%24 Pina Colada Manufacturing provided the following information about its standard costing system for 2022: Standard Data Actual Data Materials 10 Ibs. @ S4 per Ibs. Produced 4,120 units Labor 3 hrs. @$21 perhr. Materials purchased 51,230 lbs. for$220,289 Budgeted production 3,620 units Materials used 42,200 lbs. Labor worked 11,340 hrs.costing $226,800 () Determine the amount of the materials price variance. Identify whetherthe variance is favorable or unfavorable. Materials Price Variance eTextbook and Media Sarefor Later Attempts: 0 of 3 used Submit Answer (b) The parts of this question must be completed in order. This part will be available when you complete the part above.

Accounting
27th Edition
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Chapter20: Process Cost Systems
Section: Chapter Questions
Problem 20.3CP: Communication Jamarcus Bradshaw, plant, manager of Georgia Paper Company's papermaking mill, was...
icon
Related questions
Question

Unit VIII question 3 part a 

%24
Pina Colada Manufacturing provided the following information about its standard costing system for 2022:
Standard Data
Actual Data
Materials
10 Ibs. @ S4 per Ibs.
Produced
4,120 units
Labor
3 hrs. @$21 perhr.
Materials purchased
51,230 lbs. for$220,289
Budgeted production
3,620 units
Materials used
42,200 lbs.
Labor worked
11,340 hrs.costing $226,800
()
Determine the amount of the materials price variance. Identify whetherthe variance is favorable or unfavorable.
Materials Price Variance
eTextbook and Media
Sarefor Later
Attempts: 0 of 3 used
Submit Answer
(b)
The parts of this question must be completed in order. This part will be available when you complete the part above.
Transcribed Image Text:%24 Pina Colada Manufacturing provided the following information about its standard costing system for 2022: Standard Data Actual Data Materials 10 Ibs. @ S4 per Ibs. Produced 4,120 units Labor 3 hrs. @$21 perhr. Materials purchased 51,230 lbs. for$220,289 Budgeted production 3,620 units Materials used 42,200 lbs. Labor worked 11,340 hrs.costing $226,800 () Determine the amount of the materials price variance. Identify whetherthe variance is favorable or unfavorable. Materials Price Variance eTextbook and Media Sarefor Later Attempts: 0 of 3 used Submit Answer (b) The parts of this question must be completed in order. This part will be available when you complete the part above.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Segment Reporting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,