a. Draw a work package schedule showing all activities, the critical path and the overall estimated work package duration. b. Fully crash the critical path working from the lowest cost per unit time saved activity to the highest cost per unit time saved activity. Show the fully crashed work package as a schedule and give the revised work package duration. c. Compare and contrast critical path method (CPM) based and programme evaluation and review technique (PERT) based project planning approaches and examine the likely strengths and weak- nesses of each approach in relation to the proiect described in the case study

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
a. Draw a work package schedule showing all activities, the critical path and
the overall estimated work package duration.
b.Fully crash the critical path working from the lowest cost per unit time
saved activity to the highest cost per unit time saved activity. Show the
fully crashed work package as a schedule and give the revised work
package duration.
Compare and contrast critical path method (CPM) based and
programme evaluation and review technique (PERT) based project
planning approaches and examine the likely strengths and weak- nesses
of each approach in relation to the project described in the case study
C.
Transcribed Image Text:a. Draw a work package schedule showing all activities, the critical path and the overall estimated work package duration. b.Fully crash the critical path working from the lowest cost per unit time saved activity to the highest cost per unit time saved activity. Show the fully crashed work package as a schedule and give the revised work package duration. Compare and contrast critical path method (CPM) based and programme evaluation and review technique (PERT) based project planning approaches and examine the likely strengths and weak- nesses of each approach in relation to the project described in the case study C.
Table I: Normal and crash activity duration and estimated cost values
Activity
Normal dura-
Crash cost (£)
Normal cost (£) Crash duration
(weeks)
tion (weeks)
A-B
4
20 000
3
50 000
А-К
19
250 000
14
375 000
В-С
3
35 000
2
70 000
B-D
30 000
30 000
В-Е
3
40 000
75 000
10 000
15 000
C-H
50 000
C-I
15 000
D-I
25 000
25 000
E-F
4
40 000
3
60 000
E-G
2
60 000
2
90 000
F-K
5
50 000
3
85 000
G-K
80 000
80 000
H-J
70 000
70 000
3
30 000
100 000
J-L
2
15 000
45 000
K-L
3
20 000
2
40 000
L-M
4
30 000
3
35 000
M-N
5
100 000
4
T10 000
Transcribed Image Text:Table I: Normal and crash activity duration and estimated cost values Activity Normal dura- Crash cost (£) Normal cost (£) Crash duration (weeks) tion (weeks) A-B 4 20 000 3 50 000 А-К 19 250 000 14 375 000 В-С 3 35 000 2 70 000 B-D 30 000 30 000 В-Е 3 40 000 75 000 10 000 15 000 C-H 50 000 C-I 15 000 D-I 25 000 25 000 E-F 4 40 000 3 60 000 E-G 2 60 000 2 90 000 F-K 5 50 000 3 85 000 G-K 80 000 80 000 H-J 70 000 70 000 3 30 000 100 000 J-L 2 15 000 45 000 K-L 3 20 000 2 40 000 L-M 4 30 000 3 35 000 M-N 5 100 000 4 T10 000
Expert Solution
steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.