calculate takt time in seconds
Q: Calculate the average time required to produce one piece per hour if there are five machines with…
A: Given data is Number of machines = 5 Machining time per piece = 0.6 hours Servicing time per piece =…
Q: What is the process capacity for each machine-operator combination?
A: Introduction: The term Business refers to an exchange of goods and services between the buyer and…
Q: Compute the takt time for a system where the total time per shift is 480 minutes, there is one…
A: Takt time is described as the time or the rate at which products are needed to be manufactured in…
Q: In a company that processes insurance claims, the aver- age flow rate is 10 claims per hour and the…
A: Average number of claims=Average flow rate×Average throughput time=10×6=60 claims Hence, the average…
Q: Explain what is the process of determining expected output in operations
A: Outputs are the results of a task especially following its execution. All submissions for projects…
Q: A production system is as shown below. Station 1 could produce 60 per hour if the rest of the line…
A: The following information is given: The system runs at a rate of 45 per hour (actual output)…
Q: A fleet repair facility has the capacity to repair 800 trucks per month. However, due to scheduled…
A: Design Capacity = 800 trucks Effective Capacity = 600 trucks Actual Output = 400 trucks
Q: Diners are served in a process with two resources. The first resource has a capacity of 0.9 diners…
A: The total labor content is defined as the time sum of all process steps. First Resource Capacity =…
Q: a) Which server is the bottleneck of the process ? b) What is the…
A: Note: As per the guidlnies of Bartleby, only three parts have been answered, for getting answers for…
Q: A manufacturing shop is designed to operate most efficiently at an output of 550 units per day In…
A: A product is a tangible substance that is offered in the market to satisfy the desire or requirement…
Q: Compute the takt time for a service system that intended to perform a standardized service.…
A:
Q: Compute the takt time for a system where the total time per shift is 420 minutes, there is one…
A: The answer is as below:
Q: Instruction: Round your answer to one decimal place. What is the capacity of this process in units…
A: Below is the solution:-
Q: The Swanky Hotel provides room service for its guests. The process for room service begins with a…
A: “Hey, since there are multiple questions posted, we will answer the first three sub-parts. If you…
Q: People are served in a process with two resources. The first resource has a capacity of 1.4 people…
A: Given, Total capacity of resource = Capacity * Number of workers Additional worker = 3+1 = 4 Total…
Q: Dr. Gulakowicz is an orthodontist. She estimates that adding two new chairs will increase fixed…
A: Given data Increased fixed cost = $147000 Expected additional revenue brought by the patient =…
Q: a) Balance this operation using shortest operation time rule and compute the efficiency of the line.…
A: Below is the solution:-
Q: Manager must decide how many machines of a certain type to purchase. Each machine can process 100…
A: The Break-even point is the point at which the production cost and production revenue are equal for…
Q: Williams Performance Co. manufactures sports cars. After making a sale, the salesperson sends thecar…
A: Cost of Direct Labor = 5 cars per day x 5 days of week x 1/2 hr x $ 15 per hour = $187.5 Cost of…
Q: Professor McGonagall teaches a 50-minute class on MWF. She is so efficient, and her students are so…
A: Utilization rate is the rate at which the total time of the resources is fully utilized.
Q: Given the following information, compute the takt time: Total time per shift is 480 minutes per day,…
A: Takt Time = Net time available per day/ Daily demand Daily demand = 80
Q: A newly opened bed-and-breakfast projects the following: Monthly fixed costs Variable cost per…
A: Break-even analysis helps in determining the minimum levels of sales which is required to cover the…
Q: Determine the utilization and the efficiency for each of these situations:b. A furnace repair team…
A: Formula:
Q: Uberya Towing Services repair vehicles that break down at an average 8 vehicles per day. The…
A: Given Average no. Of vehicles that breakdown on a daily basis= 8Average no. Of vehicles, a mechanic…
Q: A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit…
A: Given Number of machines = 2 Production capacity of machine = 4 units/hour.
Q: Calculate Capacity utilization whereas: Design Capacity…
A: The term "utilisation" can be defined as the ratio of actual output to capacity.
Q: What type of process—project, job shop, flow shop, and continuous flow—would most likely be used to…
A: The appropriate process a firm chooses is determined through its process approach, which is the…
Q: The Stylish Hair Salon has three stylists who provideservices to women. After checking in with the…
A: Given Check-in time - 1 minute Customer’s washing, drying, and styling - 25 minutes Payment - 3…
Q: Instruction: Round your answer to three decimal places. What is the capacity of the shop (in units…
A: The answer is as follows:
Q: What are the capacity requirements for the next four years? (Assume that there is no learning.)…
A: Plastic sprinklers:1 machineCapacity 240,0005 workersTotal available capacity = 240,000 * 1 =…
Q: Compute the takt time for a system where the total time per shift is 480 minutes, there is one…
A: Formula:
Q: RideShare offers short-term rentals of vehicles that are kept in small lots in urbanneighborhoods…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: The Dahlia Medical Center has 30 labor rooms, 15 combination labor and delivery rooms, 3 delivery…
A: Room capacity= labor rooms * day period * 24 hours per day Room utilization= Hours * BabiesRoom…
Q: Explain some of the advantages of using the queuing simulator in operations strategy ?
A: Queuing Simulator This involves a branch of mathematics that helps to study how the lines are…
Q: Four employees at a fast-food restaurant each perform one of the four activities in serving a…
A: From the above given information, Greet customer = 2 seconds Taking order = 30 seconds Processing…
Q: What mean process strategy and analysis in operation management? How this information is applied to…
A: This question is related to the topic - Operations/ Business strategy and this topic fall under the…
Q: The Dahlia Medical Center has 30 labor rooms, 15 combination labor and delivery rooms, 3 delivery…
A: Total Capacity of Labor room = 30 rooms x 3 days x 24 hours = 2160 hours Actual Utilization of Labor…
Q: Professor Cook teaches operations management at StateUniversity. She is scheduled to give her class…
A: Given data is Time to grade first exam(a) = 12 minutes Learning rate = 90% Number of students(X) =…
Q: How does seasonal variability in demand affect the flow and waiting time through a process? How…
A: Seasonal variability in demand would affect the flow and waiting time. When there is peak in the…
Q: Describe cycle time as it relates to business processes. Why is it important to the management of…
A: Cycle time - The cycle time can be defined as the total time elapsed during moving a unit of work…
Q: A national restaurant chain has just opened a sit-down location at Chicago’s O’HareInternational…
A: The correct option is option d). Timing. The "to-go" section, also commonly known as the order take…
Q: Apples are prepared in a process with two resources. The first resource has a capacity of 2.1 apples…
A: Number of resources = 2 The capacity of resource 1 = 2.1 Apples pe minute The capacity of resource 2…
Q: It takes a lawyer 120 minutes to serve one customer. Demand is 2 customers per eighthour day. The…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: As the degree of customer contact increases in a service system, what worker skills would be more…
A: Diagnostic skills.
Q: As the assistant manager of a restaurant, how many servers will you need given the following…
A: Given data: Demand = 91 dinners per hour Server target utilization = 90 % = 0.90 Service rate per…
Q: The Stylish Hair Salon has three stylists who provide services to women. After checking in with the…
A: We have, Processing time per customer for receptionist = 1 +3 = 4 minutes per customer Processing…
Q: Dr. Gulakowicz is an orthodontist. She estimates that adding two new chairs will increase fixed…
A: Break even point can be calculated as Break even = (fixed cost)/(selling price - variable cost)
Q: a. An output of 930 units per shift (8.00 hours) is desired for a new processing system. The system…
A: Efficiency is the proportion between total activity time and total station time. Here, we can…
Q: Applications are scanned in a process with two resources. The first resource has a capacity of 21…
A: Given: Process Demand = 16 application/hourThe capacity of 1st resource = 21 Applications/hour The…
Using the following information, calculate takt time in seconds per meal for a fast food restaurant operation.
Hours of operation are from 8 AM to 11 PM.
Customer demand is 2000 meals per day.
NOTE: The practical use of takt time in this case would be to arrange staffing such that meals could be produced and served at takt time.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- Peter’s Paper Clips uses a three-stage production process: cutting wire to prescribed lengths, inner bending, and outer bending. The cutting process can produce at a rate of 220 pieces per minute; inner bending, 230 pieces per minute; and outer bending, 180 pieces per minute. Determine the hourly capacity of each process stage and the number of machines needed to meet an output rate of 14,000 units per hour. Round your answers for the hourly capacity of each process stage to the nearest whole mumber. Round your answers up for the number of machines needed to a whole number. Cutting process: Hourly capacity: pieces/hour Number of machines needed: machine(s) Inner bending: Hourly capacity: pieces/hour Number of machines needed: machine(s) Outer bending: Hourly capacity: pieces/hour Number of machines needed: machine(s)Identify a business operation to which you have access to information and operation to observe the physical space of the business. You can choose area of service such as clinic, restaurant, café, a specific department of a hospital/school or any other relevant business or service setting. Collect information about the capacity of service. Additionally, obtain the average number of customers obtained service for the past 6 months (each month separately). The word limit for this assignment shall be 2500 words. And the assignment shall include the following: Analyze and evaluate literature of capacity management and explain different capacity strategies and capacity constraints. Analyze and evaluate literature on demand management and explain demand management strategies. Also address the changing nature of the market demand for products or services Based on the information you have collected from the organization; discuss about the capacity and demand management strategies they are…A telephone call center uses five customer service representatives (CSRs) during the 8:30 a.m. to 9:00 a.m. time period. The standard service rate is 3.0 minutes per telephone call per CSR. Assuming a target labor utilization rate of 70 percent, how many calls can these five CSRs handle during this half-hour period? Round your answer to the nearest whole number. ?? ________calls
- Dev A restaurant earns $3,950 in sales from 64 guests for Monday’s dinner. Four (4) back-of-the-house employees work the full three-hour dinner shift that night. What is the back-of-the-house team’s sales per person-hour rate? What is the back-of-the-house team’s covers per person-hour rate?A small firm intends to increase the capacity of a bottleneck operation by adding a new machine.Two alternatives, A and B, have been identified, and the associated costs and revenues have beenestimated. Annual fixed costs would be $40,000 for A and $30,000 for B; variable costs per unitwould be $10 for A and $11 for B; and revenue per unit would be $15.b. At what volume of output would the two alternatives yield the same profit?A process currently services an average of 55 customers per day. Observations in recent weeks show that its utilization is about 90 percent, allowing for just a 10 percent capacity cushion. If demand is expected to be 85 percent of the current level in five years and management wants to have a capacity cushion of just 5 percent, what capacity requirement should be planned? Part 2 The needed capacity requirement is enter your response here customers per day. (Enter your response rounded up to the next whole number.)
- A computer repair service has a design capacity of 80 repairs per day. Its effective capacity, however, is 64 repairs per day, and its actual output is 62 repairs per day. The manager would like to increase the number of repairs per day. Critically examine these factors and explain why you would recommend that the manager investigate: quality problems, absenteeism, or scheduling and balancing?A process currently services an average of 61 customers per day. Observations in recent weeks show that its utilization is about 90 percent, allowing for just a 10 percent capacity cushion. If demand is expected to be 70 percent of the current level in five years and management wants to have a capacity cushion of just 5 percent, what capacity requirement should be planned? The needed capacity requirement is nothing customers per day. (Enter your response rounded up to the next whole number.)A process currently services an average of 52 customers per day. Observations in recent weeks show that its utilization is about 90 percent, allowing for just a 10 percent capacity cushion. If demand is expected to be 85 percent of the current level in five years and management wants to have a capacity cushion of just 6 percent, what capacity requirement should be planned?
- A small firm intends to increase the capacity of a bottleneck operation by adding a new machine.Two alternatives, A and B, have been identified, and the associated costs and revenues have beenestimated. Annual fixed costs would be $40,000 for A and $30,000 for B; variable costs per unitwould be $10 for A and $11 for B; and revenue per unit would be $15.c. If expected annual demand is 12,000 units, which alternative would yield the higher profit?McDonalds has a drive-through window and, during peak lunch times, can handle a maximum of 85 cars per hour with one person taking orders, assembling them, and acting as cashier. The average sale per order is $12.00. A proposal has been made to add two additional workers and divide the tasks among the three. One will take orders, the second will assemble them, and the third will act as a cashier. With this system, it is estimated that 120 cars per hour can be serviced. Use productivity arguments to recommend whether or not to change the current system. Hint: Productivity = revenue/labor dollarGeorge has recently joined XYZ Corporation as its vice-president of operations. Within a month of his joining, he started making operational changes in the production process of the department. The lower level workers find it extremely difficult to deal with George’s new ideas and way of thinking. Identify the problem in this case and suggest certain measures to overcome this problem.