a. Construct AON diagram for the following data. b. Identify critical path. c. Conduct CPM analysis by identifying ES, EF, LS, LF, Slack time to confirm the critical path.
Q: 1. Prepare the Activity Node Diagram and identify the Critical Path 2. Prepare Gantt Chart Thankss
A: Given data is
Q: . Draw a precedence diagram using AOA. b. Find the critical path. c. Determine the expected length…
A: Below is the solution:-
Q: What characteristic(s) of the critical path times makes them critical? What two factors are compared…
A: Critical path activities are those that, if delayed, will cause the project's completion to be…
Q: Activity Duration Predecessors A 3 | A 7 D 3 В, С E F D G H E, F, G 5.
A: A project activity network is a graphical depiction showing the sequence for the completion of a…
Q: a. Prepare a work breakdown structure showing tasks, durations, and predecessor tasks. b. Construct…
A: A - 2 B A 2 C A 1 D A 5 E B, C 2 F D, E 5 G F 1 Solution: a) Activity Description…
Q: - Find slack time using cpm approach?
A: Given that: Activities a m b A 3 6 8 B 2 4 4 C 1 2 3 D 6 7 8 E 2 4 6 F 6 10 14 G 3…
Q: 1. Which tasks can be simultaneously started immediately with Task U? 2. What is the earliest finish…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: It is necessary to provide an explanation to the audience on the objective of a Work Breakdown…
A: Work Breakdown Structure is used in projects to break down the whole project into small parts. It…
Q: 1. Jim's team has completed the WBS and WBS dictionary and the stakeholders have approved the…
A: The correct option is "d", which is "DECOMPOSITION". Decomposition would involve dividing the…
Q: Explain : Activity time, Gantt chart, Critical path, Slack time, Crashing.
A: PART A: - Activity period may be a noun that represents the particular amount of your time that…
Q: From a project resource management context, discuss the significance of a Work Breakdown Structure…
A: A work breakdown structure is a project management approach for completing a difficult, multi-step…
Q: d. How long the program is expected to finish? e. Determine the slack time for each activity using…
A: given,
Q: project. She analyzes the tasks involved in making the app and produces the PERT chart umbers…
A: This various paths are the possible ways of making the health app for the company who wants to enter…
Q: Q:2 Draw AOA and AON network diagrams and gantt chart for the project, calculate TE for each…
A: Below is the solution:-
Q: Activity Description Duration (weeks) Precedent A Team Formation 1 B Project Planning 3 A Site…
A:
Q: (Question 23) As a process analyst – you are requested to – Map the above project(refer to case…
A: While all organizations, irrespective of size, have processes that can be an endless supply, many of…
Q: EQUIRED: a. The PERT Network, identifying the critical path and including slack times.
A: We are only allowed to do one question at a time. Please post rest questions again to get answer.
Q: A. Instruction: 1. Construct both AOA diagram for the following data. a) b) Identify the paths and…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: a. Prepare a work breakdown structure showing tasks, durations, and predecessor tasks, with explain…
A: The task breakdown structure, durations, and predecessor task are shown below.
Q: [6 marks] Carefully draw an AON network diagram for the project, and perform both the forward and…
A: THE ANSWER IS AS BELOW:
Q: Scope control for improvement project?
A: It defines project scope as the work that should be done to convey an item with the predefined…
Q: Describe different ways to develop a WBS (Work Breakdown Structure) and explain why it is often so…
A: The Work Breakdown Structure is a method for representing the scope of a project or a product. WBS…
Q: An assembly is to be made from two parts X and Y. Both parts must be turned on a lathe Y must be…
A: Activity Immediate Predecessors A - B A C A D B E B, C F E G D, F H G Edge and…
Q: Software Management 1. Let's assume that you are a project manager and are assigned to develop a…
A: Software management in a project refers to the planning, resource allocation, scheduling and…
Q: a) Briefly describe what is meant by the term 'Work Breakdown Structure' (WBS), when applied to…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: days. Carl's team should be able to complete the project in
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: Instruction: a. Construct AON diagram for the following data. b. Identify critical path c. Conduct…
A: Find the Given details below: Activity ImmediatePredecessors Time Estimates (Days) A - 2 B -…
Q: Make a list of the tasks that is necessary for Management Trainee Officer job in private banks.…
A: Below is the solution:-
Q: a) Construct the network and find the duration. b) Find critical path and slacks for all…
A: Below is the solution:-
Q: Q3: The table below includes information about four jobs and three work centers. Please use the…
A: Find the Given details below: Given details: Job Work Center 1 A/2, B/1, C/4 2 C/4, A/2 3…
Q: 1. Design a chart base for the given activities Activity Description Immediate Predecessors A Buy…
A: A set of activities is given {A, B, C, D}. Additionally, the depiction of every activity is given.…
Q: Activity A B C E F G H Preceded By ** A B,C D E BC F.G Expected Time Direct Cost Regular Crash…
A:
Q: REQUIRED: a. Calculate t,(expected time) for each activity. For each activity, the estimates are to,…
A: Answer is as below
Q: Which of the following processes produces a work breakdown structure as an output? A. Create WBS B.…
A: Note- Hi! Thank you for the question As per the honour code, We’ll answer the first question since…
Q: b) Provide a brief explanation of the main difference between a Work Breakdown Structure and Network…
A: A project network diagram is shown as a chart with a sequence of boxes and arrows.
Q: what is the difference between work package and wbs?
A: Introduction of work package A work package is a group of related tasks within a project. Because…
Q: Instruction: a. Construct AON diagram for the following data. b. Identify critical path. c. Conduct…
A: This question is related to the topic-Project Management and this topic falls under the Operations…
Q: Explain work breakdown structure (WBS)?
A: Work breakdown structure (WBS) is a tool is used to understand and align the work element of a…
Q: Power Builders Inc. is planning for an upcoming job with a large client. They have listed the…
A: Given data is
Q: Kelly Melford and her team are working on redesigning a client's home. The client requested Kelly…
A:
Q: Task Follow Task Weeks (Duration) Task Description Manning Level A Start 1.0 Site Cleaning 3 Obtain…
A: Given data is
Q: Title A: Practical HRM in Aviation Objective/s: i. To gain insight of the HRM system of world’s…
A: Indigo is one of the leading and growing airlines and it is an Indian low-cost airline that is…
Q: Immediate Activity Description Time (days) Predecessors Excavate Lay Foundation Begin Initial…
A:
Q: a) Prepare the Activity Node Diagram and identify the Critical Path
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: 7. Develop a WBS for a project in which you are going to build a bicycle. Try to identify all of the…
A: A Work Breakdown Structure (WBS) is a various leveled framework of the jobs needed to finish a…
Q: Which among the following is not an activity? a. Machine set up b. Placing purchase order c. After…
A: Before answering the question, let us understand what each of them mean. Machine set up This is the…
Instruction:
a. Construct AON diagram for the following data.
b. Identify critical path.
c. Conduct CPM analysis by identifying ES, EF, LS, LF, Slack time to confirm the critical path.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 7 images
- Management Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (A) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)The expected number of days to completion for a different project is E(x) = 3.32 The variance of days to completion is var(x) = 1.22 The project cost involves A fixed cost (in thousands of dollars) of FC = $83.783 A variable cost for each day taken to complete the project ($000) VC = $9.774 15 The variance of project cost is ________. a 116.548 b 113.153 c 109.858 d 106.658The expected number of days to completion for a different project is E(x) = 3.32 The variance of days to completion is var(x) = 1.22 The project cost involves A fixed cost (in thousands of dollars) of FC = $83.783 A variable cost for each day taken to complete the project ($000) VC = $9.774 14 The expected value of the project cost is $_______ thousand. a 109.364 b 112.746 c 116.233 d 119.828
- Management Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)The expected number of days to completion for a different project is E(x) = 3.32 The variance of days to completion is var(x) = 1.22 The project cost involves A fixed cost (in thousands of dollars) of FC = $83.783 A variable cost for each day taken to complete the project ($000) VC = $9.774 16 The standard deviation of the project cost is $________. a 13.041 b 12.245 c 11.497 d 10.796I only need help with D,E,F ONLY PLEASE!! Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity C. Activity B is connected to activity D. Activity C…
- Hi, I need help answering the last question. Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed. Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A 5 3 $800 $1,200 - B 6 5 $300 $450 - C 6 5 $550 $775 - D 3 2 $750 $950 A E 6 3 $1,350 $2,250 C F 5 3 $675 $875 B What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.)I also know answer is d, but please explain each and every option why other option are incorrect too. Which of the following statements regarding PERT analysis is true? Each activity has two estimates of its duration. Project variance is the sum of all activity variances. Project standard deviation is the sum of all critical activity standard deviations. Only critical activities contribute to the project variance. none of these is true.A project’s budget was originally $100,000. The CPI is 1.2, and the project is already 40% along. Assuming the project variances are typical, how much more money will you need to complete the project? $50,000 $43,000 $150,000 $83,000
- Limbo Technologies has embarked on another project that has an estimated completion time of 40 weeks and a standard deviation of 5 weeks. It is estimated that the project completion time is normally distributed. i)What is the probability of finishing the project in 38 weeks or less? ii)The due date for the project is set so that there is a 90% chance that it will finish by this date. What is the due duration? ACTIVITY PREDECESSOR NORMAL TIME (WEEKS) CRASH TIME (WEEKS) NORMAL COST ($) CRASH COST ($) A - 4 2 1000 1600 B - 6 3 3000 3500 C A 3 1 2500 3000 D A,B 6 5 1500 1850 E D 4 2 3500 4200 F C 4 3 2250 3000 G D 3 2 1900 2500 H F,G,E 2 1 400 500Answer all. What are the critical activities? What is the expected project duration? calculate the variance of the project What is the standard deviation (te) for the project? Suppose that management allotted 13-unit time for the project. What is the probability that we will meet the 13-unit time deadline? If management wants to have a 0.99 probability of meeting the time, what should be the scheduled project duration?Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the 13th day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedence relationships are given in Table. Electric Motor Project Data Activity Normal Time(days) Normal Cost ($) Crash Time (days) Crash Cost ($) ImmediatePredecessor(s) A B C D E F G H 4 7 5 6 3 11 4 3 1000 1400 2000 1200 900 2500 800 300 3 4 4 5 2 6 3 1 1300 1200 2700 1400 1100 3750 1450 500 None None None A B C D,E F,G a. Draw the project network diagram.b. What completion date would you recommend?