
Q: Draw the Network Diagram and determine the Critical Path and duration of the project (in days).…
A: Given Information:
Q: Consider the following data for a project to install a new server at the Northland Pines High…
A: a.
Q: 1. Construct the activity-on-node network. 2. Identify the critical path. 3. Compute the duration of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: lease complete the ES, EF, LS, LF, and slack for the project below. Activity Description
A: Early start (ES) indicates the earliest time of the beginning of the activity. Early finish (EF)…
Q: The following information has been gathered for a project to install a new machine lathe at Diamond…
A: a.
Q: Consider the following data for a project to install a newserver at the Northland Pines High School:…
A: The critical path method, or critical path analysis, refers to an algorithm which is used for…
Q: a. Determine the expected time (t,) for each activity. 5. Identify the critical path(s) c. What is…
A: Answer is as below:
Q: Given the activities whose sequence is described by thefol lowing table, draw the appropriate…
A: Critical path refers to the stage sequences, that require maximum time for the project completion.
Q: The Omega department is planning to bid on large project for the development of a new communication…
A:
Q: a) Construct a Gantt chart using MS Project 2016 b) Assuming the default 5-day workweek, calculate…
A: This question is related to the topic of Project Management and this topic falls under the…
Q: oger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: The project network is the diagrammatic form in which project activities and their durations are…
Q: Example: - 02) Activities of a project with estimates of activity times are listed below. Activity…
A: In order to calculate the expected time, the following formula is used. Expected time =Optimistic…
Q: Enrichment Exercise 7.2 Promoter of championship boxing match must perform the task shown in the…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: The Scott Corey accounting firm is installing a new computer system. Several things must be done to…
A: The method of analyzing the set of activities related to the project of the company is known as the…
Q: Build a PERT Analysis for a 3-month project with 6 activities (A to F) and 5 nodes
A: The PERT Method (or Program Evaluation and Review Approach) is a standard network analysis…
Q: The following information has been gathered for a project to install a new machine lathe at Diamond…
A: a.
Q: able Activities Name A E Predecessor A А, В D C, E Time (Days) 7 9 12 9.
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: a. Draw a network diagram and determine the expected project completion time b. What is the…
A: Below is the solution:-
Q: a) Develop a network diagram for the project. Identify the critical path. b) If the company would…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Activity Predecessor Time(weeks) A 8 B A 6 4 D E A 11 F B 3 D, E, F 1 Using Table A, what is the…
A: Network Diagram,
Q: PM.58 Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities…
A: Forward Pass:Early Start (ES) = Maximum (or Highest) EF value from immediate Predecessor(s)Early…
Q: A. (5 points) Draw AON diagram of the project, including activity durations. B. (4 points) Based on…
A:
Q: Answered all given questions as below. Value for A and B will be determined by your unique id as per…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(a, b,…
Q: Task time estimates for a production line setup project at XYZ Company are as follows; Activity Time…
A: We are authorized to answer three subparts at a time since you have not mentioned which part you are…
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A:
Q: 2. Consider the data given in the following table and give what is asked. Immediate Normal Time…
A: Find the Given details below: Activity Predecessor Original duration (NT) (Days) Original cost…
Q: Below matrix shows one of the important data used in project management, identify the name of the…
A: The matrix shown in the question is named as RACI Chart or RACI Matrix. The RACI Chart or RACI…
Q: Given the activities whose sequence is describedby the following table, draw the appropriate…
A: Draw the path
Q: a) Draw the project network using AON. b) Identify the critical path. c) What is the expected…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 1. Determine the amount of slack in each of a proiect's activities (presented below), and identify…
A: Formula:
Q: 1. What is the expected (estimated) time for each activity? 2. Based on the calculation of estimated…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 2. Determine the amount of slack in each of a project's activities (presented below), and identify…
A:
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: Construct a network diagram b. State the expected finish time and critical path of the project
A: A network diagram is a graphical representation of a project which visualizing the activity…
Q: a. Construct the project network b. Determine the critical path c. Find the completion time of the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 6 - E 5 BB 8 - F 6 BC 2 A G 9 C, ED 3 A H 7 D , F Dave's earilest start (ES) and earliest finish (EF) are: Activity ES EF A 0 6 B 0 ? C D E F G HYou are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network given the information in the table that follows. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calcu-late the free slack and total slack for all noncritical activities.ID Description Predecessor Time (days)A Systems design None 2 B Subsystem A design A 1C Subsystem B design A 1D Subsystem C design A 1E Program A B 2F Program B C 2G Program C D 2H Subsystem A test E 1I Subsystem B test F 1J Subsystem C test G 1K Integration H, I, J 3L Integration test K 1
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?Given the following project: Activity Predecessor Normal Time (day) Normal Cost ($) Crash Time (day) Crash Cost ($) A - 4 800 2 1300 B - 10 1200 7 2400 C A 6 1100 4 1700 D A,B 7 1000 4 1600 E C 10 2000 8 3000 F C,D 5 900 - - (a) Draw the network and find the critical path duration of the project, total cost of project using normal times. (b) Calculate the maximum time reduction and crash cost-per-day (all activities may be partially crashed) for each activity. Then fill the table below. (Note: Activity “F” cannot be crashed) Activity Maximum Time Reduction (day) Cost to Crash per Period ($/day) A B C D E F (c) Find the optimal way of getting a 20-day delivery time. What is the project cost? (d) Find the optimal way of getting a 18-day delivery time. What is the project cost?Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way. Activity NormalTime(weeks) NormalCost ($) CrashTime(weeks) CrashCost ($) MaximumweeksReduced CrashCost perWeek ($) A 3 500 2 900 1 400 B 4 600 3 700 1 100 C 6 800 3 1,286 3 162.00 D 6 1,500 4 2,150 2 325 E 6 1,750 4 2,250 2 250 F 5 1,200 5 1,200 0 0 G 7 1,500 5 1,794 2 147 H 3 500 3 500 0 0 Reduce G by select a number of (1-4) week(s), C by select a number (1-4) of week(s), at a cost of $ __________ enter a dollar amount .
- Office Automation, has developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities that must be ac- accomplished to complete the new office-system project. Information about the activities is shown below where times are in weeks and costs are in thousands of dollars. NOTE: The crashing cost given in the last (seventh) column of the table below is the total cost to finish an activity by its minimum time given in the fifth column.The project described in the following table is scheduled to be completed in 11 weeks. Constructa network diagram using AOA or AON (see Example 5 for either type). Then answer the following questions:a. If you were the manager of this project, would you be concerned? Explain.b. If there is a penalty of $5,000 a week for each week the project is late, what is the probabilityof incurring a penalty of at least $5,000?Path ActivityEstimated Time(weeks)StandardDeviation (wks.)A C 4 0.70D 6 0.90B E 3 0.62F 9 1.90The table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities. Activity Preceding Activity Expected Time (ET) A - 7 B A 9 C A,B 5 D C 17 E C 12 F C 7 G D,E,F 10 H D,G 7 Draw a network diagram for the IS project shown above.,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST). If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?
- The table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities. Activity Preceding Activity Expected Time (ET) A - 7 B A 9 C A,B 5 D C 17 E C 12 F C 7 G D,E,F 10 H D,G 7 Construct a network diagram ,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST). If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?A solved PERT problem is detailed in the table below. The expected time and variance values and the critical activities are given in the table below. Answer the following questions by filling the blanks (WRITE YOUR ANSWERS TO 2 DECIMAL PLACES. DO NOT ROUND UP OR DOWN): a. The expected project completion time for this problem is and the standard deviation is . b. There is a 0.95 probability that the project will be completed by weeks. Activity Expected time Variance Critical? A 10 0.36 Yes B 7 0.11 No C 7 0.25 No D 3 0.48 Yes E 5 1.60 Yes F 7 0.69 No G 2 3.69 YesPlease, I need help because I have no idea how to do any of these. 11. Building a backyard swimming pool consists of nine major activities. The activities and their immediate predecessors are shown. Develop the project network. For question number 12, you need to refer to question number 11. Also the first picture is for #11 and second picture(image) is for #12 12. Assume that the activity time estimates (in days) for the swimming pool construction project in Problem 11 are as follows: a. What are the critical activities? b. What is the expected time to complete the project? c. Based only on the critical path, what is the estimated probability that the project can be completed in 25 or fewer days?