a. Draw a network diagram (activity on node), compute the earliest start and finish times of each task using most likely values. b. Compute the latest start and finish times of each task fill the rest of the values in a table format as follows: Activity Earliest Start Earliest Finish Latest Start Latest Finish Slack Is critical? c. If the project is finished within 27 weeks of its start, the project manager will receive a bonus of 500$. Find the probability of getting the bonus.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Activity
A
D
E
H
F
G
B
I
J
4. A construction company planned for a new project and represented the tasks of the project as a
list of immediate predecessors, estimated duration (best, most likely, worst) as follows:
Estimated duration (best-most likely-worst) in weeks
K
с
M
N
O
End
immediate
predecessors
a.
A
D
E
A
FL
B
I
J
C
M
N
H,G,K,O
2-4-6
6-8-10
7-9-12
2-3-5
3-4-8
Earliest
Start
5-7-9
2-2-3
2-3-6
3-4-5
4-5-8
5-8-12
1-1-1
Draw a network diagram (activity on node), compute the earliest start and finish times of each
task using most likely values.
b. Compute the latest start and finish times of each task fill the rest of the values in a table
format as follows:
Activity
6-7-11
8-9-13
Earliest
Finish
Latest
Start
Latest
Finish
Slack
Is critical?
c. If the project is finished within 27 weeks of its start, the project manager will receive a bonus
of 500$. Find the probability of getting the bonus.
Transcribed Image Text:Activity A D E H F G B I J 4. A construction company planned for a new project and represented the tasks of the project as a list of immediate predecessors, estimated duration (best, most likely, worst) as follows: Estimated duration (best-most likely-worst) in weeks K с M N O End immediate predecessors a. A D E A FL B I J C M N H,G,K,O 2-4-6 6-8-10 7-9-12 2-3-5 3-4-8 Earliest Start 5-7-9 2-2-3 2-3-6 3-4-5 4-5-8 5-8-12 1-1-1 Draw a network diagram (activity on node), compute the earliest start and finish times of each task using most likely values. b. Compute the latest start and finish times of each task fill the rest of the values in a table format as follows: Activity 6-7-11 8-9-13 Earliest Finish Latest Start Latest Finish Slack Is critical? c. If the project is finished within 27 weeks of its start, the project manager will receive a bonus of 500$. Find the probability of getting the bonus.
Expert Solution
steps

Step by step

Solved in 5 steps with 8 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.