Below is information related to: historical average processing times for Products A and B historical percentage of work center load required to produce Produdcts A and B routing and standard times to produce Product B • the product structure for Product B • a MPS covering 3 periods for Products A and B. MPS in Units End Product 2 Processing Time A 50 45 25 Historical % End Product Hours/Unit wC B. 30 25 30 100 40% A 0.80 200 50% в 1.6 300 10% Routing and Standard Time Data End Product Lot Size Work Center Set Up (Hrs) Run Time/Unit (Hrs) Hrs/Unit B 40 100 1 1.25 D (3 required) D 50 200 0.07 100 200 0.08 F 100 300 0.04 (2 required) A. Develp a rough cut capacity plan for the three work centers based on historical factors. Please fill in the table below with your final calculations. Show your work in the space belov Historical Total Work Center Percentage 1 2 3 Hours 100 200 300 Total Required Capacity Show any work here:

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
icon
Concept explainers
Topic Video
Question

Question is attached 

Below is information related to:
historical average processing times for Products A and B
historical percentage of work center load required to produce Produdcts A and B
routing and standard times to produce Product B
• the product structure for Product B
• a MPS covering 3 periods for Products A and B.
MPS in Units
End Product
2
Processing Time
A
50
45
25
Historical %
End Product Hours/Unit
wC
B.
30
25
30
100
40%
A
0.80
200
50%
в
1.6
300
10%
Routing and Standard Time Data
End Product Lot Size Work Center Set Up (Hrs) Run Time/Unit (Hrs) Hrs/Unit
B
40
100
1
1.25
D
(3 required)
D
50
200
0.07
100
200
0.08
F
100
300
0.04
(2 required)
A. Develp a rough cut capacity plan for the three work centers based on historical
factors. Please fill in the table below with your final calculations. Show your work
in the space belov
Historical
Total
Work Center Percentage
1
2
3
Hours
100
200
300
Total Required Capacity
Show any work here:
Transcribed Image Text:Below is information related to: historical average processing times for Products A and B historical percentage of work center load required to produce Produdcts A and B routing and standard times to produce Product B • the product structure for Product B • a MPS covering 3 periods for Products A and B. MPS in Units End Product 2 Processing Time A 50 45 25 Historical % End Product Hours/Unit wC B. 30 25 30 100 40% A 0.80 200 50% в 1.6 300 10% Routing and Standard Time Data End Product Lot Size Work Center Set Up (Hrs) Run Time/Unit (Hrs) Hrs/Unit B 40 100 1 1.25 D (3 required) D 50 200 0.07 100 200 0.08 F 100 300 0.04 (2 required) A. Develp a rough cut capacity plan for the three work centers based on historical factors. Please fill in the table below with your final calculations. Show your work in the space belov Historical Total Work Center Percentage 1 2 3 Hours 100 200 300 Total Required Capacity Show any work here:
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,