b) Given the demand, the cycle time for the production of the new train set =
Q: A manutacturer is designing a product layout for a new product production. It plans to use a…
A: Assembly line balancing is the process of making a decision regarding assigning the task to the…
Q: The City Commission of Nashville has decided to build a botanical garden and picnic area in the…
A: Gantt chart is a visual representation of a network diagram which helps to identify the starting and…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given- Available time per day = 8 hours × 60 minutes = 480…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: A local toy maker uses a manufacturing line running eight hours a day that produces a toy which…
A: Following is the network diagram:
Q: linois Furniture, Inc, produces all types of office furniture. The "Executive Secretary" is a chair…
A: Note: - As it is specified to answer only subpart e, we will answer subpart e here. Given data is
Q: A company is designing a product layout for a new product. It plans to use this production line…
A: The last task performed at the second workstation
Q: GardinIT performs home gardening jobs. The required jobs are shown in the following table Job…
A: Given data, Jobs Preparing Area Planting days R 3 2 S 1 3 T 4 5 U 8 5 V 6 4 W 4…
Q: The standard time to perform the regular work cycle for a certain manual operation is 4 mins. In…
A: Standard time = 4 mins Irregular work element's normal time = 2.25 mins PFD allowance = 15% Normal…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given that: Task Duration (in mins) A 2.73 B 2.01 C 2.13 D 2 E 2.61 F 2.71 G 2.95
Q: The Action Toy Company has decided to manufacture a new train set, the production of which is broken…
A: Given- Available time over 40 hours work week = 40 hours×3600 seconds per hour…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using:Cycle time = Available time / Desired output
Q: Cycle time is the longest cycle time allowed for each workstation in a line balancing to produce one…
A: The concept used here is understanding manufacturing times such cycle time, lead time, takt time…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Required cycle time = Available time / No. of units to produce =…
Q: For a given process, the raw processing time is 102 sec, the bottleneck cycle time is 20 sec/item,…
A: Given, Raw processing time = 102 seconds. Bottleneck cycle time= 20 seconds per items. Work in…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: A local toy manufacturer is using a production line that runs hours per day and produces a toy that…
A: The answer is as follows:
Q: The times required to complete each of eight jobs in a two-machine flow shop are shown in thetable…
A: A)
Q: This exercise only contains parts b, c, d, e, and f. b) Given the demand, the cycle time for the…
A:
Q: he Action Toy Company has decided to manufacture a new train set, the production of which is broken…
A: Note, Since you have posted multiple parts of the question in the same questions, we will be…
Q: If we were to coin the phrase “dual constrained” relative to the resources being scheduled, we would…
A: The manager is the person who is accountable for all the things that are happening in the…
Q: WorkPro is a small manufacturer. It uses a job process for production. The following sample of jobs…
A: "Since you have asked multiple questions, we will solve the first one for you. To get remaining…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Cycle time = Available time / Desired output
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given - A local toy manufacturer is using a production line that runs 8 hours per day and produces a…
Q: Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that…
A: Required cycle time = Available time / No. of units to produce =…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: The answer is below:
Q: The Action Toy Company has decided to manufacture a new train set, the production of which is broken…
A: Cycle time is the proportion between Total available production time and total required demand. it…
Q: You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units…
A: Given data is,
Q: Sue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro…
A: Given information Activity Duration Immediate predecessors A 10 B 12 A C 8 A, B D…
Q: An order for 100 of a product is processed on operation A and operation B. The setuptime on A is 50…
A:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: The Action Toy Company has decided to manufacture a new train set, the production of which is broken…
A: Given data: Demand = 4600 units workweek = 40 hours As per the information Precedence diagram is:
Q: Suppose we have a school building project. According to the breakdown structure, twenty work…
A: Suppose we've got a faculty building project. in keeping with the breakdown structure, twenty work…
Q: A manufacturer needs to produce 300 coffee pots per 8 hour day. The discrete tasks required to…
A:
Q: What happens to the non-bottleneck resources when the bottleneck resource is maximized?
A: Bottleneck resources generally refer to those resources whose capacity is similar or equal to or…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Working hour = 8 hours per day The total task to perform =7 task Daily demand= 100 toys Total Task…
Q: Assuming that no parallel activities are to be employed (e.g., two lines), the output selected for…
A: Cycle time is the maximum time required for manufacturing a product. Cycle time depends on the…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A:
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: What is the outcome when a bottleneck resources is augmented with more capacity? Will throughput…
A: The assets that need a lot of time working in the supply chain for a particular demand are…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: This problem can be solved using: Minimum no. of station = Total task time / Cycle time Cycle time =…
Q: Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: The table below shows the time for each work element in an manual assembly process, along with the…
A: Given that: Work element A B C D E F G H I J Time (minutes) 0.7 0.4 0.2 0.3 0.5 0.4 0.6 0.5 0.3…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Given Data: Task Time taken A 2.73 B 2.01 C 2.13 D 2.0 E 2.61…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: The answer is as follows:
Q: A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy…
A: Demand is the total quantity of products and services for which the consumers are willing to pay…
Task
|
Performance Time
(seconds)
|
Predecessors
|
|
A
|
24
|
|
−
|
B
|
30
|
|
A
|
C
|
12
|
|
A
|
D
|
15
|
|
A
|
E
|
12
|
|
B, C
|
F
|
30
|
|
D, E
|
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- A local toy manufacturer is using a production line that runs hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 201 01, 2.13, 2.0, 2.61 2.71. and 2.95 minutes for A, BC, D , and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task and task each require task B to be completed. Task must be completed prior to stating task E. Task F needs both task Dand task E to be completed. Finally, task G can start only once task Fis completed . What should be the calculated cycle time in minutes?A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed . The daily demand is 100 toys. Times of the tasks are 2.73,2.01 1,2.13,2.0,2.61,2. 2.71 , and 2.95 minutes for A, B, C, D, E, F , and G , respectively . However , due to the nature of the product there are precedence rules that must be observed . Such that Task A does not need any predecessors ; task B requires task A to be completed . To start task C and task D, each require task B to be completed . Task C must be completed prior to stating task E. Task F needs both task D and task E to be completed . Finally , task G can start only once task F is completed . What should be the calculated cycle time in minutes ? a. 0.9 b. 4.5 c. None is correct d. 4.8 e. 4.4For a given process, the raw processing time is 102 sec, the bottleneck cycle time is 20 sec/item, and the WIP is 6 items. The expected lead-time (LT) is ____ seconds. Enter a whole number answer.
- A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are: Task Time(secs) ImmediatePredecessor u 30 none v 30 u w 6 u x 12 w y 54 x z 30 v,y If the company wants the output rate to be equal to demand, what is the last task performed at the second workstation if tasks are assigned in order of the most following tasks?Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performied. The daily demand is 150 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires taskA to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed. Finally, task G can start only once taskFis completed.What is the minimum number of workstations needed?A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed . The daily demand is 100 toys . Times of the tasks are 2.73,2.01 ,2.13,2.0,2.61,2.71 and 2.95 minutes for A,B,C,D,E,F, and G, respectively . However , due to the nature of the product there are precedencerules that must be observed . Such that Task A does not need any predecessors ; task B requires task A to becompleted . To start task C and task Deach require task B to be completed . Task must be completed prior to stating task E. Task F needs both task and task E to be completed . Finally , task G can start only once task F is completed . Given we apply the most remaining tasks rule for balancing the assembly line , with ties broken according to longesttask time first , the tasks that will be assigned to the THIRD workstation are a. D and F b . None is the correct answer c. D only d. E only e. B, C , and D
- A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73,2.01,2.13,2.0.2.61,2.71 , and 2.95 minutes for A A,B,C,D,E,F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task C and task D. each require task B to be completed. Task must be completed prior to stating task E. Task F needs both task D and task Eto be completedFinally, task G can start only once task Fis completed.Given we apply the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the THIRD workstation areAssuming that no parallel activities are to be employed (e.g., two lines), the output selected for the line must fall in the range of 192 units per day to 480 units per day. As a general rule, the cycle time is determined by the desired output; that is, a desired output rate is selected, and the cycle time is computed. If the cycle time does not fall between the maximum and minimum bounds, the desired output rate must be revised.Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01 201 2.13, 2.0, 2.61, 2.71 , and 2.95 minutes for A,B,C,D,E,F, and respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task Adoes not need any predecessorsB requires task A to completed. To start task C and task Deach require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed. Finally, task G can start only once task Fis completed.Given we apply the most remaining tasks rule for balancing the assembly line with ties broken according to longest task time firstthe tasks that will be assigned to the SECOND workstation are
- A process is accomplished in 4 sequential steps- S1, S2, S3 and S4. The lead times (in minutes) and the number of resources for every step are indicated in the table below. Sub - Process Time (min) No of resources S1 12 1 S2 8 1 S3 16 1 S4 10 1 Assuming infinite customer demand, what is the utilization of process S1? (answer in decimals).An order for 100 of a product is processed on operation A and operation B. The setuptime on A is 50 minutes, and the run time per piece is 9 minutes. The setup time onB is 30 minutes, and the run time is 6 minutes per piece. It takes 20 minutes to movea lot between A and B. Since this is a rush order, it is given top priority (president’sedict) and is run as soon as it arrives at either workstation.It is decided to overlap the two operations and to split the lot of 100 into two lotsof 60 and 40. When the first lot is finished on operation A, it is moved to operation Bwhere it is set up and run. Meanwhile, operation A completes the balance of the 100units (40) and sends the units over to operation B. These 40 units should arrive asoperation B is completing the first batch of 60; thus, operation B can continue withoutinterruption until all 100 are completed.a. Calculate the total manufacturing lead time for operation A and for B withoutoverlapping.b. Calculate the manufacturing lead time…A local toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed . The daily demand is 120 toys. Times of the tasks are 2.73,2.01 1, 2.13, 2.0, 2.61, 2.71 , and 2.95 minutes for A ,B,C,D,E,F, , and G, respectively . However, due to the nature of product there are precedence rules that must be observed . Such that Task A does not need any predecessors ; task B requires task be completed. To start task C and task D, each require task B to be completed . Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed . Finally, task G can start only once task F is completed . What is the minimum number of workstations needed? a. 4 b. 5 c. 6 d. None of them e. 8