Analyze the following set of data in the table below. Is the process in control? Is it capable? The target is 66 and the customer requirements are 60 and 72 respectively. A defect cost $5 to rework. The process is in control. Average Range 64 9 Sample 4/5 67 4/6 65 4/765 4/8 65 66 67 67 66 66 63 4/96S回的663664 410 67 66 69 65 65 67 65 621 61 60 68 63 65 66 66 4 063 65 7 85 7 66 3 66 4 65 9 65 6 4. 41166166 6716766167 6 412 6716706164(64 67 66 41367 656765 66 66 63 414 66 66 7o 65 66 64 66 62 65 416 68161 66 69 621 68 4/17 64 66 66 68 66 65 68 4/18 66 63 66 71 65 64 67 3. 61 66.1 65 7 66 3 415 69 65 64 67 68 68 66.1 66 0 4/19 67 69 63 67 65 62 65 65.4 65.9 66.1 66.3 66.1 4/2064 66 6468 66] 66 67 4/21 67 68 65 65 65 67 66 67 41 3 4/22 66 68 66 66 68 63 66 4/23 65 65 66 70 67 64 4/24 66 68]l 63 66 67 65 65 65.7 65.7 66.3 65.3 5. 4/25 67 65 66 64 67 64 67 4/26 66 6865 67 64 70 64 64 4/27 63 66 68 63 68 65 4/28 66 65 68 69 68 66 65 4/29 68 66 67 67 69 66 67 66.7 4. 67.1 Ag- 66.01 4.88 False True

Glencoe Algebra 1, Student Edition, 9780079039897, 0079039898, 2018
18th Edition
ISBN:9780079039897
Author:Carter
Publisher:Carter
Chapter10: Statistics
Section10.5: Comparing Sets Of Data
Problem 14PPS
icon
Related questions
Question

8

Analyze the following set of data in the table below. Is the process in control? Is it capable? The
target is 66 and the customer requirements are 60 and 72 respectively. A defect cost $5 to rework.
The process is in control.
Average Range
64 9
Sample
4/5 67
4/6 65
4/765
4/8 65 66 67 67 66 66 63
4/96S回的6636664
410 67 66 69 65 65 67 65
65 621 61 60
67 6063 6
66 66 69] 65 66
66 4
66 3
65.7
65 7
66 3
66 4
65 9
51
4.
411 66 66 671671661 67 66
412 67 67 66 64 64 67 66
413 67 6567 65 66 66 63
404 66 66 70 65 66 64 66
62 65
68
3.
65 6
66.1
65 7
66 3
66.1
4.
61
415 69 65 64 67 68
416 68]61 66 69 621 68
4/17 64 66 66 68 66 65 68
4/18 66 63 66 71 65 64 67
4/19 67 69 63 67 65 62
66 0
65
65.4
65.9
66.1
66.3
66.1
4/20 64 66 64 68 6] 66
67
41
4/21 67 68 65 65 65 67 66
4/22 66 68 66 66 68 63
67
4/23 65 65 66 70 67 64
66
4/24 66 66]l 63 66 67 65
425 67 65 66 64 67 64 67
65
65.7
65.7
66 3
65.3
4/26 66 6865 67 64 70
64
4/27 63 66 68 63 68
65
64
65
4/28 66 65|l 68 6968] 66
4/29 68 66 67 67 69 66 67
66.7
4.
67.1
Ag-
66.01
4.88
False
True
Transcribed Image Text:Analyze the following set of data in the table below. Is the process in control? Is it capable? The target is 66 and the customer requirements are 60 and 72 respectively. A defect cost $5 to rework. The process is in control. Average Range 64 9 Sample 4/5 67 4/6 65 4/765 4/8 65 66 67 67 66 66 63 4/96S回的6636664 410 67 66 69 65 65 67 65 65 621 61 60 67 6063 6 66 66 69] 65 66 66 4 66 3 65.7 65 7 66 3 66 4 65 9 51 4. 411 66 66 671671661 67 66 412 67 67 66 64 64 67 66 413 67 6567 65 66 66 63 404 66 66 70 65 66 64 66 62 65 68 3. 65 6 66.1 65 7 66 3 66.1 4. 61 415 69 65 64 67 68 416 68]61 66 69 621 68 4/17 64 66 66 68 66 65 68 4/18 66 63 66 71 65 64 67 4/19 67 69 63 67 65 62 66 0 65 65.4 65.9 66.1 66.3 66.1 4/20 64 66 64 68 6] 66 67 41 4/21 67 68 65 65 65 67 66 4/22 66 68 66 66 68 63 67 4/23 65 65 66 70 67 64 66 4/24 66 66]l 63 66 67 65 425 67 65 66 64 67 64 67 65 65.7 65.7 66 3 65.3 4/26 66 6865 67 64 70 64 4/27 63 66 68 63 68 65 64 65 4/28 66 65|l 68 6968] 66 4/29 68 66 67 67 69 66 67 66.7 4. 67.1 Ag- 66.01 4.88 False True
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer