A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according ?to longest task time first, What will the estimated idle time in minutes for FIRST workstation

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
icon
Concept explainers
Topic Video
Question
A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total
of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and
2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence
rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be
completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating
task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is
completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according
?to longest task time first, What will the estimated idle time in minutes for FIRST workstation
0.06 .a O
None is the correct anser
.b O
0.09
.c O
1.00 .d O
1.85 .e O
ace
近
Transcribed Image Text:A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed. Finally, task G can start only once task F is completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according ?to longest task time first, What will the estimated idle time in minutes for FIRST workstation 0.06 .a O None is the correct anser .b O 0.09 .c O 1.00 .d O 1.85 .e O ace 近
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,