Mega Corp. is designing a product layout for a new electronic product. They plan to use this production line 8 hours a day in order to meet forecasted demand of 700 units per day. For output to meet the forecasted demand, the cycle time for this production line should be? Round-up to the nearest integer Select one: a. 64 seconds b. 42 seconds c. 32 seconds d. 38 seconds

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
icon
Concept explainers
Topic Video
Question
Mega Corp. is designing a product layout for a new electronic product. They plan to use this production line 8 hours a
day in order to meet forecasted demand of 700 units per day. For output to meet the forecasted demand, the cycle
time for this production line should be? Round-up to the nearest integer
Select one:
a. 64 seconds
b. 42 seconds
c. 32 seconds
d. 38 seconds
Transcribed Image Text:Mega Corp. is designing a product layout for a new electronic product. They plan to use this production line 8 hours a day in order to meet forecasted demand of 700 units per day. For output to meet the forecasted demand, the cycle time for this production line should be? Round-up to the nearest integer Select one: a. 64 seconds b. 42 seconds c. 32 seconds d. 38 seconds
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,